0% found this document useful (0 votes)
65 views3 pages

Contractor'S Statement of Work Accomplished: Environmental Management Bureau 10

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 3

Republic of the Philippines

Department of Environmental and Natural Resources


ENVIRONMENTAL MANAGEMENT BUREAU 10
DENR Compound, Macabalan, Cagayan de Oro City
Website: http://www.r10.emb.gov.ph
Telephone: (088) 856 9362

CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED

Project Lot No. 1 Construction and Supply of Materials of Administration Building


Location Brgy. Dulay, Marawi City, Lanao del Sur
Contractor Ahmadi Builders

Weightage % %
%
Items Description as per Accomplishmen Cost to Date Balance
Accomplishment
Contract to Date
1 Project Billboard / Signboard 100%
2 Occupational Safety and Health Program 100%
3 Structure Ex cavation (Common Soil) 100%
4 Embankment From structure Excavation 100%
5 Embankment From Borrow 100%
I 6 Gravel Fill 100% 30.00% 30.00% 1,694,486.81 0.00
7 Structural Concrete (class A, 28 days) 100%
8 Septic Vault 100%
9 Reinforcing Steel (Deformed 40) 100%
10 Formworks and Falseworks 100%
100 mm . CHB Non Load Bearing (including
11 100%
reinforcing steel)
12 Aluminum Windows & Frames (Analok) 100%
Sliding Doors & Frames (Analok) including
13 100%
accessories
14 PVC Doors & PVC Jambs 100%
15 Wooden Doors & Jambs 100%
16 Railling 0%
17 Cement Floor Finish with Floor Hardener 100%
18 Cement Plaster Finish 100%
19 Structural Steel (Trusses) 100%
20 Structural Steel (Purlins) 100%
21 Metal Structure Accessories (Crossbracing) 100%
22 Metal Structure Accessories (Sagrods) 100%
II 23 Painting Works (Masonry/Concrete) 100% 50.00% 48.69% 2,750,168.15 73,976.54
24 Painting Works (Wood) 100%
25 Painting Works (Steel) 100%
Ceiling - Metal Furring with Board
26 100%
(Hardiflex)
Prepainted GI Roofing Sheets (Long Span,
27 100%
0.4mm thk.)
Fabricated Metal Roofing Accesory (Ridge
28 100%
Roll, .6mm thk)
Fabricated Metal Roofing Accesory (Flashing,
29 100%
0.4mm thk)
30 Insulation foam 59%
31 Plumbing Works 59%
32 Water line Works 59%
33 Unglazed Tiles (30cm x 30cm) 50%
34 Glazed Tiles (30cm x 30cm) 50%
35 Granite Tiles (60cm x 60cm) 50%
AC Unit Ceiling Cassette Type (3pcs.-3hp &
36 50%
2pc 2hp)
III 37 Conduit, Boxes, and Fittings 25% 20.00% 7.70% 434,654.96 695,002.91
38 Wires and Wiring Devices 25%
Power Load Center, Switchgear and
39 25%
Panelboard
40 Lighting Fixtures 25%
41 Fire Alarm System 25%
IV Total for Administrative Building 86.39% 4,879,309.93 768,979.45

Prepared By: Submitted By: Approved By:

Ismail A. Miondas Abdul Hamid R. Batugan Reynaldo S. Digamo


Project Manager Project Engineer OIC - Regional Director
Ahmadi Builders DENR Region X DENR Region X
Republic of the Philippines
Department of Environmental and Natural Resources
ENVIRONMENTAL MANAGEMENT BUREAU 10
DENR Compound, Macabalan, Cagayan de Oro City
Website: http://www.r10.emb.gov.ph
Telephone: (088) 856 9362

CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED

Project Lot No. 2 (Construction and Supply of Materials of 3 Unit Overhauling Area)
Location Brgy. Dulay, Marawi City, Lanao del Sur
Contractor Ahmadi Builders

Weightage % %
%
Items Description as per Accomplishmen Cost to Date Balance
Accomplishment
Contract to Date

1 Project Billboard / Signboard 67%


2 Occupational Safety and Health Program 67%
3 Structure Excavation (Common Soil) 67%
4 Embankment From structure Excavation 67%
I 30.00% 20.10% 1,045,086.14 514,743.92
5 Embankment From Borrow 67%
6 Gravel Fill 67%
7 Structural Concrete (class A, 28 days) 67%
8 Reinforcing Steel (Deformed 40) 67%
9 Formworks and Falseworks 67%
10 Structural Steel (Trusses) 67%
11 Structural Steel (Purlins) 67%
12 Metal Structure Accessories (Crossbracing) 67%
13 Painting Works (Masonry/Concrete) 67%
14 Painting Works (Wood) 67%
II 15 Painting Works (Steel) 67% 50.00% 33.47% 1,740,408.25 859,308.51
16 Marine Plywood on Metal Frame Ceiling 67%
Prepainted Metal Sheets (Long Span, RIB-
17 67%
TYPE)
Fabricated Metal Roofing Accesory
18 67%
(Flashing)
19 Waaterline Works 15%
20 Septic Vault 67%
21 Sanitary/Plumbing Fixtures 25%
22 Conduit, Boxes, and Fittings 25%
III 23 Wires and Wiring Devices 25% 20.00% 5.00% 259,971.68 779,915.03
Power Load Center, Switchgear and
24 25%
Panelboard
25 Lighting Fixtures 25%
IV Total for 3 Unit Overhauling Area 58.57% 3,045,466.07 2,153,967.46

Prepared By: Submitted By: Approved By:

Ismail A. Miondas Abdul Hamid R. Batugan Reynaldo S. Digamo


Project Manager Project Engineer OIC - Regional Director
Ahmadi Builders DENR Region X DENR Region X
Republic of the Philippines
Department of Environmental and Natural Resources
ENVIRONMENTAL MANAGEMENT BUREAU 10
DENR Compound, Macabalan, Cagayan de Oro City
Website: http://www.r10.emb.gov.ph
Telephone: (088) 856 9362

CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED

Project Lot No. 3 (Construction and Supply of Materials of Warehouse and Storage Room)
Location Brgy. Dulay, Marawi City, Lanao del Sur
Contractor Ahmadi Builders

Weightage % %
%
Items Description as per Accomplishmen Cost to Date Balance
Accomplishment
Contract to Date

1 Project Billboard / Signboard 100%


2 Occupational Safety and Health Program 100%
3 Structure Excavation (Common Soil) 100%
4 Embankment From structure Excavation 100%
I 30.00% 30.00% 531,738.08 0.00
5 Embankment From Borrow 100%
6 Gravel Fill 100%
7 Formworks and Falseworks 100%
8 Reinforcing Steel (Deformed 40) 100%
9 Structural Concrete (class A, 28 days) 100%
100 mm . CHB Non Load Bearing (including
10 100%
reinforcing steel)
11 Structural Steel (Trusses) 100%
12 Structural Steel (Purlins) 100%
13 Metal Structure Accessories (Crossbracing) 100%
14 Metal Structure Accessories (Sagrods) 100%
Prepainted Metal Sheets (Long Span, RIB-
15 100%
TYPE)
Fabricated Metal Roofing Accesory (Ridge
II 16 100% 50.00% 48.44% 858,640.03 27,590.09
Roll)
Fabricated Metal Roofing Accesory
17 100%
(Flashing)
18 Marine Plywood on Metal Frame Ceiling 100%
19 Cement Plaster Finish 100%
20 Cement Floor Finish with Floor Hardener 100%
21 Window Frames 100%
22 Sliding Windows 50%
23 Railing With Steel Matting 50%
24 Steel Gate 50%
25 Wood Panel Door 50%
26 PVC Door and Frames 50%
27 Unglazed Tiles 50%
28 Glazed Tiles 50%
29 Painting Works (Masonry/Concrete) 50%
30 Painting Works (Wood) 80%
31 Painting Works (Steel) 80%
III 32 Plumbing Works 30% 20.00% 9.08% 160,924.20 193,567.85
33 Conduit Boxes & Fittings 30%
34 Wires and Wiring Devices 50%
35 Panelboard with Main and Branch Breaker 50%
36 Lighting Fixtures 50%
37 Fire Alarm System 15%
IV Total for Warehouse/ Storage Room 100.00% 87.52% 1,551,302.32 221,157.94

Prepared By: Submitted By: Approved By:

Ismail A. Miondas Abdul Hamid R. Batugan Reynaldo S. Digamo


Project Manager Project Engineer OIC - Regional Director
Ahmadi Builders DENR Region X DENR Region X

You might also like