Inspection Requisition / Report

The document is an inspection requisition report for grouting work for a proposed 6-storey data centre building project. It lists no items to be inspected and requests inspection of the grouting work. The inspection is to check if the work meets contract specifications and drawings. Space is provided for client representatives to sign off to release, conditionally release, or hold the work for re-inspection.

Uploaded by

Hanuman Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views2 pages

Inspection Requisition / Report

The document is an inspection requisition report for grouting work for a proposed 6-storey data centre building project. It lists no items to be inspected and requests inspection of the grouting work. The inspection is to check if the work meets contract specifications and drawings. Space is provided for client representatives to sign off to release, conditionally release, or hold the work for re-inspection.

Uploaded by

Hanuman Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Inspection Requisition / Report

(OC-F601-1-02-7, Rev 1)

Client : Gammon Pte Ltd QA/QC Insp . No: TTJ/ 2333/ GR-001
Attn. : Mr. Andy Chan Type of Inspection : Grouting

Project : J300 Proposed 6-Storey Data Centre with Underground Fuel Storage
Tanks at Woodlands Avenue 12 Date :
W/O : 2333 Time :
Area / Building : Location : Site
Sheet : 1 of 1

S/No. Size / Mark no. Rev. Qty. Item Description Area Remarks

We request / notify the inspection for the abovementioned work. The work has been inspected/reviewed by our in-house shop fabrication supervisors, engineers and
QA/QC personnel, found satisfactory in all respect accordance to the drawings & contract specifications requirements.
Inspected / Reviewed by :

TTJ - QA/QC (Name/Date)

* To be completed by client's representatives


( ) We have inspected/witness/reviewed the abovementioned work and found accordance to the approved drawings, contract specifications requirements.
See comments (if any)
Comments :
( ) Inspected & released for further operation
( ) Inspected with comments (see below)
( ) Hold for re-inspection

Witnessed / Reviewed by : Witnessed / Reviewed by : Witnessed / Reviewed by :

ITA (Welding Inspector) Gammon Pte Ltd Consultant Representative


Name / Signature / Date Name / Signature / Date Name / Signature / Date
Inspection Requisition / Report
(OC-F601-1-02) (Rev.01 - 15/04/03), Page 1 of 1

Client :Kimly - Shimizu JV QA/QC Insp. No:TTJ/2288/GI-001


Attn : Type of Inspection : Galvanizing Inspection
Project :Yishun Community Hospital @ Yishun Central Date :
W/O :2288 Time :
Area/ Building:All Location : TTJ Workshop
Sheet : 1 of 1

S/No. Size / Mark no. Qty Rev Item Description Location Remarks

We request / notify the inspection for the abovementioned work. The work has been inspected/reviewed by our in-house shop fabrication supervisors,
engineers and QA/QC personnel, found satisfactory in all respect accordance to the drawings & contract specifications requirements.

Inspected / Reviewed by :

TTJ - QA/QC (Name/Date)

* To be completed by client's representatives


( ) We have inspected/witness/reviewed the abovementioned work and found accordance to the approved drawings, contract specifications requirements.
See comments (if any)
Comments :
( ) Inspected & released for further operation
( ) Inspected with comments (see below)
( ) Hold for re-inspection

Witnessed / Reviewed by : Witnessed / Reviewed by : Reviewed by :

ITA Representative Client's Representative Owner's representative


Name / Signature / Date Name / Signature / Date Name / Signature / Date

You might also like