Total Project Cost

The document provides a total project cost estimate for the construction of East Zone High School MMM. The total project cost is estimated to be $98,193,950. This includes $90,163,279 for construction costs, $4,027,171 for furniture/fixtures/equipment, and $4,003,500 for technology. The largest construction cost is $69,709,425 for new building construction. The estimate was prepared by Scott Reichenbacher and lists BSSW as the architect and Suffolk as the construction manager.

Uploaded by

Erin O'Brien
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
253 views1 page

Total Project Cost

The document provides a total project cost estimate for the construction of East Zone High School MMM. The total project cost is estimated to be $98,193,950. This includes $90,163,279 for construction costs, $4,027,171 for furniture/fixtures/equipment, and $4,003,500 for technology. The largest construction cost is $69,709,425 for new building construction. The estimate was prepared by Scott Reichenbacher and lists BSSW as the architect and Suffolk as the construction manager.

Uploaded by

Erin O'Brien
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

EAST ZONE HIGH SCHOOL "MMM" TOTAL PROJECT COST ESTIMATE

CATEGORY ESTIMATE NOTES


PHASE #1 BOARD APPROVAL $ 2,575,000.00 Pre-construction Board approved amount
DESIGN SERVICES $ -
Architect Included in Phase #1
Civil Engineer Included in Phase #1

CONSTRUCTION COSTS $ 83,660,661.00


Management Fee & General Conditions $ 11,514,518.00
New Construction $ 69,709,425.00
Owner Contingency $ 2,436,718.00 Owner Contingency 3% of $81.2M

ANCILLARY COSTS $ 3,927,618.00


HVAC Testing $ 75,000.00
Inspections & Testing $ 607,900.00 Pre-construction costs were in Phase #1
Moving Expenses $ 100,000.00
Permits & Fee $ 25,000.00
Portable Expenses $ 1,500,000.00
Security ITV/TV/I-C Within GMP
Surveys & Assessments $ 100,000.00
Utilities (Gas/Water/Electric) $ 450,000.00 Allowance
Other Ancillary Costs $ 150,000.00 Allowance, includes Auditing costs
Mitigation $ 919,718.00 Final value

SUB-TOTAL CONSTRUCTION COSTS $ 90,163,279.00

SITE COSTS In GMP


Property Appraisals $ -
Site Purchase $ -
Site Development $ -
Offsite (Roadwork) $ -
$ -
TOTAL CONSTRUCTION W/SITE COST $ 90,163,279.00
FF&E (Furniture, Fixtures & Equipment) $ 4,027,171.00
Technology (IT Dept) $ 4,003,500.00
Legal Fees Included in Phase #1
TOTAL PROJECT COST $ 98,193,950.00
NOTE: Line Item Values may be adjusted for accounting purposes by Executive Management, however, the Total Project Cost Estimate will not be
increased due to adjustments made.

Architect: BSSW Prepared by:Scott Reichenbacher


Construction Manager: Suffolk
Building Official: Universal 7/25/2019