Tutorial 1 - Dr. Rob Stephen-Optimising Line Design PDF
Tutorial 1 - Dr. Rob Stephen-Optimising Line Design PDF
• AC LINE DESIGN
• ELECTRICAL CHARACTERISTICS
• MECHANICAL CHARACTERISTICS
• THERMAL RATING
• PLANNERS REQUIREMENTS
• OBJECTIVE INDICATOR
• DC LINE DESIGN
• ELECTRICAL CHARACTERISTICS
• OBJECTIVE INDICATOR
• COST OF LINES
• EXAMPLES OF OPTIMISATION
OPTIMISING LINE
DESIGNS
TUTORIAL FOR TB 638
AC LINE DESIGN
4
LINE MODEL
5
Maximise Power Transfer
• Zs is surge impedance
• SIL is the surge impedance loading
• Reduce L and increase C to maximise transfer
L is series
inductance
C is shunt
capacitance
7
Variation with current
1.14
1.12
1.10
1.08
Rac/Rdc
1.06 Penguin(1+6)
107 mm2
Tcond=80°C
1.04
1.02
1.00
0 100 200 300 400 500 600 700 800
I(A)
1.10
1.08
1.06
Rac/Rdc
800 mm2
Falcon(19+54)
1.04
Tcond=80°C
1.02
1.00
0 1000 2000 3000 4000 5000 6000 7000 8000 I(A)
8
Determination of L
• L is a function of Geometric mean radius (GMR) and Geometric mean Distance
(GMD)
• Larger bundle radius and closer phase spacing gives lower L
9
Determination of C
• To increase capacitance
keep phases closer together.
10
Summary
• SIL (L and C) can be varied by
− varying phase spacing closer is better
− Increasing bundle size larger is better
• Resistance can be improved by
− Varying lay ratios per layer (not practical)
− Different materials
− Homogeneous conductors
11
Corona limitations
• Corona can produce audible noise under certain weather conditions. This is very
difficult to mitigate. It is desirable to avoid corona inception.
− Smaller bundle radius will reduce corona up to a point.
− Wider phase spacing better
− More sub conductor bundles better.
12
AC LINE DESIGN
MECHANICAL CHARACTERISTICS
14
Tower top Geometry
• Tower top geometry design applies to conventional towers with metal surrounded
center phase (tower window) as well as three phases in the same window as is
the case with the cross rope suspension.
• The interaction between the phases as well as the shielding angle for the
conductors needs to be carefully designed to ensure optimal insulation co-
ordination providing the required level of reliability.
AC LINE DESIGN
THERMAL RATING
17
Joule and magnetic heating
• Joule dependent on AC resistance and temperature
• Magnetic heating dependent on current and conductor layers.
18
Solar heating
• Darkness of conductor
• Diameter of conductor
• Solar radiation
19
Convective cooling
• Dependent on
− the conductor diameter (bigger is better)
− Wind speed
− Temperature difference (bigger is better)
− Roughness
20
Templating temperature
• Templating temperature is the conductor temperature at which the height above
ground is in accordance with the OHS act
21
SUMMARY
22
AC LINE DESIGN
PLANNING REQUIREMENTS
24
Conductor size and temp
25
Conductor type
27
INSULATOR SELECTION
• Location of conductor bundle determined to meet insulation co-ordination
requirements
• Insulator creepage, dry arching distance, basic insulation level (BIL) determined.
− Depends on pollution levels in the line route
• Insulator configuration depends on tower selection, I or V or other.
• Material depends on pollution, vandalism, maintenance.
• Hardware depends on material (corona rings for composite), live line
requirements
• For cross rope towers I string permits less pollution accretion especially from
birds.
LIGHTNING CONSIDERATIONS
• Shield angle determination depends on tower type.
− Negative shield angles generally give better performance.
• Tower footing resistance needs to be determined and reduced on the line
− “crows foot”, buried earthwire, bentonite mix
• Note towers with large footprints generally give lower tower footing resistances.
− Cross rope suspensions provide excellent results
• If tower footing resistance still high may consider line surge arresters installed on
certain towers.
• Shield or earth wires are now often OPGW.
− Care to be taken for fault current in the earth wire.
AC LINE DESIGN
OBJECTIVE INDICATOR
31
FACTOR 1 Life Cycle Cost (k1)
• Covers determination of optimum aluminium area required. (Kelvin’s law)
• Cost of maintenance (estimate)
• Cost of losses – use system losses not line losses. (Due to power flow in
interconnected system)
32
FACTOR 2 THERMAL (k2)
• Cost is directly proportional to Thermal rating
− Higher rating higher initial cost
• A ratio is therefore needed
− Initial cost/MVA thermal (emergency or normal)
• The lower the ratio the better.
33
FACTOR 3 SIL (k3)
• The higher the SIL the higher the initial cost (normally)
• Ratio is therefore also required
− Initial cost/MVA sil
34
COMBINATION OF THE FACTORS
• Objective Matrix method
− Present practice is given 3/10
− 0 or 10 level is determined (normally trial and error) and a linear interpolation
used.
• ATI = w1k1+w2k2+w3k3
− wn are weighting factors
35
CONDUCTOR SELECTION
CONDUCTOR OPTIMISATION
900.00
800.00
700.00
600.00
2 X IEC800
4 X KINGBIRD
LCC(Rmil)
500.00 3 X BERSFORT
3 X TERN
400.00 3 X YEW
3 x Bersfort 4 X TERN
300.00
4 x Tern
200.00
4 x Kingbird
100.00
3 x Tern
0.00
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400
Pmean(MVA)
36
TOWER SELECTION
37
EXAMPLE LINE
38
ATI SCORES
CASE AL AREA DESCRIPTION K1 (LCC) K2 K3
mm2 (CI/MVAth) (CI/MVAsil)
39
ATI WEIGHTING
40
FINDINGS/BENEFITS
• Tower, foundation, hardware, electrical designers work together with planners
(iterative process)
• Indicator very sensitive and detects errors rapidly
• Line optimisation is possible looking at overall line design.
• Reliability is assumed constant for options
• Cost system is critical
• Most aspects of the line design are taken into account
41
CONCLUSIONS
• Line design options can be objectively determined
• ATI is a guide from which options can be finalised.
• Alignment with Planners requirements
42
OPTIMISING LINE
DESIGNS
TUTORIAL FOR TB 638
DC LINE DESIGN
and the equation applies for both 10% and 15% volt drop. {1/sqrt(44) is an approximation of 15/100} and the format
removes the generality of the basic and simple equation.
L=Distance in kilometres.
DC resistance
• DC resistance not dependent on current
• Dependent on conductor geometry and conductivity of material.
• Dependent on temperature.
Effect of conductor radius (TB388)
The higher the conductor diameter and the more sub-conductors in the bundle the more resistant the bundle is to
corona and therefore the designer is more able to raise the voltage to ground and hence increase the power capability
of the line.
Corona power loss
E mas d n HS
P = 11 + 40 log + 20 log + 15 log − 10 log
25 3.05 3 225
Where P is the corona loss is dB above 1 W/m, Emax is the positive polarity maximum bundle gradient in kV/cm, d is the
sub-conductor diameter in cm, n is the number of sub-conductors in the bundle, H is the average conductor height in m
and S is the pole spacing in m.
INSULATOR CONSIDERATIONS
• Similar requirements to AC as far as tower window design.
• For glass insulators need germanium glass as normal glass will shatter
− Zinc collar also required
• Creepage larger than for AC
• Space charge considerations as well as uneven pollution on insulator to be taken
into account.
• Composite insulators can be used for AC and DC lighter weight often suit long
insulator installation.
• Porcelain disc are also successfully used.
Summary of options
LCC is the life cycle cost expressed in terms of a score from 1 to 10 and IC is the initial cost.
MVAthermal is the thermal rating of the line and depends, as in the AC case, to the templating temperature of the line.
Application of HVDC Indicator
Line requirements
Guyed structure
lines 1991 59.6 40.4 32.8 3.2 8.3 36.0 19.8
Lines with 1
conductor/phase 1991 64.4 35.6 32.2 4.2 8.5 36.3 18.8
Lines with 2
conductors/phase 1991 64.6 35.4 32.3 4.0 8.1 36.2 19.4
Lines with 3
conductors/phase 1991 60.8 39.2 35.1 3.7 7.0 40.3 13.8
Lines with 4
conductors/phase 1991 61.4 38.6 33.4 2.7 7.6 33.4 22.9
R375,000
46%
R300,000 52% Saving
Saving
R225,000 Misc Costs
Insulation
R150,000 Hardware
Tower Erection
Tower Supply
R75,000
Foundations
R0
72 structures
0-15 degree 15-30 degree structures
705A tower at NETFA
73
REFERENCES/
ACKNOWLEDGEMENTS
[Stephen 2004] Stephen R. “Use of indicators to optimise design of overhead transmission lines”. Paper 330-1
Shanghai Symposium, Cigré 2003. (Held in Lubljana April 4-6 2004)
[Stephen 2011] Stephen R “Objective detetermination of Optimal power line designs” PhD thesis submitted in 2011
University of Cape Town.
[Muftic]. Muftic D, Bisnath S, Britten A, Cretchley DH, Pillay T, Vajeth R “The Planning design and construction of
overhead power lines” Published by Crown publications 2005 ISBN 9780620330428
[Southwire] Overhead Conductor Manual First edition copyright 1994.
Prof. C.T.Gaunt (UCT) acknowledged for comments and input.
J. Lindquist AC/DC conversion TB 583
Nolasco, Jardini, TB 388
74