Mohaupt High Voltage GMBH, Austria: P. Mohaupt, K. Misteli, H. Geyer
Mohaupt High Voltage GMBH, Austria: P. Mohaupt, K. Misteli, H. Geyer
79
Nordic Insulation Symposium - Nord-IS 13 - Trondheim, Norway, June 9 - 12, 2013
demodulator (SVU) Although all components of high and extra high voltage
cables for transmission systems are factory routine
tested before deployment, this does not guarantee a
flawless operational start or continued operations for the
resonator
inductor complete transmission system. The dependency on a
high voltage infrastructure is ever increasing and
disruptions in transmission are affecting more and more
power users, hence becoming less accepted. The change in grid
modul topology resulting from the increasing amount of
renewables installed, adds to the complexity of the
situation. With the trend to deliver longer cables without
exciter joints to reduce time, effort, cost and – at the same time
Fig. 2: Working principle DRT system – increased reliability of the cable system it is a logical
consequence that thorough testing of the completely
installed system is required The network owners and
Additionally, a DRT system can also do testing at DC operators usually do not accept anymore the traditional
by charging a capacitive load with a charging current of existing solutions such as “24 hour soak tests” or partial
up to several Ampere. A controlled discharge is testing of systems as a final test. The DRT technology
achieved by applying the same constant, but reversed, provides a very cost effective, fast and technologically
current to the test setup. This is realised in one system simple and reliable solution to this problem.
together with a standard DRT setup. Fig. 3 shows the
voltage at the resonance circuit (pink) and at the
output/test object (yellow).
80
Nordic Insulation Symposium - Nord-IS 13 - Trondheim, Norway, June 9 - 12, 2013
excessive losses. This required the installation of [4] Patent WO PCT/AT09/00211 00, VLF Test
offshore transformers at a central connection point and a Generator
high-voltage AC connection to the transmission network [5] Patent WO PCT/AT09/00212 00, VLF Test
on-shore, a practice that has now been operational for Generator
some years [9]. [6] W. Kemmetmüller, A. Kugi, “Mathematical
With even larger wind farms and even further offshore Modelling and Analysis of a DRT-VLF High
the transmission links became more powerful and Voltage Test Generator”, e&i – Elektrotechnik und
longer, driven by the continuously increasing power of Informationstechnik, to appear, 2011
the individual windmill and the number of windmills [7] Statnett, What is the value of avoiding overhead
within the parks. These powerful links served multiple lines, Internal publication,
wind farms off-shore and required a direct connection to www.statnett.no/en/About-Statnett/Research-and-
the high voltage transmission grid to avoid bottlenecks innovation-/What-is-the-value-of-avoiding-
in the integration with the existing transmission overhead-lines
infrastructure. These very high capacity wind farms [8] R. Schrott, State of the Art of HV/UHV power
currently favour HVDC connections to the shore and the cables. Elektra 229. 2006
use of AC connections for infield cables. [9] Tennet CDV 09-076 Positioning Paper Infra op Zee,
page 4. Internal publication
As a consequence of this development the need for
testing offshore high voltage AC and DC cables has
strongly emerged, increasingly even more supported by
latest developments in wind farms technology.
81