(CG Greenfield FTTX Project) : Tasks

The document outlines the timeline for a fiber-to-the-home (FTTx) project. It includes tasks such as civil work from September 1st to 30th, installing metal doors from September 10th to 14th, and a technical site survey from October 1st to 2nd. Testing and commissioning tasks are planned from November to January, including acceptance testing between December 16th and January 5th. Milestones include the start of civil work on September 1st, infrastructure work beginning on September 10th, installation and commissioning starting November 1st, and final acceptance on December 16th.

Uploaded by

samaratul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views2 pages

(CG Greenfield FTTX Project) : Tasks

The document outlines the timeline for a fiber-to-the-home (FTTx) project. It includes tasks such as civil work from September 1st to 30th, installing metal doors from September 10th to 14th, and a technical site survey from October 1st to 2nd. Testing and commissioning tasks are planned from November to January, including acceptance testing between December 16th and January 5th. Milestones include the start of civil work on September 1st, infrastructure work beginning on September 10th, installation and commissioning starting November 1st, and final acceptance on December 16th.

Uploaded by

samaratul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

[CG Greenfield FTTx Project]

8/17/... 9/6/... 9/26/... 10/16/... 11/5/... 11/25/... 12/15/... 1/4/...

Tasks
Start End Duration Label Vert. Position Vert. Line
Civil Work
9/1/2020 9/30/2020 30
Sep 1 - Sep 30 -15 -15
Installation Metal door
9/10/2020 9/14/2020 4
Sep -20 -5
Technical Site14Survey
10 - Sep
10/1/2020 10/2/2020 2
Oct 1 -System
Oct 2 Installation -25 -5
Earth
10/3/2020 10/7/2020 5 -30 -30
Oct 3 - Octcabling
Electrical 7
10/8/2020 10/12/2020 5 -35 -35
Oct
Power8 - equipment
Oct 12 Installation
10/13/2020 10/22/2020 10 -40 -5
Oct 13 -
AcceptanceOct 22
Test (AT) of Power Components
10/23/2020 10/24/2020 2 -45 -45
Oct 23 - Oct 24
Installation of Security Systems
10/25/2020 10/29/2020 5 -15 30
Oct 25 - Octof
Installation 29fire fighting system
10/30/2020 11/6/2020 8 -20 -5
Oct 30 - Novof6 Rack
Installation
11/7/2020 11/11/2020 5 -25 -5
Nov 7 - Nov of
Installation 11Cable tray
11/12/2020 11/16/2020 5 -30 -5
Nov
Installation of16
12 - Nov euipments (Active Components)
11/1/2020 11/6/2020 5 -35 -5
Nov 1 - Nov 6
Fiber Cable, Power Cable routing and Labeling
11/22/2020 11/29/2020 7 -40 -5
Nov 22 - Nov 29of Routers
Commissioning
11/1/2020 12/1/2020 30
Nov 1 - Dec 1 of EMS server and Node Integration -15 25
Commissioning
11/15/2020 11/30/2020 15 -20 -5
Nov 15 - Nov 30of ACS
Commissioning
11/1/2020 11/16/2020 15
Nov 1 - Nov 16 of OSS and BSS System and Integration -25 -5
Commissioning
11/1/2020 12/16/2020 45
Nov #REF! #REF!
(AT)1of- Dec 16 Components
Active
12/16/2020 12/26/2020 10
Dec 16 - Dec 26 (AT) PAT OSS and BSS -10 #REF!
Acceptance Test
12/16/2020 1/5/2021 20 -15 -5
Dec 16 - Jan 5
Insert new rows above this one

Milestones
Date Label Position
9/1/2020 Civil Work Sep 1 50
9/10/2020 Infra Work 25
11/1/2020 Installation Of Equipment/Commissioning 30
12/16/2020 Acceptance 50