31 Samss 001
31 Samss 001
31 Samss 001
Contents
Part 1 – General Requirements ............................... 2
1 Scope ................................................................ 2
2 Normative References ...................................... 3
4 General ............................................................. 5
5 Accessories..................................................... 13
6 Inspection, Testing, and
Preparation for Shipment ......................... 18
7 Supplier’s Data................................................ 21
Part 1 – Annex E.................................................... 23
Part 1 – Annex J - Material Selection and
Joining Methods for Auxiliary Piping......... 27
Part 2 – Non-Integrally Geared Centrifugal
and Axial Compressors ............................ 31
5 Accessories..................................................... 33
6 Inspection, Testing, and Preparation
for Shipment ............................................. 33
Part 3 – Integrally Geared Compressors ............... 35
6 Inspection, Testing, and Preparation
for Shipment ............................................. 36
Part 4 – Expander-Compressors ........................... 37
6 Inspection, Testing, and Preparation
for Shipment ............................................. 38
Revision Summary................................................. 38
The following parts and paragraph numbers refer to API STD 617, Eighth Edition,
which is a part of this specification. The text in each paragraph below is an
addition, unless noted as an exception, modification, or deletion to API STD 617.
Paragraph numbers not appearing in API STD 617 are new paragraphs to be inserted in
numerical order. The requirements of this specification have precedence over the
content of API STD 617.
1 Scope
1.1 Scope
Page 2 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
In the area of component design, the Vendor must show that each
component has operated under similar or more severe conditions than
those of the proposed machine.
2 Normative References
Material or equipment supplied to this specification shall also comply with applicable
sections of the latest edition (unless an edition is specified) of the references listed
below or in the body of this document.
Page 3 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Page 4 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4 General
4.4.1 General
4.4.1.1 Performance
4.4.1.1.3 (Modification) The compressor power at the normal operating point shall
be guaranteed within 1% positive tolerance. For compressors with an inlet
flow coefficient greater than 0.02, the compressor polytropic efficiency at
normal operating point shall be 81% minimum. The flow coefficient
definition is per ASME PTC 10.
Page 5 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.4.1.3 If sea water cooling is used, a design inlet temperature of 35°C (95°F)
shall be used.
4.5 Materials
4.5.1 General
Page 6 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
(0.34 kPa). All casing, impeller and shaft welds, including repair welds,
in contact with the service gas shall include hardness testing as part of the
welding procedure qualification. Testing may be performed on a sample
(mock-up test).
4.5.3 Forgings
4.6 Casings
4.6.1.3 The use of ductile iron casings for air or other nonflammable services may
be acceptable subject to the approval by the Compressors, Gears, and
Steam Turbines Standards Committee Chairman. Cast Iron or ductile iron
casings are prohibited for all other services.
Page 7 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.6.1.7.3 All threaded stud or bolt holes in casing and diaphragms shall be spaced a
minimum of ½ stud/bolt diameter from any wall/edge or other holes.
Repair: Any procedure that will require anything other than minor
machining or grinding (e.g., welding, plating, sleeving, etc.).
Page 8 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
in non-magnetic materials.
4.6.4.2.2 (Exception) Flanges shall conform to ANSI B16.5. Flanges above 24-inch
NPS shall conform to ASME B16.47 Series A in Class 150 - 900.
Flanges over Class 600 operating in a piping system shall be ring-jointed.
4.7.5 The maximum stress, at maximum continuous speed, within any of the
rotor’s components (including impellers) shall not exceed 80% of the
material yield strength. Impeller shroud minimum thickness shall not be
less than 3 mm. If requested, impeller dimensions and stress analysis shall
be submitted for review and approval.
4.7.9 Any axial clearance requirement between shaft sleeves to allow for
expansion shall be clearly indicated on the rotor drawing. The method of
impeller attachment to the shaft and any interference fit requirement shall
also be clearly specified on the rotor drawing.
4.7.10 Impellers
4.7.10.1 (Modification) Cast impellers are not acceptable. Impellers shall be made
from forgings and shall be of single-piece or two-piece construction.
Alternatives, with justification, require the approval of Compressors,
Gears, and Steam Turbines Standards Committee Chairman.
Page 9 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.7.10.2 (Modification) For manually welded impellers, full profile grinding of all
vane to disc and cover welds is required at both vane entrance and exit for a
minimum length of two inches or 10% of vane length, whichever is less.
No weld undercut is permitted for the profile ground areas. Profile grinding
shall be performed in accordance with the requirements of Figure 1 or
Figure 2 of Annex K.
4.8 Dynamics
4.8.1 General
4.8.2.1 Amplification factors shall not exceed 14 for any critical speed lower than
trip speed.
4.8.2.4.h The use of squeeze film dampers is not allowed without strong justification
and prior approval of Consulting Services Department.
4.8.2.8 The plots in the analysis report shall be provided for the range of
conditions and parameters covered in paragraph 4.8.2.4.
4.8.2.9 Bode plots and deflected rotor shape plots, clearly stating the assumed
parameters shall be provided for the additional analyses to be used during
the Unbalanced Rotor Response Verification Test.
4.8.7.2 The Vendor having unit responsibility shall conduct a torsional vibration
analysis of the complete train, and submit its report for review and approval.
4.8.7.7 The Vendor having unit responsibility shall demonstrate that the stress
levels in the entire drive train at torsional resonance are within
Page 10 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.8.7.8.4 For synchronous motor driven trains, a flexible spacer coupling shall be
provided. If the train torsional analysis indicates that using a standard
flexible spacer coupling results in exceeding the allowable shaft fatigue
stress, then alternative designs (e.g., quill-shaft spacer coupling, torsionally
damping coupling) shall be proposed. Minimum acceptable design life for
all train components in units passing through torsional resonances during
start-up shall be 1,000 starts.
4.9.1 General
4.9.1.2 Bearing metal temperature shall not exceed 105°C (221°F) at the loaded
area based on an oil inlet temperature of 60°C (140°F), design bearing
clearances and seal clearances that cause highest load.
4.9.2.1 Hydrodynamic radial bearings shall be of tilt-pad design and shall be split
for ease of assembly.
4.9.4.4 Wiring shall exit bearing housings using oil resistant and waterproof
fittings with oil resistant elastomer compression inserts to ensure zero
leakage of oil [Cable Gland seal].
4.9.4.6 (Exception) Any oil flow control orifices used within the housing shall be
replaceable and shall be clearly marked with the part number and/or orifice
Page 11 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
size. Minimum orifice diameter is 316 " (4.75 mm). They shall also be
identified on the assembly drawing.
4.10.1 General
4.10.1.1 Dry gas seals shall be provided for all flammable and toxic services.
4.10.1.3 (Modification) The maximum sealing pressure shall be at least equal to the
maximum specified discharge pressure.
The guaranteed leakage rate for each seal shall be stated in the Vendor's
proposal and shall be no greater than 5 scfm (141 liters/min) for any
service with an inlet pressure less than 200 bars. The Vendor shall
demonstrate adherence to these rates during shop tests, and later in field
tests at contract conditions during commissioning. The Seal System shall
be supplied by the Dry Gas Seal supplier, or as a minimum, the Seal
System design shall be approved by the Dry Gas Seal supplier and
confirmed not cause failure or impact the reliability of any of the
compressor seals. The Seal System supplier shall demonstrate in a
functional test, the ability of the seal gas system to provide the required
amount of seal gas, and its ability to detect and give warning of any seal
failure.
Page 12 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.12.1 Nameplates shall be in the English language and shall also include
Purchase Order number.
5 Accessories
5.1.3 The compressor vendor shall show on the compressor speed torque curve
the moment of inertia and suction conditions assumed in the calculation of
the curve. Slow-rolling or barring shaft devices shall not be required on
motor driven centrifugal compressors.
5.1.5 (Exception) For motor-driven units, the motor shall be in accordance with
17-SAMSS-502 or 17-SAMSS-520, as specified on the Data Sheet.
The motor nameplate rating (exclusive of service factor) shall be a minimum
of 110% of the greatest horsepower (including gear and coupling losses)
required for any of the specified operating conditions. The motor shall also
be capable of bringing the compressor train to normal speed within the
maximum safe allowable motor start time stipulated by the motor Vendor
when started under conditions specified by the Purchaser.
Page 13 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
5.3.3 Lube oil systems shall be in accordance with 32-SAMSS-013 Parts 1 and 2.
5.4.1 General
5.4.1.2.3 (Modifications)
b) All mounting surfaces in the same horizontal plane shall be within
250 μm (0.01 in.).
d) Different mounting planes shall be parallel to each other within
250 μm (0.01 in.).
5.4.2 Baseplates
5.4.2.1 The baseplate shall be constructed with longitudinal steel beams and full-
depth cross members. Cross members must be located underneath all
supports for machinery. All welding shall be continuous. For steam
turbine driven and motor driven compressors, the driver, transmission, and
compressor shall be mounted on a common baseplate, unless otherwise
approved by Consulting Services Department.
5.4.2.4 (Exception) The baseplate shall be provided with decking welded to the
peripheral and cross members. All walk areas shall be provided with non-
slip decking (e.g., grit coated). Floor plates with diamond or other patterns
shall not be used. Baseplate design shall not allow any liquids to collect
on the surface.
Page 14 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
5.4.2.5 The baseplates shall be suitable for column mounting when mezzanine
mounting is specified by the purchaser.
5.4.2.10 The baseplate shall have machined mounting pads that straddle all anchor
bolt hole locations.
5.4.2.12 An integrated lube oil reservoir within the baseplate is not acceptable.
5.5.1 General
5.5.1.8 Closed conduits shall be used for routing cables and shall be threaded, hot-
dip galvanized, rigid steel per ANSI C80.1. Certified, liquid-tight flexible
conduits suitable for the area classification may be used only between the
rigid conduit and terminal head to tolerate vibration. Conduit fittings shall
be steel, cast iron or malleable iron, and hot dip galvanized or zinc
electroplated. Nickel-plated brass conduit fittings are also acceptable.
Additionally, for offshore or nearshore installations, the conduit, and
fittings shall be PVC coated per NEMA RN 1 (minimum thickness of
PVC: 40 mils).
The alarm and shutdown system shall be as specified in the purchase order
Page 15 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
and on the data sheets. For compressors driven by VFD motors, 2-o-o-3
overspeed trip protection shall be provided based on shaft speed
measurement. Electric switches shall be fail safe devices that close
(energize) during normal operation and open (de-energize) to alarm or trip.
Each radial and thrust bearing shall be provided with two temperature
sensors or a single duplex type sensor. All wiring must terminate in a
single externally mounted terminal box that is accessible. Bearing
temperature sensors shall be supplied in accordance with Forms SA-8020-
415, SA-8020-415-M, and SA-8020-416.
5.6.1 General
5.6.1.1 (Modification) Auxiliary piping sizing, materials and joining method shall
be in accordance with Table J-1 in Annex J. All piping systems shall be
provided with vent valves at highest points and drain valves at lowest
points. Horizontal runs in pressure piping shall slope gradually towards
drain points. The minimum slope of drain lines shall be 1:50. Vents and
drains shall be flanged for connection at site.
5.6.1.4 The vendor shall submit a 3D drawing of the proposed compressor skid
detail drawing for Company review and approval during the detailed
design phase. All auxiliary piping and conduits or cable trays shall be
routed adjacent to or below the compressor. A block valve, ¾-inch NPS
minimum, shall be installed in each instrument take-off connection from
the main lines and shall be located as close as feasible to this main line,
vessel, or mechanical equipment. One common instrument air supply and
one common Nitrogen supply connections shall be provided for each skid.
Page 16 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
5.6.1.5 Bearing and coupling drains shall be provided and routed to their respective
console return manifolds. All casing drain valves shall be located in an
accessible area, outside the compressor footprint. Drain lines shall be piped
separately (not to a common manifold) to flanged terminations at the edge of
the baseplate for connection to the closed drain system.
5.6.1.7 Tubing shall not be used in services with a maximum pressure above
3,400 kPa (500 psig) or a maximum temperature above 120°C.
The minimum size of auxiliary piping and tubing shall be ½-inch NPS.
5.6.1.8 Piping of 1-½ inch NPS or smaller shall be provided with firm, welded
gussets or braces in two perpendicular planes at the take-off connection
between the machinery or auxiliary equipment and the first block (root)
valve. Refer to Standard Drawing AB-036521 for valve bracing. Tubing
shall be clipped with clamps.
5.6.1.9 Fittings and flanges shall conform to the following Standards or equivalent
international specifications:
a) Malleable iron threaded fittings, ASME B16.3 Class 150 with
material to ASTM A197, hot dip galvanized to ASTM A153.
b) Flanges, carbon steel to ASME B16.5 and stainless steel to
ASTM A182 Grade TP-316L.
c) Butt welding fittings to ASME B16.9. Stainless steel to ASTM A403
Grade WP-316L.
d) Socket welding and threaded fittings shall be ASME B16.11
Class 3000 or Class 6000 carbon steel to ASTM A105 N and stainless
steel to ASTM A182 Grades F-316L.
e) For tubing, connectors and adapters shall be compression type
meeting UNS S-31600 and ASTM A276.
5.6.1.10 Miter fittings such as miter elbows or miter bends are prohibited.
5.6.1.11 Gaskets for raised flanges shall be spiral-wound, Type 316 stainless steel.
Gaskets for ring joint flanges shall be soft iron octagonal ring. Gaskets
containing asbestos are not permitted.
5.6.1.12 Auxiliary process gas valves shall be in accordance with API STD 602
Class 800 or ASME B16.34 with rating as required for the service
conditions. Valve materials shall be as required for the service but as a
minimum shall be forged or cast steel to ASTM A105 or A216 Grade
WCB with trim to 11-13% chrome AISI 410 stainless steel. For throttling
service, globe, or needle valves shall be used.
Page 17 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
5.6.1.13.1 Pipe bends shall have surfaces free of cracks and buckles. Flattening of
the cross section of bends shall not exceed 8% of the nominal pipe
diameter. Bending procedures and heat treatment requirements shall be in
accordance with ASME B31.3.
5.6.1.13.2 Where pipe, fittings, and flanges are to be joined by butt welds, the
corresponding parts shall be matched such that any misalignment at the
inside of the piping shall not exceed 1.5 mm at any point on the
circumference of the joint.
5.6.1.13.3 All welds must meet the minimum quality requirements of ASME B31.3
together with the following additional requirements:
a) For pipe sizes 2 inch and smaller the first pass of butt welded joints
shall be made with Gas Tungsten Arc Welding (GTAW) process.
b) Permanent backing rings are prohibited, but consumable inserts of the
same chemistry as the remaining weld metal may be used.
5.6.1.13.5 Shop fabricated piping shall be cleaned internally prior to installing on the
mechanical equipment and prior to mechanical or performance testing.
Stainless steel lube oil and seal oil piping downstream of the filter shall be
mechanically cleaned at welds to the extent that all foreign materials are
removed. All other piping shall be cleaned by steam, air or water flushing
and if necessary by mechanical cleaning. All piping shall be completely
drained and dried after cleaning and after hydrotesting. All carbon steel
piping shipped uninstalled shall be flushed with a rust preventative prior to
shipment.
6.2 Inspection
6.2.1 General
Page 18 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
6.2.1.6 Hardness, welds, etc., shall be verified per the requirements of paragraph
2.2.1.6.
6.3 Testing
6.3.1.2 (Exception) The Vendor shall submit, for Company approval, detailed test
procedures, acceptance criteria and dated schedule for the mechanical and
performance tests at least 12 weeks prior to the scheduled tests.
Comments on these test procedures shall be submitted back to the Vendor
at least four weeks prior to the scheduled tests. Other tests should be in
accordance with the Inspection and Test Plan (ITP).
6.3.5.9.1 Calibration of the vibration probe and monitor circuits to be used shall be
verified immediately prior to the test, utilizing a wobulator or equivalent
device or method. Alternatively, recent calibration certificates for the
vibration measurement circuits shall be provided.
6.3.5.9.5 e) Isolating seal buffer gas flow rate shall be monitored for each seal.
Upon completion of the test any evidence of oil inboard of the isolating
seals, by checking the drain lines, is cause for rejection.
6.3.5.9.6 The oil pressures and temperatures shall be varied through their allowable
ranges during the test. The oil shall be held at minimum pressure and
maximum temperature (producing lowest viscosity) for at least 15 minutes
and the vibration and temperatures recorded. The same should be done at
maximum pressure and minimum temperature (producing the highest
viscosity) for at least 15 minutes with the vibration and temperatures
recorded. This shall also be repeated at minimum, normal, and maximum
continuous speeds for variable speed compressors.
6.3.5.9.7 (Modification) The test shall be performed using the design lube oil
specified on the data sheet. When the lube oil specified on the data sheet
is not available, the test may be conducted using shop lube oil conditioned
to a viscosity equivalent to that of the specified oil at site operating
conditions. Bearing metal temperatures shall not exceed 45°C (81°F)
above oil supply temperature.
Page 19 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Commentary Note:
6.3.5.12 Upon completion of the test, the purchaser shall be provided with copies of
all test data, graphs and charts. The data shall be arranged in a format that
clearly show acceptance criteria versus test measurements for each
parameter. Additionally, charts of shaft deflection during the mechanical
running test and the unbalance response test shall be provided to verify
compliance to the requirements of paragraphs 2.6.4.2.a and b.
For compressors in hydrogen services, the casing shall be tested for gas
leakage with helium after the hydrostatic test.
Page 20 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
6.4.3.9 Loose components shall be properly identified with tags prior to crating or
boxing. Individual components shall be marked or tagged with its
equipment number, description, drawing number, and item number as
marked on the drawing. Piping which cannot be installed on the
mechanical equipment during transport for reasons of space or risk of
damage shall be packed in a wooden box or crate and shall be shipped
together with the mechanical equipment.
7 Supplier’s Data
7.2 Proposals
7.2.3 q) The Vendor shall state the guaranteed rates for primary seal leakage,
secondary seal gas supply, secondary seal leakage, and separation seal gas
supply.
7.3.2.1 Curves
Page 21 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
7.3.5.1 General
Page 22 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Part 1 – Annex E
E.4.4.1 The vendor shall also provide the following additional requirements:
Special tools as required for installation and maintenance.
Power and instrumentation interconnecting wiring from the bearings
and auxiliary instrumentation to the control cabinet.
Any required cooling systems for the bearings and the control system.
E.4.4.2 The magnetic bearing vendor shall confirm that all equipment will not
malfunction when subjected to an electromagnetic field from radiating
sources, in particular hand held radio transceivers (walkie-talkies),
operating at 5 watts within the frequency range of 68 MHz to 470 MHz.
E.4.5 Materials
For bearings that are normally not in contact with the process gas, the
windings, insulation, laminations and backup bearings shall be designed so
that exposure to the process gas (e.g., upon seal failure) can be tolerated
without failing the magnetic bearings or the backup bearings.
E.4.8 Dynamics
E.4.9.1 General
Page 23 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
E.5.1.2 The control system shall include continuous monitoring capability and
remote communication with standard Modbus protocol compatible with
the Purchaser supplied DCS system. The control system shall be fail-safe
and shall be a fully digital system with self-diagnostic capabilities to
permit identification of sensor or control board level faults. The magnetic
bearing vendor shall supply a listing of all controller addresses for all
signals available across the DCS link. As a minimum, the following
signals shall be available:
Vibration
Shaft position
Bearing temperatures
Amplifier currents (DC & AC)
Bearing loads
Rotor speed
Auxiliary bearing contact counter
Control system and amplifier status
Page 24 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
E.5.2 Cabling
E.5.2.1 (Exception) The cable length between the skid mounted junction boxes
and the magnetic bearing control cabinet shall be defined by the purchaser.
The magnetic bearing vendor shall identify cable sizes and types,
installation procedures, maximum allowable cable lengths, and any
additional hardware required for power and instrumentation systems to
provide reliable control and power operations over the distance specified.
All cable between skid edge and remote control cabinets shall be suitable
for direct burial.
E.6.3 Testing
E.6.3.4 The complete job control system shall be connected for each bearing and
rotor system during the performance and mechanical running tests.
Preliminary tuning of the bearing system shall be carried out to center the
rotor in the bearings, and the rotor shall be brought to running speed and
held there for a four-hour period.
Following this run, during the unbalance rotor response verification test
with an unbalance weight equivalent to the allowable unbalance limit
placed at an agreed upon location, the rotor shall be rerun maintaining the
same control tuning, and the vibration and bearing loads shall be recorded.
The controller shall then demonstrate the ability of the system to
compensate for the unbalance. Finally, the power shall be cut and the
ability of the back-up bearings to handle the rotor load during shutdown
shall be verified.
E.6.3.5 (Exception) The bearings and control system shall be tested to verify the
load capability of the bearings. This may be done statically but shall be no
less than 1.5 times the maximum design loads in both radial and axial
directions.
E.10 Documentation
Page 25 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Page 26 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Part 1 – Annex J - Material Selection and Joining Methods for Auxiliary Piping
Table J-1 – Sizing, Material Selection, and Joining Methods for Auxiliary Piping
Pipe Pipe Tubing
Size Range
Service Material Joining Material
inches
(1,2) (3,4,5) (6)
Control, Lube, Seal, ½ in. thru 1-½ in SS BW, FG, SW, TS ST
and Hydraulic oil 2 in. and Larger SS BW, FG
Auxiliary Process Gas ½ in. thru 1-½ in CS (7), SS BW, FG, SW ST
(e.g., drain, vent) 2 in. and Larger CS (7), SS BW, FG
Nitrogen, Instrument, ½ in. thru 1-½ in SS, GS BW, FG, SW, TC, TS ST
or Plant Air 2 in. and Larger SS, GS BW, FG, TC
½ in. thru 1-½ in CS, SS BW, FG, SW ST
Instrument Process Lines
2 in. and Larger
½ in. thru 1-½ in CS BW, FG, TC, TS ST
Steam
2 in. and Larger CS BW, FG, TC
FG, TC
½ in. thru 1-½ in GS, CS
BW, FG, SW, TC ST
Utility Water
FG, TC
2 in. and Larger GS, CS
BW, FG
½ in. thru 1-½ in (8) BW, FG, SW
Sea Water
2 in. and Larger (8) BW, FG
Table Legend:
CS Carbon Steel Pipe: API 5L Seamless, ASTM A106 Grade B, or equivalent
SS Stainless Steel Pipe: ASTM 316L (weldable)
GS Galvanized Steel Pipe: ASTM A53, API Grade B, or equivalent
BW Buttwelded
FG Flanged
SW Socket Welded
TC Threaded and Coupled
TS Threaded and Coupled, Seal Welded
ST Stainless Steel Tube: ASTM A269; TP-316 without welding (TP-316L with welding)
Table Notes:
1) The minimum wall thickness of piping and butt welding fittings shall be Schedule 40 for sizes larger than
2-inch and Schedule 80 for sizes 2-inch and smaller. For lube oil service, Schedule 10S is acceptable for
sizes 2-inch and larger.
2) Galvanized steel pipe and malleable iron fittings are limited to temperatures between 0 and 90°C.
3) Flanges, socket welding and threaded fittings shall be the class, rating or wall thickness to match the pipe
ratings. Galvanized steel pipe Schedule 40 and malleable iron fittings shall be Class 150.
Page 27 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4) Threaded connections shall conform to ASME B1.20.1 Pipe Threads. The material of the first threaded
nipple to mechanical equipment shall be compatible with the material of the equipment and the thickness
shall be minimum of Schedule 80. Socket welding and threaded joints are limited to sizes 1-½-inch and
smaller.
5) Socket welded or threaded fittings may be used where indicated for temperatures between -18 and
400°C. Above 400°C flanged connections are required. Socket welded end connections shall take
preference over threaded and seal welded connections.
6) Tubing may be used instead of pipe beyond the first valve in a line where socket welded or threaded
connections are normally permitted. For tubing, connectors and adapters shall be compression type
meeting UNS S-31600 and ASTM A276.
7) Corrosion resistant of selected material shall be based on the process fluid and operating conditions.
8) For sea water service, the material shall be stainless steel UNS S31254 welded with ERNiCrMo-3.
Page 28 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Part 1 – Annex K
Figure 1
Page 29 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Figure 2
Page 30 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
The Vendor shall indicate clearly in the proposal datasheet and curves if
any of the operating points specified on the data sheets will be within 10%
or less from surge capacity. The Vendor shall also guarantee that the surge
capacity (without the use of a bypass) shall be no more than 70% of the
Normal operating point flow. The head-capacity curve at 100% speed
shall extend to at least 110% of the flow at Compressor Rated Point.
The Vendor shall specify relative inlet and absolute outlet Mach numbers
at maximum continuous speed and rated operating point for each impeller
exceeding the following limits:
For hydrocarbon gas service: 0.7 relative Mach at impeller inlet (eye)
For other services: 0.9 relative Mach at impeller inlet (eye)
4.6 Casings
4.6.1.3 Radially split casings shall have forged steel end cover(s) (head) if the
maximum allowable working pressure exceeds 6,900 kPa ga (1,000 psig).
Each end cover of a radially split compressor shall be utilize a minimum of
two radial O-rings to seal the end cover to casing. The O-rings shall be
continuous, and not of the jointed/glued type. In corrosive gas services,
the O-rings seal grooves and landings shall all be coated or weld-overlaid
with Inconel alloy.
4.6.1.5 (Modification) Except for air services, O-rings are not permitted in the top
and bottom flanges of axially split compressor casings.
Page 31 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.7.2 Shafts
4.9.3.6 When directed lube thrust bearings are used, their design shall ensure that
the directed lube oil passages will not be plugged. Flooded lube thrust
bearings are also acceptable.
Page 32 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
5 Accessories
The Vendor shall provide sufficient baseplate space with a clear area at the
non-drive end of the compressor to accommodate inner barrel removal.
All required tools and detailed procedures for inner barrel removal shall be
provided by the Vendor. Any anti-friction bearings used for barrel support
shall be sized for the full barrel load.
6.3.3.1.1 A performance test shall be conducted in the Vendor's shop for each
compressor service to verify the predicted aerodynamic and
thermodynamic performance. Reynolds number correction shall not be
applied to performance test data. All proposal performance curves shall be
corrected and reissued based on the results of the performance test. If the
test fails to demonstrate compliance with the requirements of this
specification, the Vendor shall modify the compressor and repeat the
complete test at no additional cost to the Buyer.
6.3.3.1.2 In addition to the test points specified in 6.3.3.1.5, test points for
compressors with variable operation (e.g., Variable Speed, AIGVs) shall
also include surge, intermediate and maximum capacities at maximum,
minimum and at least three intermediate speeds or AIGV positions
(including speeds or guide vane positions corresponding to operating
conditions specified on the datasheet).
6.3.3.1.3 (Modification) The tolerances for power, surge and end of curve (capacity
limit or overload) shall be in accordance with the requirements of 4.4.1.1
in this specification.
6.3.3.1.5 (Modification) The tolerances for power, surge and end of curve (capacity
limit or overload) shall be in accordance with the requirements of 4.4.1.1
in this specification. Compressor test points shall include a minimum of
five points:
Page 33 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Page 34 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
4.4.1 Performance
The head-capacity curve of the rated point shall extend to at least 105% of
the capacity at Compressor Rated Point.
The Vendor shall specify relative inlet and absolute outlet Mach numbers
at maximum continuous speed and rated operating point for each impeller
exceeding the following limits:
For hydrocarbon gas service: 0.7 relative Mach at impeller inlet (eye)
For other services: 0.9 relative Mach at impeller inlet (eye)
Curves shall be provided showing the surge capacity and normal operating
point for each section and for overall operation.
5.5.7.7 Vibration detectors, key phasors, shaft axial position monitors, and bearing
temperature detectors shall be in accordance with 34-SAMSS-625.
Page 35 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
6.3 Testing
Page 36 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
Part 4 – Expander-Compressors
The Vendor shall also guarantee that the turndown capacity (without the use
of a bypass) shall be no more than 70% of the capacity at normal operating
point. The Vendor shall also indicate if any of the other operating points
specified on the data sheets will be within 10% from surge capacity.
The head-capacity curve at 100% speed shall be guaranteed to extend to at
least 110% of the capacity at the Compressor Rated Point.
The Vendor shall specify relative inlet and absolute outlet Mach numbers
at maximum continuous speed and rated operating point for each impeller
exceeding the following limits:
For hydrocarbon gas service: 0.7 relative Mach at impeller inlet (eye)
For other services: 0.9 relative Mach at impeller inlet (eye)
4.5 Materials
4.9.1 General
Page 37 of 38
Document Responsibility: Compressors, Gears, and Steam Turbines Stds Committee 31-SAMSS-001
Issue Date: 23 August 2017
Next Planned Update: 23 August 2020 Axial and Centrifugal Compressors and Expander-Compressors
6.3 Testing
Revision Summary
30 April 2013 Revised the “Next Planned Update.” Reaffirmed the content of the document, and reissued
with minor revision to improve equipment efficiency, reliability, and value.
23 August 2017 Major revision, removed 01-SAMSS-017 reference, and updated to API STD 617, 8th Edition.
Page 38 of 38