Periodicity for
Periodicity for Periodicity for
ERDMP Review and
S. No. Name of Installation T4S Audit IMS Audit
Certification
(Years) (Years)
(Years)
1 Refinery # 3 #
2 Gas Processing station # 3 #
3 LNG Re-gasification
# 3 #
Installation
4 Natural Gas Pipelines 3 5 3
5 Propane/ Butane
# 5 #
Pipelines
6 Liquid Petroleum
3 5 3
Product Pipelines
7 Petroleum Storage
# 5 #
Facilities
8 Gas Storage Facilities
and terminals including
# 5 #
storage facilities at LNG
Re-gasification terminals
9 Hydrocarbon gas
bottling Installations
having receiving,
storage and handling # 5 #
facilities including
storage for LPG,
propane and butane;
10 City or Local Natural
Gas Distribution 3 5 3
Network
11 Dispensing Stations and
# 5 #
retail outlets
12 Transportation of
Petroleum Products by # 5 #
road
13 Any other installation as
may be notified by the # # #
Board from time to time
Note: (1) The periodicity specified above is maximum period in which audit is to be carried out.
However, the audit/review may be carried out by the entity whenever there is a major change,
modification, debottlenecking, expansion etc in installation and also in consideration of factors like
type of technology, levels of automation, age of plant, changes in the neighborhood such as
demography, coming up of hospitals, places of large congregation etc having potential to alter risk
level or have an impact to response measures to a risk or as may be required under any other
applicable Statutes.
(2) The periodic third party audit under Integrity Management Regulations for natural gas pipelines
shall be carried out with reference to third party audits carried out earlier under T4S Regulations
and Integrity Management Regulations in order to examine and confirm the compliance of
mitigation of any non-conformity reported in the previous T4S / Integrity Management Audits and to
also look into compliance of provisions of T4S Regulations with respect to new connectivity/
facilities in the natural gas pipeline system which have come up subsequent to previous third party
audits.