following tasks on machines M1 and M2 in the order M1, M2. Using Johnson’s rule
find the minimum total elapsed time. Also find the machine idle hours.
(2.5 Marks)
Task A B C D E F G H I
M1(hrs) 2 5 4 9 6 8 7 5 4
M2(hrs) 6 8 7 4 3 9 3 8 11
1
2) Find the sequence that minimizes the total elapsed time required to complete the
following tasks on the machines in the order Machine 1 and Machine 2. Find the total
elapsed time and the idle time on the machines. (2.5
Marks)
2
3) A project schedule has the following characteristics: (2.5 Marks)
Task Precedence Duration (hrs.)
A --- 4
B A 1
C A 1
D B, C 1
E C 6
F E 5
G E 4
H F, G 8
I D 1
J H, I 2
3
4) The project whose activities and the three time estimates of these activities (in weeks)
are given below. Compute (2.5 marks)
1) The critical path
2) Critical activities.