Methodology: CD WORKS: BOX, SLAB & PIPE Culvert
Methodology: CD WORKS: BOX, SLAB & PIPE Culvert
_____________________________________________________________________________
_
_____________________________________________________________________________
_
TABLE OF CONTENT
_____________________________________________________________________________
_
1.0 PURPOSE :
The purpose of this Segment Quality Plan for Construction of Cross Drainage
Works is to provide details of the Construction Methodology, Quality Assurance &
Control System/Procedures adopted by H.C.C. and its Sub-
contractor’s/Supplier’s etc. in execution of Cross Drainage Works i.e., Box, Pipe
and Slab Culverts etc. at various locations/stretches as shown in the
Construction Drawings.
This Segment Quality Plan for Flexible Pavement also consists a brief note on
proposed Traffic Safety and Environmental Management Practices/Plans
adopted by HCC and provides list of cross reference documents on the subject
matter for more details.
2.0 SCOPE :
The Scope of this Segmental Quality Plan covers the following activities:
3.0 DEFINITIONS :
The words like contract, Contractor, Engineer (Synonymous to Engineer’s
representative), Drawing, Employer, Government, Works, Worksite used in this
Quality Plan shall be considered to have the meaning as understood from the
definitions of these terms given in the General conditions of the contract.
The following abbreviations shall have the meaning as set forth below:
_____________________________________________________________________________
_
RCC : Reinforced Cement Concrete
BOQ : Bill of quantities
This Segment Quality Plan shall be read in conjunction with the following
documents:
5.0 RESPONSIBILITIES :
Responsible personnel for execution of the Segment of Cross Drainage Works
are as per the following Responsibilities Matrix and also as per the Project
Organization Chart:
_____________________________________________________________________________
_
approval / Site Engineer
All the Survey Instruments used shall be calibrated periodically as per Calibration
Plan. Survey Check Reports / other relevant data shall be maintained in relevant
Inspection formats.
Standard shuttering plates shall be used for inside and outside wall shuttering,
vertical props and cross bracings of sufficient strength shall be used to protect
any bulkage/deformation of concrete. All the joints will be properly sealed. PVC
joints, sealing tapes, foam, Rubber will be used in order to prevent leakage of
slurry. Weep holes shall be provided as per drawing and specification. Concrete
_____________________________________________________________________________
_
of required grade and specification shall be mixed at batching plant of capacity
30 Cu.M erected at 109 Km and transported to site by using Transit
Mixers/Tippers.
The Hume pipes shall be laid, as per drawing, where two or more pipes shall be
laid adjacent to each other; they shall be separated by distance as mentioned in
the drawing. The laying of pipe shall be carried out as per specification laid in
M.O.R.T.H clause 2904. The newly laid pipe shall be placed in such a way that
these will be joining gap of 13mm to 18mm.The our side and inside jointing gap
shall be filled with cement mortar in 1:2 ratio. Care shall be taken to fill all voids
of the joints from inside and outside and surplus mortar shall be removed. After
jointing of pipe as per M.O.R.T.H Clause 2906, the pipe shall be in a cradle
constructed of concrete in M 15 conforming to section 1700. The shape and
dimensions of the cradle shall be as per the drawing.
_____________________________________________________________________________
_
These Inspection and Test Plans shall consists of type of Inspection and name of
the Test to be conducted for Product Realization, frequency of testing,
acceptance criteria and category of Inspection as mentioned in the legend of ITP.
Inspection and Test Plans shall be revised whenever there is any change in
methodology and specifications etc. Various Field and Laboratory Test Formats
referred in Inspection and Test Plans shall be maintained as per the frequency
mentioned in respective ITP’s for various activities.
Any Non-Conformity observed during Field Inspection and also during Testing of
Materials the same Non-Conformity shall be recorded in the specified Format
and necessary Corrective/Preventive actions shall be initiated to prevent such
things in future.
8.0: ATTACHMENTS:
ITP for the Inspection of the segment:
ITP for the Testing of the segment: .
_____________________________________________________________________________
_