03 Case Studies - Answers
03 Case Studies - Answers
03 Case Studies - Answers
Outline
1. Claim Based on Provision Contained in Covering Letter to Tender
2. Claim Based on Counter Offers
3. Claim Based on Subsoil Conditions
4. Claim Based on Archaeological Remains
5. Claim Based on Omissions
6. Claim Based on Taking Possession of a Building Before Completion
7. Claim Based on Liquidated Damages Payable by Subcontractors
8. Claim for Delay in Completing Sections of the Works
9. Claim where a contractor’s progress is originally behind schedule
10. Claim Based on Variations in a Delay Period
11. Claim Arising Out of Delays
12. Claim Arising Out of Delays & Prolongation Costs
13. Claim Based on Period for Calculating Prolongation Costs
14. Claim Arising out of Delays due to Errors in Designs
15. Claim for Extension of Time without Proper Notice
16. Claim for Liquidated Damages where the Employer suffers no loss
Claim Based on Provision Contained in
Covering Letter to Tender
Letter 1:
1 September 2000
Contractor to Engineer
With reference to Payment Certificate No 4 we included in our statement an item for
250 m3 of material S supplied and fixed in the Works at an extra cost of £10.20 per
m3. This item, however, was deleted. In subsequent discussion the Engineer’s
Representative contended that this was not payable as the contract is on a fixed price
basis and contains no Price Fluctuation Clause.
We would, however, draw your attention to the covering letter to our tender in
which we said that our tender was based on buying material S at X price and that if,
under the circumstances of the project, we had to get it at a higher price we would
expect to be reimbursed the extra cost.
We therefore contend we are entitled to payment of the sum of £3,060 and would
be glad if you would include this in the next certificate.
Letter 3:
3 December 2001
Engineer to Contractor
With reference to your letter dated 26 November, I have been instructed to inform you
that your request to increase your tender by £20,000 is not acceptable. It is
therefore intended to revert to your original tender including price fluctuation
provisions. I am instructed to inform you that that tender is hereby accepted in the
sum of £104,000 less £2,214 in respect of arithmetical errors and subject to a
redistribution of the excessive prices for preliminaries referred to in my letter dated
23 November 2001 which letter is now cancelled.
Claims Based on Counter Offers
Letter 4:
8 December 2001
Contractor to Engineer
Thank you for your letter dated 3 December 2001. It is regretted that we cannot agree to
proceed with this contract on the basis of your letter; to redistribute the Preliminary
Items as you require would involve us in additional costs of finance.
We are, however, prepared to stand by the offer contained in our letter dated 26 November
2001 to execute the work for the sum of £124,000 on a firm price basis.
Letter 5:
14 December 2001
Engineer to Contractor
I am instructed to inform you that my client considers there is a binding contract with you
and you are accordingly requested to proceed without further delay.
After about three weeks from the last letter the Contractor did started work on the site,
variations were issued and interim payments made. A claim arose related to the Contract
Price. The Engineer contended that the Contract Price is £104,000 less £2,214 including
price fluctuation provisions, whereas the Contractor contended that the Contract Price is
£124,000 on a firm price basis.
As a judge, draft your opinion. Explain.
Letter 2:
21 July 2000
Engineer to Contractor
I have to inform you that an inspection of the ship's timbers encountered took
place and it was found that they are of no archaeological interest and
normal work may be resumed.
Letter 2:
23 September 2001
Contractor to Engineer
We refer to Variation No 143 dated 21 September 2001 in which you ordered the
omission of the whole of the landscaping as well as some earthworks and drainage.
We notice that another contractor has appeared on site. We understand that this
firm is to undertake the landscaping work omitted from our contract. We therefore
reserve the right to claim compensation in respect of lost overheads and profit on
this work.
Letter 2:
27 August 2012
Contractor to Engineer
We are extremely surprised to receive your letter of 15 August 2012. You have moved
in on 15 July 2012. Liquidated damages could not be deducted for the period after
that date.
Letter 4:
3 September 2012
Contractor to Engineer
We cannot comprehend your situation, since you actually moved in on 15 July 2012.
Claim Based on Taking Possession of a
Building Before Completion Cont.
Letter 5:
7 September 2012
Engineer to Contractor
We note that you were still engaged in finishing off the work until 25 August 2012. We
further note that there is no clause in the Contract which states that, if the employer
at any time before substantial completion of the works take possession of a part of
or the whole of the works, then substantial completion of the part or the whole of
the works taken into possession is deemed to have taken place.
Letter 1:
1 December 2011
Contractor to Subcontractor
You have been informed in several occasions that the progress of the Subcontract work
was behind schedule, for reasons for which you are responsible. You are hereby
informed that liquidated damages will be deducted.
The Subcontractor tried to argue that he was not responsible for part of the delay.
However, his argument was duly rejected.
Claim Based on Liquidated Damages
Payable by Subcontractors Cont.
Letter 2:
1 April 2012
Contractor to Subcontractor
The progress of the Subcontract work is extremely behind schedule, for reasons for
which you are responsible. Accordingly, and as you have been informed in several
occasions, the Main Contract Works have been subject to delay as well. The
Employer has decided to deduct liquidated damages from our payments. The
deducted liquidated damages will be passed down to you, as per Clause 8.
Letter 3:
5 April 2012
Contractor to Subcontractor
We would like to inform you that you are liable to pay us liquidated damages
equivalent to $2,500,000, which is the amount deducted by the Employer under the
Main Contract.
Letter 3:
12 April 2012
Contractor to Subcontractor
Unfortunately, the employer will levy a claim for liquidated damages against us, since
the completion of the Main Contract Works are delayed. Our delay is due to a
default on your part.
There is nothing that restricts the liquidated damages that should be payable by you.
These should be payable irrespective of the value of the subcontract works.
As a judge, draft your opinion. Explain your answer.
Claim Based on Liquidated Damages
Payable by Subcontractors – Held
The injured party is entitled to recover damages from the party in breach.
These damages should include only those losses which under normal
circumstances are likely to arise and are within the contemplation of both
parties.
Subcontractors who, in breach of their subcontract, complete late will be
liable to pay the resultant damages incurred by the contractor. These
damages will include any liability the main contractor has to pay as
liquidated damages to the employer. This procedure will apply irrespective
of the value of the subcontract works.
It is open to the subcontractor to argue, if the main contract liquidated
damages are extremely high, that the sum involved was outside his
contemplation at the time the contract was entered into.
To preclude this type of argument main contractors, usually with the
Bidding Documents, will set out details of the main contract (including the
sum included for liquidated damages).
Letter 1:
1 December 2010
Engineer to Contractor
You have been informed in several occasions that the progress of the work was behind
schedule in Buildings B and C, for reasons for which you are responsible. You are
hereby informed that liquidated damages will be deducted for the two Buildings.
Letter 3:
15 December 2010
Engineer to Contractor
Sectional completion dates are included in the Contract. In case you complete a section
or more late, you will be liable to pay liquidated damages. However, the liquidated
damages percentage will not be applied to the full Contract Price, but to the value of
the section that is completed late.
As a judge, draft your opinion. Explain your answer.
Claim for Delay in Completing Sections
of the Works – Held
Contractors often include a single liquidated damages figure in respect of
the whole of the works but no liquidated damage figures for the
milestone completion dates.
The employer will be entitled to levy a claim for liquidated damages if the
contractor fails to complete the whole of the works by the completion
date, and for unliquidated damages for a failure to complete by the
milestone dates.
Letter 4:
24 February 2013
Engineer to Contractor
The progress of the work was originally behind programme. Had work been carried out
in accordance with the programme, the weather would not have affected the
progress or completion of the works. Accordingly, your claim is rejected.
Letter 2:
27 March 2002
Contractor to Engineer
We refer to Variation No 114 dated 25 March 2002. It is estimated that the
execution of the works under the variation will take 2 weeks. We formally
give you a notice of delay under the Contract.
Letter 4:
5 April 2002
Contractor to Engineer
Thank you for your letter of 29 March. We think, however, there must be some
mistake in the date given as the revised date for completion. Surely this
should be 2002 not 2001.
Claim Based on Variations in a Delay
Period Cont.
Letter 5:
7 April 2002
Engineer to Contractor
With reference to your letter of 5 April 2002, there is no mistake in the date quoted, ie
11 May 2001. It is pointed out that apart from the matter of the variation, the delay
is wholly your responsibility and there is no entitlement to further extension of time.
Allowing two weeks beyond the original date for completion for the work in re-hanging
the doors, the revised date for completion thus becomes 11 May 2001.
Letter 6:
8 April 2002
Contractor to Engineer
We cannot accept your interpretation of the contract as contained in your letter of 7
May. The variation order in question was dated 25 March 2002 and it was agreed
that two weeks were required to do the work and that this was complete on 8 April.
Therefore there cannot possibly be any question of giving an extension of time till May
2001 for an event which occurred in April 2002.
Letter 8:
15 April 2002
Contractor to Engineer
The work involved in Variation No 114 may be relatively trivial but we are entitled to an
extension of time beyond the date of the order sufficient to enable us to do the
work. It matters not that some or even all of the previous delay may have been
attributable to us. It was up to you to issue such variation. It is well understood that
due to the timing of the variation, an extension of time should be granted up to the
date the variation was issued plus adequate time to carry out the extra work.
Claim Based on Variations in a Delay
Period Cont.
Letter 9:
17 April 2002
Engineer to Contractor
With reference to your letter of 15 April 2002, we note that work on your contract
should have been completed some months ago and you should have been off the
site before now.
We contend that the correct approach should be a net extension of time, that is to say,
one which calculated the revised completion date by taking the date currently fixed
for completion and adding to it the 2 weeks that are considered to be fair and
reasonable for the re-hanging works.
Letter 10:
19 April 2002
Contractor to Engineer
We draw your attention that if the net method was adopted, the extended completion
date would expire before the variation giving rise to the extension had been
instructed, which is logically and physically impossible. We consider this problem
resulted from the Employer's own voluntary conduct in requiring a variation during a
period of culpable delay.
The same result would apply if the variation was issued after the revised
completion date but prior to practical completion.
Claim Arising Out of Delays
Relevant Information:
The contract was for the construction of a small pumping station.
Contract Sum: £148,486. Commencement Date: 1 April 1999. Time for
Completion: 15 months.
There was a spell of very bad weather which affected the earthworks rather
badly. There was a suspension order by the Engineer. There was a
succession of variation orders, not great in value but taking a relatively long
time to carry out. Certain bending schedules which the contractor needed
were delayed by the employer. There was a delay due to exceptionally
adverse weather in August 2000 and the work was not finally completed
until December 2000.
In fact the drawings and schedules were not issued until end of May 2000. Work
continued and was delayed for further three weeks of exceptionally adverse weather
in August 2000.
In November, the Engineer wrote:
Letter 4:
3 November 2000
Engineer to Contractor
Your attention is drawn to the lack of progress on this job and in accordance with Clause
46 of the Conditions I must request you to take such steps as are necessary to
expedite progress.
Claim Arising Out of Delays Cont.
Letter 5:
6 November 2000
Contractor to Engineer
We were astonished to receive your letter of 3 November invoking Clause 46. You are
aware of the delays which have occurred. Our request dated 9 January 2000 for
extension of time has not been granted. Since then there have been delays of six
weeks because of non-issue of the revised bending and three weeks for exceptionally
inclement weather in August, not to mention the many variations involving extra work
(total value of £12,450) for which we require an extra ten weeks.
We formally request an extension of time of 26 weeks.
Letter 6:
20 November 2000
Engineer to Contractor
I hereby extend the time for completion by 22 weeks in respect of delay notified to date.
Letter 8:
1 December 2000
Engineer to Contractor
I have allowed 5 weeks for delay due to inclement weather and the suspension order, 4
weeks in respect of late issue of bending schedules, 3 weeks for inclement weather in
August 2000 and 10 weeks for extra work.
Claim Arising Out of Delays Cont.
Letter 9:
2 December 2000
Contractor to Engineer
We consider your allowance for some of the delays are somewhat short. We submit
herewith our claim for compensation in respect of the extension of time to which we
consider ourselves entitled and we should be glad of an early payment on account. In
any case, we hereby submit a claim for additional costs for the extended 22 weeks.
CLAIM
22 weeks' delay consequent upon extension of time as per letter of 1 December 2000 at
£342 per week= £7,524.00
Analyze the contractor’s entitlement under each claim event, explaining the
contractor’s entitlement, as of the merit of his claim, in terms of extension
of time, cost and profit in respect of each. (No need to check the
calculations. This will be done in the following Case Study)
Claim Arising Out of Delays – Held
Initial inclement weather in November & December:
The first 3 weeks are in respect of inclement weather. Thus, the
Contractor is entitled to extension of time of three weeks for
inclement weather, but no cost.
Suspension:
The one week of inclement weather in December overlapped with
one week of the suspension. The net effect of the suspension is
therefore 3 weeks. Thus, the Contractor is entitled to extension
of time, cost and profit for three weeks for suspension.
Prolongation Costs:
• Delay Period = 11 weeks
• Site Overheads during delay period = 261.55 * 11 = 2,877.00
• Head Office Overheads = 2,877.00 * 8.5% = 244.54
• Sub-total = 3,121.54
• Add Profit = 3,121.54 * 5% = 156.08
• Total Prolongation Costs = 3,277.62
Claim Arising Out of Delays &
Prolongation Costs – Held
Extra work:
There is a misconception concerning additional overheads for extra work. It is
sometimes argued that extra work is being priced based on similar items in
the BOQ with rates, which themselves include overheads. However, this might
not suffice to cover actual overheads. On the basis that similarity of character
and of conditions is an essential term of the contract, if the extra work is of
small value relative to the time required to do it, the extra work should not be
considered similar. (For example, to take it to the extreme, if such work was
instructed to be executed during the original time for completion, the
Contractor might have executed them without extra overheads). Site
overheads are generally related to turnover, so that if turnover in relation to
variations is less than that for contract works generally, some adjustment is
called for. Thus, the Contractor is entitled to extension of time, cost and profit
for the 10 weeks for extra work, after adjustment in accordance with the
contract.
Value of Extra work / Turnover per week = 12,450 / 2,284.4 = 5.45 weeks
• Actually executed in = 10 weeks
• Lost overheads for a duration of: 10 – 5.45 = 4.55 weeks
Site Overheads per week * 4.55
• Lost Site Overheads for such duration =
= 261.55 * 4.55 = 1,190.03
• Lost Head Office Overheads = HO * Lost Site Overheads = 8.5 % * 1,190.03 = 101.15
• Sub-total = 1,291.18
• Add Profit = P * Sub-total = 5 % * 1,291.18 = 64.56
• Total Claim = 1,355.74
Claim Based on Period for Calculating
Prolongation Costs
Relevant Information:
The contract was for the construction of a school.
Commencement Date: 1 January 2010. Time for completion: 8 months.
The Contractor submitted with his tender a breakdown of his site overheads. The site
overheads are varying over the project duration.
Work on site had been subject to delay, as certain drawings were required to be issued
in the first week of month 4 (April), but they were delayed to the first week of
month 6 (June).
Letter 1:
25 March 2010
Engineer to Contractor
We regret to inform you that there will be a delay in the issue of the drawings. It is
expected that the drawings will be ready soon.
In fact the drawings were not issued until 1 June 2010.
Letter 3:
20 June 2010
Engineer to Contractor
We agree to your request for extension of time and grant an extension of time till 1
November 2010. However, you should calculate the site overheads for the extended
period, i.e. the site overheads should be related to the period between the contract
completion date and the extended completion date.
Claim Based on Period for Calculating
Prolongation Costs Cont.
Letter 4:
30 June 2010
Contractor to Engineer
We do not agree with your view regarding prolongation costs. The value of the
prolongation costs related to the overrun period at the end of the contract is much
less than the value of the prolongation costs at the period when the delay occurred.
We request the value of the prolongation costs at the period when the delay
occurred, which we contend is the correct value resulting from the delay.
300,000
200,000
100,000
0
1 2 3 4 5 6 7 8
Claim Based on Period for Calculating
Prolongation Costs – Held
The intention is for the contractor to be reimbursed the additional cost
which resulted from the employer delays. This involves a comparison
between the actual costs incurred and what the cost would have been
had no delay occurred.
Thus, the evaluation should relate to the period when the effect of the
delay occurs and not by reference to the overrun period at the end of the
contract. That is because the period when the delay actually took place is
the period when the costs were incurred.
Thus the correct period is months 4 and 5 (from 1 April 2010 to 1 June
2010).
Letter 2:
20 October 2007
Engineer to Contractor
We are glad to inform you that no design changes will be made. Accordingly, you are
instructed to proceed with the original drawings.
Letter 4:
20 November 2007
Contractor to Engineer
With reference to our letter of 10 November 2007, please find attached the detailed
particulars for our claim for extension of time and additional payment.
Claim for Extension of Time without
Proper Notice Cont.
Letter 5:
30 November 2007
Engineer to Contractor
With reference to your letter of 10 November 2007 and to Clause 21 where you are
required to serve a notice for extension of time and additional payment within 15
days after the event giving rise to the claim has first arisen. You have failed to
provide proper notice in accordance with the Contract. Accordingly, we regret to
inform you that your claim is rejected.
Letter 6:
2 December 2007
Contractor to Engineer
We are surprised with your letter of 30 November 2007. You are well aware that the
Employer has suspended the works for 19 days. Thus, the works are delayed for
reasons attributable to the Employer and for which the Contractor holds no
responsibility. We are surprised you are intending to reject our plain obvious claim,
for a mere procedural matter.
Letter 8:
20 December 2007
Contractor to Engineer
We contend that the durations for the notice and particulars are mere procedural
matters. Failure to abide by such durations should not result in loss of our rights.
Abiding by such durations is not a condition precedent to our rights under Clause 21.
Claim for Extension of Time without
Proper Notice Cont.
Letter 9:
25 December 2007
Engineer to Contractor
We re-iterate that we regret that you have misinterpreted the Clause. Why include
durations in a Clause, when it is not expected from the Contractor to abide by them?
You have agreed to the Clause and to the durations by signing the Contract.
Letter 10:
27 December 2007
Contractor to Engineer
But if we follow your logic, then you will deduct liquidated damages from us, although
the Employer delayed the works?
The progress of the work was behind schedule, for reasons for which the Contractor
was responsible. Instead of being completed in June 2011, work was completed in
August 2011.
Claim for Liquidated Damages where
the Employer suffers no loss Cont.
Letter 1:
1 August 2011
Engineer to Contractor
You have been informed in several occasions that the progress of the work was behind
schedule, for reasons for which you are responsible. You are hereby informed that
liquidated damages will be deducted with a value equivalent to 10% of the Contract
Price, i.e. $100,000.
Letter 2:
10 August 2011
Contractor to Engineer
We note that the university is not working in the summer. Accordingly, you have
suffered no loss as a result of our delay. We thus contend that the liquidated
damages expressed in the contract should not become payable.
Thank You