APQP Final Procedure
APQP Final Procedure
APQP Final Procedure
Doc. No.:
SEI/DEV/PRO/41
Revision No.:01
Effective Date:10.05.2018
Page No.: 1 of 9
QUALITY SYSTEM PROCEDURE
PURPOSE
This Procedure is to be defining new product development and Changes in existing Parts and to
define the process needed for the Product Quality planning process to ensure that:
1. Resources are directed to satisfy the customer.
2. To promote early identification of problems / changes to avoid late changes
3. To provide a quality product on time at the lowest cost.
4. Use of CFT approach & Simultaneous engineering during design and development of the
process.
5. To Ensure flaw less launch
SCOPE
CATEGORY DETAILS
AA Absolutely new component : no Experience of Production so far
That the part happens to be similar to what had been produced so far but there happens to be
A large scale difference in raw material, Machining Methodology, In the structure or in the
function.
B That whenever there happens to be a minor deviation in the component produce so far (To
implement only for inspection of initial product) ECN & DCN parts
That whenever there happens to be extremely Process change in details related to the
C component ,so much so that even the inspection becomes non mandatory(It becomes more of
checks in regard to monitoring of the points of variation in regard to 4M(M/c Procurements &
Supplier change).
D That whenever there happens to be changed in production site
RESPONSIBILITY
It is the responsibility of the MR to ensure that this procedure is latest, implemented and
understood by all appropriate personnel across the organization.
Prepared By: Reviewed and Approved By:
SEI SHRI RAM ENGINEERING INDUSTRY
Doc. No.:
SEI/DEV/PRO/41
Revision No.:01
Effective Date:10.05.2018
Page No.: 2 of 9
QUALITY SYSTEM PROCEDURE
It is the responsibility of the CFT & relevant functional heads to ensure that this procedure is
implemented in their respective departments.
PROCEDURE
Review Time:
CFT Review: CFT Members will review the project status every 10 days & the same will be
recorded in MOM. If any delay found it will be reviewed & corrective action planned. Timing
plan also updated accordingly if required.
After Sample Submission CFT Team shall be review the project month wise instant of date.
CFT Members shall appraise the Top Management about the status and analysis for any variance
to provide further appropriate supports (Interims of Resource Requirements) and the same are
mounted in Management Support & Review Meeting Report for Long duration project shall be
reviewed month wise instead of phase wise.
REFERENCES - DOCUMENTS:
6 New Product Development Micro Plan SEI/DEV/F-04A Till the product is alive
7 Management support & Review Meeting SEI/MGT/F-15 5 yrs
8 Quotation Free format Till further revision
9 Purchase Order Free format Till further revision
10 List of new equipment’s / Tooling / SEI/DEV/F-27 Till Next Status
Gauges / Facilities
11 Packaging standards / specifications SEI/DEV/F-11 Till further revision
12 Process flow diagram SEI/DEV/F-07 Till further revision
13 List of Special Characteristics Matrix SEI/DEV/F-24 Till further revision
14 Potential Process FMEA SEI/DEV/F-08 Till further revision
15 Control Plan- Prelaunch SEI/DEV/F09 Till further revision
• - Customer Representative shall maintain copies of the above records in the APQP file for each
part.
AMENDMENT SHEET
Re
v Date Change Description Reason for Change Remarks
No.
00 New Release