Inspection and Test Plan: Tile Works

This document outlines the inspection and test plan for tile work on a construction project. It details 4 phases of work with inspection requirements: 1) material submittal and receiving, 2) installation, 3) cleaning and protection. Specific inspections include reviewing product data and samples, material receiving inspections, visual inspections of surface preparation and installation, and a final cleaning and protection inspection. Responsibilities are assigned to the subcontractor and contractor for inspections, with the US Corps of Engineers providing oversight.

Uploaded by

Alvene Tagoc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (4 votes)
980 views2 pages

Inspection and Test Plan: Tile Works

This document outlines the inspection and test plan for tile work on a construction project. It details 4 phases of work with inspection requirements: 1) material submittal and receiving, 2) installation, 3) cleaning and protection. Specific inspections include reviewing product data and samples, material receiving inspections, visual inspections of surface preparation and installation, and a final cleaning and protection inspection. Responsibilities are assigned to the subcontractor and contractor for inspections, with the US Corps of Engineers providing oversight.

Uploaded by

Alvene Tagoc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Title: CONSTRUCTION OF FACILITIES AND INFRASTRACTURE TO SUPPORT MH‐60R AIRCRAFT

Contract No.: W912ER18C0015 Revision No.: 00


Sub-Contractor : NABA INTERNATIONAL COMMERCIAL ENTERPRISES LTD. ITP No. : NICE-CIV-ITP-010

INSPECTION AND TEST PLAN : TILE WORKS


INSPECTION
INSPECTION TEST REQUIREMENTS REFERENCE DOCUMENTS
SL VERIFYING RESPONSIBILTY
ACTIVITY PHASE Test or REMARKS
No. DOCUMENTS Sub US Corps
Inspection Stage / Frequency Spec/Standards/Codes Acceptance Criteria Cntrctr
Cntrctr
of Engr.
Performed

1.0 MATERIAL SUBMITTAL


Review Material &
Product Data Project Specification Project Specification Approved Material
1.1 Floor and Wall Tiles Test Certificates from I I/R R/W
& Sample Sec 09‐30‐10 Part1.2 Sec 09‐30‐10 Part2 Test Report
the manufacturer
Review Material &
Product Data Project Specification Project Specification Approved Material
1.2 Tile Grout and Adhesives Test Certificates from I R R
& Sample Sec 09‐30‐10 Part1.2 Sec 09‐30‐10 Part2 Test Report
the manufacturer

2.0 MATERIAL RECEIVING


 Product Data
Test Report Project Specification
2.1 Material Receiving Inspection On delivery  Test Report  MRIR I w R
Delivery Note Sec 09‐30‐10 Part1.4
 Delivery Note

3.0 INSTALLATION
 Alignment and plumbs
are maintained in
Prior to start
Visual Project Specification horizontal and vertical  Inspection Request
3.1 Surface preparation installation of Floor I I W
Inspection Sec 09‐30‐10 Part3.0  IFC Drawing and  Quality checklist
and Wall Tiles
approved shop
drawing
 Alignment and plumbs
are maintained in
Prior to start
Installation of Floor and Wall Visual Project Specification horizontal and vertical  Inspection Request
3.2 installation of tile I I W
Tiles Inspection Sec 09‐30‐10 Part3.0  IFC Drawing and  Quality checklist
grout
approved shop
drawing

Page 1 of 2
Project Title: CONSTRUCTION OF FACILITIES AND INFRASTRACTURE TO SUPPORT MH‐60R AIRCRAFT
Contract No.: W912ER18C0015 Revision No.: 00
Sub-Contractor : NABA INTERNATIONAL COMMERCIAL ENTERPRISES LTD. ITP No. : NICE-CIV-ITP-010

INSPECTION AND TEST PLAN : TILE WORKS


INSPECTION
INSPECTION TEST REQUIREMENTS REFERENCE DOCUMENTS
SL VERIFYING RESPONSIBILTY
ACTIVITY PHASE Test or REMARKS
No. DOCUMENTS Sub US Corps
Inspection Stage / Frequency Spec/Standards/Codes Acceptance Criteria Cntrctr
Cntrctr
of Engr.
Performed

4.0 Cleaning and Protection


 Project Specification
Visual Project Specification Sec09‐30‐10 Part3.7  Inspection Request
4.1 Cleaning and Protection Prior to hand over I W S
Inspection Sec09‐30‐10 Part3.7  Manufacturer’s  Quality checklist
recommenndation

LEGENDS:
S– Surveillance W – Witness I – Inspection
R – Documents Review T – Test H – Mandatory Hold Point
Prepared By Sub Contractor Review By Contractor Client
Naba International Commercial Enterprises Ltd Al Ayuni Contracting
Date:22 April 2020 Date:

Page 2 of 2