PR808-01 Civil Works
PR808-01 Civil Works
PR808-01 Civil Works
T S
K J
CONSTRUCTION
A Chopra
Checked By:
D Gevaux D Gevaux
Approved By:
(Executive Project Manager)
JP Oppenheim JP Oppenheim
Date:
Pages Revised: 4,8,9,11,12,13
& forms
NOTE: Type in date, and initials and sign the appropriate box for the current revision.
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 2 of 13
TABLE OF CONTENTS
1.0 OBJECTIVE
2.0 QUALITY CONTROL PROCEDURES
3.0 INSPECTION AND TEST PLANS
4.0 RESPONSIBILITIES
5.0 IMPLEMENTATION
5.1 Reinforcement steel
5.2 Anchor Bolts
5.3 Water
5.4 Cement
5.5 Admixtures
5.6 Aggregates
5.7 Other Civil Materials
5.9 Concrete Placement
5.10 Fill Placement and Compaction
5.11 Foundation Settlement
5.12 Asphalt Surfacing
5.13 Concrete Products (Pre-Cast Units)
5.14 Quality Control Testing Performed by Subcontractor
5.15 Surveying
6.0 RECORDS
7.0 REFERENCES
8.0 QUALITY CONTROL FORMS
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 3 of 13
1.0 OBJECTIVE
The purpose of this procedure is to outline the project quality requirements
pertaining to Civil Works and to provide documents for use by the
Subcontractor, Contractor and Company to record necessary data to ensure
correct materials, installation, workmanship, inspection and testing was
accomplished, witnessed and approved as required by project specifications.
4.0 RESPONSIBILITIES
The subcontractor is responsible for implementing a quality assurance/quality
control program, which includes 100% inspection and documentation of the
work. The Contractor area engineers and supervisors will provide assistance to
the subcontractors as needed and will provide full time surveillance of the work
in progress. The engineers will attend the Hold, Witness and Random
inspection and the Records Review as shown on the subcontractors' inspection
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 4 of 13
and test plan.
The Contractor QA personnel will audit and monitor the quality
control/inspection of the work. The QC and NDE personnel will conduct
inspections of welding and civil operations and will perform the non-destructive
examinations required by project specifications. Contractor QA/QC will
determine if the inspections are being performed in a competent and
satisfactory manner and that the relevant documentation is being prepared,
signed and maintained in a retrievable manner.
5.0 IMPLEMENTATION
5.3 Water
Subcontractor shall perform water analyses via an Independent Test Laboratory
as per the applicable British Standard at the frequency specified in the Project
Specification Amendment. Results shall be reported on Form PR 808-01-A18
or as per the Independent Test Laboratory Format. Subcontractor QC shall
confirm on a daily basis that only water from approved sources is used in the
concrete and grout mixes. Additional tests on water shall be conducted by the
Subcontractor as per the Project Specification Amendment, where required.
5.4 Cement
Cement shall be tested to prove compliance with applicable Standards as
required in the Project Specification and Amendment. Subcontractor shall retain
MTRs of each delivery of cement to the batch plant to confirm that all cement
has been tested and meets these requirements. Cement shall not be received
without the proper test certificate.
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 5 of 13
For cement older than three (3) months, Subcontractor shall conduct the
required tests specified in the Project Specification Amendment and shall
prepare Form PR 808-01-A17 , PR 808-01-A17.1 or Independent Test
Laboratory for Contractor approval.
5.5 Admixtures
Use of admixtures in concrete shall be subject to Contractor approvals.
Admixtures shall meet the requirements of the Project Specification and the
referenced ASTM standard.
Subcontractors supplying ready-mix concrete shall retain manufacturer and
laboratory certificates of all admixtures approved to verify that admixtures
supplied for use in the concrete is the same as those subjected to the required
testing.
5.6 Aggregates
All aggregates shall be tested and approved prior to use in a concrete mix.
Subcontractor shall be responsible for daily inspection and periodic testing of
materials during receipt and stockpiling operation.
Subcontractors supplying ready-mixed concrete shall issue test certifications to
Contractor to verify that aggregates to be used in concrete comply with Project
Specifications.
The following forms may be used to document test results. This is not an all
inclusive list of tests that will be required on concrete materials. Tests
performed by offsite Independent Test Laboratories (ITL) may be submitted on
ITL forms.
Note: Combined aggregates grading is not recommended for use for concrete
grades C20 or higher.
PR 808-01-A9 : Sieve Analysis of combined aggregates
(including organic impurities )
PR 808-01-A15 : Sieve Analysis of Aggregates
PR 808-01-A20-01 : 10% Fines Value
PR 808-01-A26 : Material <75 Microns
PR 808-01-A39 : Chemical Analysis of Aggregates
PR 808-01-A44 : Clay Lumps Test
PR 808-01-A45 : Soundness test
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 6 of 13
5.8 Concrete Mixes
After receiving approval from the Contractor of (1) source of materials (2) the
ingredients to be used, and (3) proposed mix quantities, Subcontractor shall
prepare and test trial mixes. The trial mixes shall be in accordance with DEP
34.19.20.31,APPENDIX 2. A guideline for a mix design report and durability
RILEM test method are reported on forms PR-808-01-A46 and A21.The
potential for alkali-aggregate reactivity (ASTM C 289) and coal/lignite content
( ASTM C123 ) shall be investigated by the third party laboratory for initial
approval and anytime there is a changing of source of the aggregates. Results
of the trial mixes must be submitted to Contractor for approval not less than 30
days prior to the scheduled start of concrete construction.
Each of these steps shall be included on Subcontractor inspection and test plan
and will be witnessed by Contractor. Each design mix must be approved by
Contractor prior to use in permanent plant constructions.
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 7 of 13
signed the Mix Order forms after mixing is complete.
When ready to deliver a mix the batch plant shall issue a Delivery Note, form
PR 808-01- A16, also indicating the sequential number of the relevant Mix
Order as well as its own. This shall be transported with the driver to the point of
placement. The concrete foreman will sign the note and the driver will return it
to the batch plant for filling.
Subcontractor shall issue a Concrete docket, detailing information about the
placement, Form PR 808-01-A27. This shall indicate both Mix Order and
Delivery Note numbers in addition to its own. Each separate concrete pour
shall have its own Concrete Docket (so it is possible that a given delivery will
cover more than one pour). When a pour requires more than one delivery a
separate page of the Concrete Docket shall be used and numbered as ‘sheet x
of y’ in the series for the particular pour. Any forms used to record sample
taken for fresh concrete tests shall also indicate the relevant Concrete Docket
number. Subcontractor shall attach the Concrete Dockets to the matching Pre-
placement forms on his files.
Suppliers of ready-mixed concrete shall allocate a sequential batch number to
all batches of concrete supplied and clearly indicate on the delivery docket the
applicable reference number. In the case of Subcontractor-supplied ready-
mixed concrete, docket number should be prefixed with the Subcontract
identifier (number).
Supplier of ready-mixed concrete shall maintain copies of details of mix
proportions of concrete batches dispatched.
Batch plant detail shall as a minimum display the time, date, mix components,
batch number and quantity of each batch, as well as subcontract number to
which the concrete was delivered.
Subcontractor shall document each fresh concrete test results on the following
forms:
Subcontractors shall document each hardened concrete test result using the
forms PR808-01-A10, A22, A29. Relationship between the rebound values and
compression test of cubes shall be maintained. The results of each test are to
be submitted to Contractor’s QA/QC Manager after completion of seven (7) and
twenty-eight (28) day tests for each set of cubes. Failure of any sample to meet
the specified strength shall be reported immediately to the QA/QC Manager,
who will notify the Site Technical Manager for resolution. Non-conforming test
results shall be documented per Procedure PR 809, Non-Conformance
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 8 of 13
Reports.
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 9 of 13
Contractor’s Site Technical Manager shall be responsible for designating which
foundations shall be checked for settlement. It is anticipated that this shall
include major foundations and any suspect areas.
Contractor’s nominated Surveyor shall be responsible for implementing
settlement readings on the designated foundations and recording all readings
on Foundation Settlement Form (Form PR 808-01-A6).
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 10 of 13
c) type of test
d) test report number
e) result of test.
A master set of Civil Plot Plans with areas marked up to reflect location of all
acceptance testing performed shall be maintained by Subcontractor and
available for Contractor review.
5.15 Surveying
Subcontractor will carry out general surveying and levelling using modern and
properly calibrated equipment and by employing suitably qualified surveyor(s)
on site.
Using appropriate surveying and levelling methods, all excavation to foundation
bases, pile caps, sewer boxes, plinth blocks, walls, pipework and paving will be
checked and results recorded in the survey log (PR 808-01-A11).
For finished concrete surfaces, invert levels for pipework and paving to required
falls, surveying checks will be carried out and the surveyor will be required to
complete the standard form PR-808-01-A11 - Surveying Log. Such forms,
where required, will be provided with other relevant quality control documents
for Contractor’s verification and final submission.
The surveyor will carry out periodical calibration checks on surveying
instruments - theodolite, EDM, and level, and will maintain the records of such
calibrations by completing the forms PR-808-01-A12, PR-808-01-A13 and PR-
808-01-A14 or approved equivalent forms as per the Subcontractors Inspection,
Measuring & Testing Equipment Procedure.
The final locations and projections of anchor bolts are critical and surveying
techniques must establish these projections and locations within the tolerances
dictated by the Project Specifications.
6.0 RECORDS
The subcontractors' quality system shall provide procedures to assure that
sufficient records are maintained to verify that the requirements of the
subcontract documents have been fully met. He will obtain the required
signatures of the Contractor and will maintain all documentation required for
handover of the work.
7.0 REFERENCES
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 11 of 13
DEP 34.13.20.31-Gen + T-12.416.009 Roads, Paving, Surfacing, Slope
Protection and Fencing
DEP 34.19.20.31-Gen + T-12.416.015 Reinforced Concrete Foundations and
Structures
Project Procedures As applicable to subcontract scope of work
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 12 of 13
PR 808-01-A21 : Impermeability Test on Concrete Cubes
PR 808-01-A22 : Rebound Hammer Test on Concrete Cubes
PR 808-01-A23 : Temperature of All Constituents of the Mix
PR 808-01-A24 : Fresh Concrete Testing in the Laboratory
PR 808-01-A25 : Moisture Content of Aggregates
PR 808-01-A26 : Material < 75 Microns
PR 808-01-A27 Mix Order and Pour Docket Combined
PR 808-01-A28 : Flakiness and Elongation Index
PR 808-01-A29 : Concrete Statistical Analysis
PR 808-01-A29-01 : Concrete Statistical Trend
PR 808-01-A30 : Grouting for Steel Structures and Equipment
PR 808-01-A31 : Bitumen Analysis & Extraction Test
PR 808-01-A32 : Computation of Properties of Asphalt Mixtures
PR 808-01-A33 : Computation of Properties of Asphalt Mixtures
PR 808-01-A34 : Bitumen Spray Test
JP 1000 NLG
Procedure PR 808-01
/conversion/tmp/scratch/489886083.doc
Nigeria LNG Limited Civil works
Natural Gas Liquefaction Complex Revision B2
Bonny Island, Nigeria Page 13 of 13
PR 808-01-A52 : Determination of In-situ Density ( Sand Cone Method )
PR 808-01-A53 : Determination of Compressive Strength
PR 808-01-A54 : Determination of Unconfined Compressive Strength
PR 808-01-A55 : Sand Cement Stabilisation Rate of Spread
PR 808-01-A56 : Grouting for Platipus Anchor
PR 808-01-A57 : Water Proofing Work Construction Inspection Report
PR 808-01-A58 : Masonry Works Rendering Mortar Compressive Tests
PR 808-01-A59 : Masonry Works Erection Mortar Compressive Tests
PR 808-01-A60 : Sand Equivalent Value of Soil and Fine Aggregates