PMP Certi Cation All-In-One For Dummies Cheat Sheet
PMP Certi Cation All-In-One For Dummies Cheat Sheet
Careers Project Management PMP Certi cation All-In-One For Dummies Cheat Sheet
Cheat Sheet
Looking at a career as a certi ed Project Management Professional (PMP)? This Cheat Sheet
gives you quick, handy PMP certi cation facts to remember on test day to help you answer
exam questions. You can review major project management concepts; key tools, techniques,
outputs, and processes; and and some common equations found on the exam. Many key terms
are de ned in the Project Management Body of Knowledge (PMBOK) Guide Glossary.
When you’re ready to take the PMP (Project Management Professional) Certi cation exam,
expect to see up to ten questions dealing with network diagrams, precedence diagramming,
and scheduling issues. Here are some PMP details you need to know:
FS = Finish-to-start
FF = Finish-to- nish
SS = Start-to-start
SF = Start-to- nish
https://www.dummies.com/careers/project-management/pmp-certification-all-in-one-for-dummies-cheat-sheet/ 1/6
8/26/2020 PMP Certification All-In-One For Dummies Cheat Sheet
Lead = The amount of time an activity can be advanced with respect to a predecessor
activity
Lag = The amount of time a successor activity is required to be delayed with respect to a
predecessor activity
You can apply PMP (project management professional) estimating techniques to resources,
e ort, duration, and costs. PMPs use di erent methods of estimating, depending on the
situation.
Analogous estimating Generally used at the start of the project when not much is
known. Compares the current project with past similar projects. A
quick and relatively easy method of estimating, although not
terribly accurate.
Parametric estimating Used for estimates that are quantitatively based, such as
dollars per square foot or number of installations per day. A
relatively simple method, but not every activity or cost can be
estimated quantitatively.
https://www.dummies.com/careers/project-management/pmp-certification-all-in-one-for-dummies-cheat-sheet/ 2/6
8/26/2020 PMP Certification All-In-One For Dummies Cheat Sheet
Bottom-up estimating Used when there is signi cant detail about the activity. A
detailed assessment of the resources, capabilities, and amounts are
used to determine an accurate duration or cost estimate. This is
the most accurate method but also the most time-consuming and
expensive form of estimating.
PMPs (project management professionals) often apply basic statistics to their projects. For the
PMP certi cation exam, here’s what you need to know when dealing with normal and
cumulative distributions:
Equations are based on a normal distribution. In a normal distribution, keep the following in
mind:
If you’re looking at a normal curve and need a cumulative distribution, you should remember
these values:
0.15% of the data points fall between 0 and –3 from the mean.
2.25% of the data points fall between 0 and –2 from the mean.
16% of the data points fall between 0 and –1 from the mean.
84% of the data points fall between 0 and +1 from the mean.
97.75% of the data points fall between 0 and +2 from the mean
99.85% of the data points fall between 0 and +3 from the mean.
https://www.dummies.com/careers/project-management/pmp-certification-all-in-one-for-dummies-cheat-sheet/ 3/6
8/26/2020 PMP Certification All-In-One For Dummies Cheat Sheet
Experienced project management professionals (PMPs) know that as they plan and execute
projects, they’ll encounter con icts and di erences of opinion. As you study for your PMP
certi cation exam, become familiar with these six strategies to resolve con ict.
Confronting / Confronting the con ict as a problem to When you have con dence in the
Problem-solving be solved other party’s ability to
problem solve
When the relationship is important
When you need a win-win solution
Collaborating Win-win through collaboration and When there is time and trust
meeting to resolve When the objective is to learn
issues When you want to incorporate
multiple views
When there is time to come to
consensus
Compromising When you are looking for some degree When there is a willingness to give
of satisfaction for both and take
parties When both parties need to win
When you can’t win
When an equal relationship exists
between the parties in
con ict
When the stakes are moderate
To avoid a ght
https://www.dummies.com/careers/project-management/pmp-certification-all-in-one-for-dummies-cheat-sheet/ 4/6
8/26/2020 PMP Certification All-In-One For Dummies Cheat Sheet
On the PMP certi cation exam, you’ll see ve to ten questions on variances and indexes. Here’s
fundamental information that project managers need to determine cost and schedule variances
and indexes.
SV = EV – PV
CV = EV – AC
SPI = EV / PV
CPI = EV / AC
There are many ways to assess quality control, and professional project managers (PMPs) make
good use of them. When you take the PMP certi cation exam, you should be able to apply the
following quality control tools:
Cause and e ect diagram. Diagrams that de ne the inputs to a process or product in
order to identify potential causes of defects.
https://www.dummies.com/careers/project-management/pmp-certification-all-in-one-for-dummies-cheat-sheet/ 5/6
8/26/2020 PMP Certification All-In-One For Dummies Cheat Sheet
Control chart. A graphic display of process data over time and against established control
limits, and that has a centerline that assists in detecting a trend of plotted values toward
either control limit.
Flowcharting. The depiction in a diagram format of the inputs, process actions, and
outputs of one or more processes within a system.
Pareto chart. A histogram, ordered by frequency of occurrence, that shows how many
results were generated by each identi ed cause.
https://www.dummies.com/careers/project-management/pmp-certification-all-in-one-for-dummies-cheat-sheet/ 6/6