Contoh: Jadual Pembahagian Jumlah Jam Latihan

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

JADUAL PEMBAHAGIAN JUMLAH JAM LATIHAN

MC-027-3:2012 FLUX CORE ARC WELDING


CONTOH
MC-027-3:2012-C01 FLUX CORE ARC WELDING (FCAW) FOR FILLET WELD 1F, 2F, 3F, 4F, BUTT
WELD 1G AND 2G
Work Activities JAM LATIHAN (TEORI) JAM LATIHAN (AMALI) KESELURUHAN
1. Carry out safety assessment at
24 JAM 24 JAM 48 JAM
work area
2. Comply to work instruction and
relevant Welding Procedure 30 JAM 10 JAM 40 JAM
Specification (WPS)
3. Verify base metal material used 4 JAM 4 JAM 8 JAM
4. Verify consumable as specified 8 JAM 8 JAM 16 JAM
5. Check GMAW equipment and
16 JAM 8 JAM 24 JAM
accessories functionality
6. Perform GMAW process 24 JAM 256 JAM 280 JAM
7. Perform visual inspection and
40 JAM 40 JAM 80 JAM
testing (destructive test)
8. Carry out back grinding and back
welding as required in 4 JAM 8 JAM 12 JAM
accordance with test specimen
9. Compile work completion
4 JAM 4 JAM 8 JAM
checklist
KESELURUHAN 516 JAM
JADUAL PEMBAHAGIAN JUMLAH JAM LATIHAN
MC-027-3:2012 FLUX CORE ARC WELDING
CONTOH
MC-027-3:2012-C02 FLUX CORE ARC WELDING (FCAW) FOR
BUTT WELD 3G AND 4G
Work Activities JAM LATIHAN (TEORI) JAM LATIHAN (AMALI) KESELURUHAN
1. Carry out safety assessment at
24 JAM 24 JAM 48 JAM
work area

2. Comply to work instruction and


40 JAM
relevant Welding Procedure 30 JAM 10 JAM
Specification (WPS)

3. Verify base metal material used 8 JAM 8 JAM


16 JAM
4. Verify consumable as specified 8 JAM 8 JAM
16 JAM
5. Check GMAW equipment and
16 JAM 24 JAM 40 JAM
accessories functionality
24 JAM 256 JAM 280 JAM
6. Perform GMAW process
40 JAM 40 JAM
7. Perform visual inspection and
80 JAM
testing (destructive test)

8. Carry out back grinding and back


4 JAM 8 JAM 12 JAM
welding as required in accordance
with test specimen

9. Compile work completion checklist 4 JAM 4 JAM


8 JAM
KESELURUHAN 540 JAM
JADUAL PEMBAHAGIAN JUMLAH JAM LATIHAN

MC-027-3:2012 FLUX CORE ARC WELDING


CONTOH
MC-027-3:2012-C03 FLUX CORE ARC WELDING (FCAW)
FOR 5G AND 6G (UP-HILL AND DOWN-HILL)
Work Activities JAM LATIHAN (TEORI) JAM LATIHAN (AMALI) KESELURUHAN
1. Carry out safety assessment at
24 JAM 24 JAM 48 JAM
work area

2. Comply to work instruction and


40 JAM
relevant Welding Procedure 30 JAM 10 JAM
Specification (WPS)

3. Verify base metal material used 4 JAM 4 JAM


8 JAM
4. Verify consumable as specified 8 JAM 8 JAM
16 JAM
5. Check GMAW equipment and
16 JAM 24 JAM 40 JAM
accessories functionality
40 JAM 240 JAM 280 JAM
6. Perform GMAW process

7. Perform visual inspection and


40 JAM 40 JAM 80 JAM
testing (destructive test)

8. Compile work completion checklist 4 JAM 4 JAM


8 JAM
KESELURUHAN 520 JAM