Contractor'S Statement of Work Accomplished: Environmental Management Bureau 10
Contractor'S Statement of Work Accomplished: Environmental Management Bureau 10
Contractor'S Statement of Work Accomplished: Environmental Management Bureau 10
Weightage % %
%
Items Description as per Accomplishmen Cost to Date Balance
Accomplishment
Contract to Date
1 Project Billboard / Signboard 100%
2 Occupational Safety and Health Program 100%
3 Structure Ex cavation (Common Soil) 100%
4 Embankment From structure Excavation 100%
5 Embankment From Borrow 100%
I 6 Gravel Fill 100% 30.00% 30.00% 1,694,486.81 0.00
7 Structural Concrete (class A, 28 days) 100%
8 Septic Vault 100%
9 Reinforcing Steel (Deformed 40) 100%
10 Formworks and Falseworks 100%
100 mm . CHB Non Load Bearing (including
11 100%
reinforcing steel)
12 Aluminum Windows & Frames (Analok) 100%
Sliding Doors & Frames (Analok) including
13 100%
accessories
14 PVC Doors & PVC Jambs 100%
15 Wooden Doors & Jambs 100%
16 Railling 0%
17 Cement Floor Finish with Floor Hardener 100%
18 Cement Plaster Finish 100%
19 Structural Steel (Trusses) 100%
20 Structural Steel (Purlins) 100%
21 Metal Structure Accessories (Crossbracing) 100%
22 Metal Structure Accessories (Sagrods) 100%
II 23 Painting Works (Masonry/Concrete) 100% 50.00% 48.69% 2,750,168.15 73,976.54
24 Painting Works (Wood) 100%
25 Painting Works (Steel) 100%
Ceiling - Metal Furring with Board
26 100%
(Hardiflex)
Prepainted GI Roofing Sheets (Long Span,
27 100%
0.4mm thk.)
Fabricated Metal Roofing Accesory (Ridge
28 100%
Roll, .6mm thk)
Fabricated Metal Roofing Accesory (Flashing,
29 100%
0.4mm thk)
30 Insulation foam 59%
31 Plumbing Works 59%
32 Water line Works 59%
33 Unglazed Tiles (30cm x 30cm) 50%
34 Glazed Tiles (30cm x 30cm) 50%
35 Granite Tiles (60cm x 60cm) 50%
AC Unit Ceiling Cassette Type (3pcs.-3hp &
36 50%
2pc 2hp)
III 37 Conduit, Boxes, and Fittings 25% 20.00% 7.70% 434,654.96 695,002.91
38 Wires and Wiring Devices 25%
Power Load Center, Switchgear and
39 25%
Panelboard
40 Lighting Fixtures 25%
41 Fire Alarm System 25%
IV Total for Administrative Building 86.39% 4,879,309.93 768,979.45
Project Lot No. 2 (Construction and Supply of Materials of 3 Unit Overhauling Area)
Location Brgy. Dulay, Marawi City, Lanao del Sur
Contractor Ahmadi Builders
Weightage % %
%
Items Description as per Accomplishmen Cost to Date Balance
Accomplishment
Contract to Date
Project Lot No. 3 (Construction and Supply of Materials of Warehouse and Storage Room)
Location Brgy. Dulay, Marawi City, Lanao del Sur
Contractor Ahmadi Builders
Weightage % %
%
Items Description as per Accomplishmen Cost to Date Balance
Accomplishment
Contract to Date