ACTIVITY IDENTIFIED HAZARD PERSONS AT RISK S L RISK LEVEL RISK CONTROL / REDUCTION MEASURES
Approaching
near the Struck by moving Harris Calnan Areas of machinery and plant movement to be avoided.
moving plant, crush, impact office based 2 3 High Only designated walkways and safe routes to be used.
machinery and fall injuries staff on sites Hi-visibility jackets/vests to be worn at all times on site.
and plant
Visiting site
areas where Struck by falling Harris Calnan Access to areas below working activities to be avoided -where not
operatives are objects, crush and office based 2 3 High possible ask operatives (if possible) works to be suspended.
working impact injuries staff on sites Hard hat to be worn at all times on site.
overhead
Walking on Harris Calnan Areas where risk of flying objects i.e. grinding, concrete breaking
Struck by flying
construction office based 2 2 Medium to be avoided.
objects
site staff on sites Suitable eye protection to be worn.
RISK ASSESSMENT KEY S = Hazard Severity HS3-02-Updated August 2011-Risk Assessment-Visiting Construction Sites Page 1 of 2
Risk Assessment = S x L 1 = Slight 2 = Serious 3 = Major
3 = Likely Medium High High
L = likelihood 2 = Possible Low Medium High
1 = Rare Low Low Medium
HEALTH AND SAFETY MANAGEMENT SYSTEMS
RISK ASSESSMENT: VISITING CONSTRUCTION SITE (OFFICE BASED STAFF)
Staff are responsible for undertaking specific risk assessments for any unforeseen or additional hazards and taking appropriate action to protect their own and others health & safety.
Staff are allowed to stop the work/activity if adequate control measures cannot be put in place
ACTIVITY IDENTIFIED HAZARD PERSONS AT RISK S L RISK LEVEL RISK CONTROL / REDUCTION MEASURES
Harris Calnan
Contact with Electrocutions,
office based 2 2 Medium All services on site to be assumed live and contact avoided.
live services burns, scalds, falls
staff on sites
Exposure to very
Visiting sites low temperatures,
Harris Calnan Site visits to only be attempted when safe to do so.
in adverse high winds, icy, wet
office based 2 2 Medium Extent of visit and areas to be accessed to consider weather
weather slippery conditions
staff on sites conditions, ensuring all practicable precautions are taken.
conditions causing falls, falling
objects
Areas without edge protection must be avoided.
Visiting high Only complete, inspected scaffolding to be accessed on site.
Harris Calnan
level area on Visiting Harris Calnan staff not to use of any contractors equipment
Falls from height office based 2 2 Medium
site or near to i.e. mobile towers, ladders, MEWP’s etc.
staff on sites
excavation Any access to height to be agreed with Site Management and
suitable controls implemented.
Visiting Harris Calnan Visiting Harris Calnan staff have a duty to report any unsafe
Noticing any unsafe
construction office based 2 2 Medium actions by site operatives, unsafe condition or any hazard that is
acts or on site
site staff on sites not suitably protected or identified to Site Management urgently.
Visiting Harris Calnan
Fire, burns, scalds, Actions to be taken in accordance with emergency plan identified at
construction office based 2 2 Medium
smoke inhalation site induction or to follow Site Management instructions.
site staff on sites
Visiting Hit by debris, crush, Harris Calnan Staff must not visit demolition sites unless absolutely necessary.
demolition trapped, impact, office based 3 2 High Visiting staff to be accompanied by Site Management at all times.
areas on site falling objects staff on sites All identified PPE to be worn at all times.
RISK ASSESSMENT KEY S = Hazard Severity HS3-02-Updated August 2011-Risk Assessment-Visiting Construction Sites Page 2 of 2
Risk Assessment = S x L 1 = Slight 2 = Serious 3 = Major
3 = Likely Medium High High
L = likelihood 2 = Possible Low Medium High
1 = Rare Low Low Medium