Quiz I - 2017-Answers
Quiz I - 2017-Answers
Quiz I – Examination
Answer to questions
Total Marks : 25
1. Explain the Difference between the main and skirt pile jackets with neat sketches.
Installation of pile from above water condition using Installation is by means of underwater hammer (such
diesel type hammer (diesel hammer can only work in as hydraulic) and requires pile to be pitched in single
above water condition) piece.
Pile design for installation can be optimized by Pile design becomes complex due to single pile
dividing the length in to many pieces. length during installation
More offshore time required for welding pile pieces Less time as no offshore welding is envisaged
Piles have to be supported of the jacket during Pile is placed directly on to the seabed and thus
welding and thus putting the jacket in stability pinned to the soil.
related issues
More time is required for grouting the full length of Less time is required for grouting as the length of the
the jacket – pile interface grout is limited
1
2. Differentiate wind driven and tidal driven current with neat sketches.
The wind driven current variation with depth can be expressed as:
y
VW VoW
h
Where VW is the wind driven current at any height from sea bed, VoW is the wind driven current at the
surface, y is the distance measured in m from seabed and h is the water depth in m.
The tidal driven current variation with depth can be expressed as:
1
y 7
VT VoT
h
Where VT is the tidal current at any height from sea bed, VoT is the tidal current at the surface, y is the
distance measure in m from seabed and h is the water depth in m
The major parameters governing the geometry of the substructure are listed below.
2
4. Draw wind pressure variation on a tubular member for a wind speed of 50m/sec (at 10m above MSL) for
height extending from 10m to 50m and calculate the total force. Use 1/8th Power law for wind speed
variation along height.
3
5. Calculate the drag force due to wave and current on a submarine pipeline of diameter 500mm
subjected to a tidal driven current of 0.5m/sec near seabed and the wave induced velocity is
0.6m/sec. The drag coefficient for a submarine pipeline resting on seabed shall be taken as 0.7.
The wave and current approaches normal to the axis of pipeline.
4
Setting on bottom is to leave the jacket without crane assistance for a temporary phase. This is
required as the crane may be used to lift the pile or the hammer.
Pile driving is followed to secure the jacket on to the seabed
Levelling is an essential activity to make sure the jacket is perfectly or near vertical.
Grouting is carried out to fill the annulus space between the jacket and pile.
8. Estimate the deck structure elevation at a location where the HAT is 4m and the storm surge is 2m
and the 100 year storm wave height is 18.3m and the water depth is 30m. Crest height is to taken
as 72% of wave height.
Deck Elevation = HAT + Storm Surge + Wave Crest Elevation + Air Gap
= 4m + 2m + (0.72*18.3m) +1.5m = 20.676m
In addition, large lateral loads caused by wind, wave and current make the design far challenging
than the onshore structures.
10. A well head jacket is to be installed in a water depth of 50m. Draw typical elevation showing the
bracing arrangement and leg batter. Take work point elevation as 9m.