Suki Kinari To Maira 500kV DC T/L (Approx. 170km) : Assignment - A: Engineering Design and Tendering

This document outlines the engineering design and tendering process for a 170km 500kV transmission line between Suki Kinari and Maira in northern Pakistan. The process includes: 1) reviewing existing data, surveying the route, and conducting geotechnical investigations; 2) developing the transmission line plan, profile, and structure list; 3) designing the hardware, foundations, and specifications; 4) preparing tender documents; 5) opening the project to bidding for 60 days; and 6) evaluating bids and awarding contracts over 75 days. The entire process from commencement to contract award is scheduled to take 272 days, from October 2018 through September 2019.

Uploaded by

tayyab zafar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views

Suki Kinari To Maira 500kV DC T/L (Approx. 170km) : Assignment - A: Engineering Design and Tendering

This document outlines the engineering design and tendering process for a 170km 500kV transmission line between Suki Kinari and Maira in northern Pakistan. The process includes: 1) reviewing existing data, surveying the route, and conducting geotechnical investigations; 2) developing the transmission line plan, profile, and structure list; 3) designing the hardware, foundations, and specifications; 4) preparing tender documents; 5) opening the project to bidding for 60 days; and 6) evaluating bids and awarding contracts over 75 days. The entire process from commencement to contract award is scheduled to take 272 days, from October 2018 through September 2019.

Uploaded by

tayyab zafar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

500kV TRANSMISSION LINES INTERCONNECTION ARRANGEMENT FOR POWER EVACUATION FROM SUKI KINARI, KOHALA AND MAHL HYDROPOWER 

PROJECTS IN NORTHERN AREAS OF PAKISTAN
ASSIGNMENT – A: ENGINEERING DESIGN AND TENDERING
Suki Kinari to Maira 500kV DC T/L (approx. 170km)
WBS ID Task Name Baseline Dur. Start Finish 2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov D
A1 Line Segment (Suki Kinari ‐ Maira) 272 days Mon 10/29/18 Tue 9/10/19
A1.1 Commencement of Services 0 days Mon 10/29/18 Mon 10/29/18 Oct 29 '18
A1.1.1 Commencement of Services 0 days Mon 10/29/18 Mon 10/29/18 Oct 29 '18
A1.2 Review of existing information and data  26 days Thu 11/1/18 Fri 11/30/18
A1.2.1 Review of existing information and data  26 days Thu 11/1/18 Fri 11/30/18 Nov 1 '18 Nov 30 '18
A1.3 Transmission Line route alignment and detailed survey 116 days Thu 11/1/18 Fri 3/15/19

A1.3.1 Transmission Line route alignment and detailed survey 116 days Thu 11/1/18 Fri 3/15/19 Nov 1 '18 Mar 15 '19

A1.4 Geotechnical, geohazard and soil resistivity investigations 49 days Fri 2/1/19 Fri 3/29/19

A1.4.1 Geotechnical, geohazard and soil resistivity investigations 49 days Fri 2/1/19 Fri 3/29/19 Feb 1 '19 Mar 29 '19

A1.5 Transmission Line Plan and Profile and Structure List 63 days Fri 2/1/19 Mon 4/15/19

A1.5.1 Transmission Line Plan and Profile and Structure List 63 days Fri 2/1/19 Mon 4/15/19 Feb 1 '19 Apr 15 '19

A1.6 Conductor and Span Utilization 50 days Thu 11/1/18 Fri 12/28/18


A1.6.1 Conductor and Span Utilization 50 days Thu 11/1/18 Fri 12/28/18 Nov 1 '18 Dec 28 '18
A1.7 Preparation of Engineering Design 145 days Mon 10/29/18 Mon 4/15/19
A1.7.1 Collection of Data and Investigations 132 days Mon 10/29/18 Sat 3/30/19 Oct 29 '18 Mar 30 '19
A1.7.2 Insulation Coordination Study 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.3 Design of Hardware and Damping System 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.4 Design of Tower Family and Foundations 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.5 Preparation of Project Specifications 77 days Tue 1/1/19 Sat 3/30/19 Jan 1 '19 Mar 30 '19
A1.7.6 Preparation of BoQ and Costing 29 days Wed 3/13/19 Mon 4/15/19 Mar 13 '19 Apr 15 '19
A1.8 Preparation of Tender Documents 90 days Tue 1/1/19 Mon 4/15/19
A1.8.1 Preparation of Tender Documents 90 days Tue 1/1/19 Mon 4/15/19 Jan 1 '19 Apr 15 '19
A1.9 Tendering (Bidding Period) 60 days Tue 4/16/19 Fri 6/14/19
A1.9.1 Tendering (Bidding Period) 60 days Tue 4/16/19 Fri 6/14/19 Apr 16 '19 Jun 14 '19
A1.0 Evaluation and Award of Contract(s) 75 days Sat 6/15/19 Tue 9/10/19
A1.0.1 Evaluation and Award of Contract(s) 75 days Sat 6/15/19 Tue 9/10/19 Jun 15 '19 Sep 10 '19

Page 1 of 1 
NESPAK Revision No.: 00
National Engineering Services of Pakistan Dated: Wed 1/9/19