1.1 Terms and Definitions Direct Test
1.1 Terms and Definitions Direct Test
1.1 Terms and Definitions Direct Test
INTRODUCTION
1.1 Terms and definitions
Direct Test
Test in which the applied voltage, the current and the transient and power-frequency
recovery voltages are all obtained from a circuit having a single-power source, which
may be a power system or special alternators as used in short-circuit testing stations
or a combination of both.
Synthetic Test
Test in which all the current, or a major portion of it, is obtained from one source
(current circuit) and in which the applied voltage and/or the recovery voltages
(transient and power frequency) are obtained wholly or in part from one or more
separate sources ( voltage circuits).
Auxiliary circuit-breaker(s)
Circuit-breakers) forming part of a synthetic test circuit used to put the test circuit-
breaker into the required relation with various circuits.
Current circuit
That part of the synthetic test circuit from which all or the major part of power-
frequency current is obtained.
Voltage circuit
That part of the synthetic test circuit from which all or the major part of the applied
voltage and/or recovery voltage is obtained.
1
Current - injection method
Synthetic test method in which the voltage circuit is applied to the test circuit-breaker
before power-frequency current zero.
Voltage-injection method
Synthetic test method in which the voltage circuit is applied to the test circuit-breaker
after power-frequency current zero.
Injected current
Current supplied by the voltage circuit of a current injection circuit when it is
connected to the circuit-breaker under test.
Post-arc current
Current which flows through the arc gap of a circuit breaker when the current and
arc voltage fallen to zero and transient recovery voltage has begun to rise.
Amplitude factor
The ratio between the maximum of transient recovery voltage to the crest value of
the power frequency recovery voltage.
2
Restriking Voltage
The transient voltage which appears across the breaker contacts at the instant of arc being
extinguished is known as restriking voltage.
Recovery Voltage
The power frequency rms voltage, which appears across the breaker contacts after the arc is
finally extinguished and transient oscillations die out, is called recovery voltage.
3
instant of cessation of post-arc current
~ hieh-currcnt interval
4
capability, is limited in its power to perform the direct tests. At the present time a
complete pole of SPY, circuit-breaker can consist of a single interrupting chamber with
an interrupting power above the 10GVA level. Even KEMA’S high power laboratory
can not verify the short-circuit interrupting capability by direct test methods.
The limitations of direct testing using the power system or short-circuit alternators
are as follows:
• High cost of installation of testing stations
• Availability of limited power for testing of high voltage and Extra high
voltage circuit-breakers
• Requires high power for testing circuit-breakers
• Flexibility of the system available is limited.
Therefore Indirect methods of testing are used for testing of large circuit-breakers.
Direct testing facility available at CPRI high power laboratory in India is of
2500MVA capacity at 36/72.5kV in three phase and 1400MVA capacity, up to 245kV
in single phase for testing of circuit-breakers.
The Indirect testing methods can be classified as Unit testing and synthetic testing
Unit testing means testing one or more units separately. Generally, high voltage circuit-
breakers are designed with several arc interrupter units in series. Each unit can be tested
separately. From the test results of one unit, the capacity of the complete breaker can
be determined.
The unit testing method is used in laboratory to test Extra and ultra high voltage
circuit-breakers at present. With this method, interrupting units are tested at a part of
rated voltage of the complete breaker. This method is recognized by the IEC standard,
but one major problem remains, namely the influence of the post-arc conductivity on
the voltage distribution across the units. The trend of increasing the interrupting
capability of a single interrupting unit will result in it being impossible to test a
single unit in the high power laboratory.
Synthetic testing is an alternative equivalent method for testing of high voltage
circuit-breakers and is accepted by the various standards.
At present, synthetic testing facility for testing high voltage circuit breakers at CPRI
high power laboratory, Bangalore is only up to 245kV, 63kA rating circuit breakers.
5
In this research work, 4-parameters TRV synthetic testing circuit has been proposed
for testing circuit breakers of ratings up to 800kV for both terminal fault and short
line fault test conditions with optimized circuit components according to new TRV
• Detailed study about TRV rating concepts, TRV circuits, IEC standards TRV
envelopes and standard values of TRV parameters for a particular ratings of
circuit-breakers.
• Short circuit tests require circuit with response specified by IEC standards for
2 - Parameters and 4 -Parameters TRV envelopes.
• To design and simulate 4-parameters TRV synthetic testing circuit for testing
circuit-breakers of rating up to 800kV for both Terminal and short-line fault
test duty conditions with optimized circuit components according to new TRV
descriptions or parameters given in IEC 62271-100.
6
• To design and simulate various 4-parameters TRV control circuits based on
parallel current injection method for a 245kV and 420kV rating circuit-breakers
as per new TRV descriptions or parameters given in EEC 62271-100 for
comparison purpose.
The research work reported in this thesis has been focused on the analysis, design,
simulation and development of synthetic test circuits ( TRV shaping circuits) with
automatic controller and triggering circuit for testing high and extra high voltage
circuit-breakers of ratings up to 800kV according to IEC standards.
The work reported in this thesis has been organized into 8 chapters. The contents of
each chapter are presented in brief in the following paragraphs.
Chapter 2 reviews and reports various methods of testing circuit-breakers and their
comparison, necessity of synthetic testing for circuit-breakers, comparison of various
synthetic test circuits. It also covers the literature surveyed during the work carried
out.