Work Method Statement For Trail Trench
Work Method Statement For Trail Trench
Work Method Statement For Trail Trench
SCOPE:
1. This procedure applies to the procedure for making the trial holes.
2. To provide INSTRUCTIONS regarding, how to carry out the trial holes, before applying the
construction NOC.
METHOD OF STATEMENT:
1. Mobilization
1.1 Permit from all necessary governing authorities before starting the work.
2. Equipment required
2.1 Swivel, spades, brushes, plastic sheet, safety cones, warning tapes, Safety gloves, safety helmet, etc.
3. Safety
3.1 All site tools and equipments should be kept in a safe area easily accessible for work
3.2 Hard hats, safety footwear & clothing must be worn at all times.
3.3 All the members involved in the activity should have to wear reflective jacket to prevent any
accident, while doing the excavation work.
3.4 Ensure the safety of the personnel and the equipment throughout the work process.
Page 1 of 3
WORK METHOD STATEMENT
FOR TRAIL TRENCH
4. Workmanship
4.1 Ensure that:
5. General
5.2.1 The works will be carried out by experienced foremen and laborers under the supervision
of experienced engineers.
5.2.2 The engineers will brief the personnel involved in the activity before the works Commence. This
will involve going through the method statement.
5.2.3 Ensure the availability of Work Permit from all the governing authorities before starting the work.
5.2.4 With the approved drawings and the indicated areas with coordinates the trial holes to be
carried out with all safety precautions.
5.2.5. Only manual excavation will be done in the marked areas and no sharp edged tools will be used.
5.2.6 The area will be barricaded with safety cones and warning tapes to avoid any hazard.
5.2.8 After the trial holes are done, the area will be barricaded with safety cones and warning tapes
to avoid any hazard.
5.2.9 The exposed trial holes to be then verified by AADC and all necessary governing authorities for the
availability of any existing cables and approval to be given for construction NOC accordingly.
Page 2 of 3
WORK METHOD STATEMENT
FOR TRAIL TRENCH
5.2.10. Shop drawing of all existing services shall be amended in the shop drawing and submitted to
AADC for approval.
5.2.11. After approval of concern authorities trail trench shall be backfilled to its original.
5.2.12. Clear site and dispose of all waste materials & debris after the work is complete.
6. Quality Control
6.1. Ensure that job is carried out according to this work instruction.
7. Demobilization
7.2 After completing the works, clean and clear the site.
Page 3 of 3