(Lab Logo) : This Test Report Relates To The Test Sample Submitted and List of Documents Attached

Download as pdf or txt
Download as pdf or txt
You are on page 1of 95

[LAB LOGO]

Test Report No.: xx001 Page 1 of xx

Issue Date: DD/MM/YYYY

Manufacturer: Applicant’s Name


Applicant’s address

Test item: Cash Register

Identification: (Model No.) Serial No.:

Receipt No.: Date of receipt:

Testing laboratory and its Lab Name


address:
Lab address

Test specification: IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 /


IEC 60950-1: 2005 + A1: 2009 + A2 : 2013

Test Result: The test item passed / failed the test specification(s).

Other Aspects:
- Brief description or additional details could be given by the labs here.

This test report relates to the test sample submitted and list of documents attached.

Approved by /
Tested by: Issued by:
Authorized Signatory:

(Name / Designation) (Name / Designation) (Name / Designation)

Date: Date: Date:


[LAB LOGO]

TEST REPORT
IS 13252 (Part 1): 2010 + A1: 2013+ A2: 2015 /
IEC 60950-1: 2005 + A1: 2009 + A2: 2013
Information technology equipment – Safety –
Part 1: General requirements
“Cash Register”
Report Reference No. ..................... : xxxxxxxxx 001
Date of issue..................................... : (see cover page)
Total number of pages ...................... (see cover page)
Testing Laboratory ......................... : Lab Name
Address ............................................ : Lab address

Manufacturer’s name ..................... : Applicant’s Name


Address ............................................ : Applicant’s address

Test specification:
Standard ........................................... : IS 13252 (Part 1): 2010 + A1: 2013+ A2:2015 /
IEC 60950-1: 2005 + A1: 2009 +A2:2013
Test procedure ................................. : Compliance Report
Non-standard test method…………..: N/A
Test Report Form No. ..................... : BIS_IT/CR_IS13252_V1.2

Test Report Form(s) Originator ........ : Bureau of Indian Standards


Master TRF....................................... : 03/06/2016
Test item description ..................... : Cash Register
Trade Mark ....................................... :
Model/Type reference ...................... :
Ratings ............................................. :
Other Documents submitted ............. : Please refer to Table – List of Attachments at Page No. xx

Approved by /
Tested by: Issued by:
Authorized Signatory:

(Name / Designation) (Name / Designation) (Name / Designation)

Date: Date: Date:

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 3 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Test Code Description Measurement/ testing Total No. Total no. of No. of Page
of tests applicable tests/ No.
tests/ Req. Req.
passed
EL 2100 General Components (Cl.1.5)
Requirements
EL 2101 General Power interface (Cl.1.6)
Requirements
EL 2102 Marking Marking &
Requirements instructions(Cl.1.7)
EL 2103 Electrical safety Protection from electric
shock and energy
hazards (Cl.2.1)
EL 2104 Electrical safety SELV Circuits (Cl.2.2)
EL 2105 Electrical safety TNV Circuits (Cl.2.3)
EL 2106 Electrical safety Limited current circuits
(Cl.2.4)
EL 2107 Electrical safety Limited Power sources
(Cl.2.5)
EL 2108 Electrical safety Provisions for earthing
and bonding (Cl.2.6)
EL 2109 Electrical safety Overcurrent and earth
fault protection in
primary circuits (Cl.2.7)
EL 2110 Electrical safety Safety Interlocks
(Cl.2.8)
EL 2111 Electrical safety Electrical Insulation
(Cl.2.9)
EL 2112 Electrical safety Clearances, Creepage
distances and distances
through insulation
(Cl.2.10)
EL 2113 Wiring Wiring, connections
and supply (Cl.3)
EL 2114 Wiring Connection to a main
supply (Cl.3.2)
EL 2115 Wiring Wiring terminals for
connection of external
conductors (Cl.3.3)
EL 2116 Wiring Disconnection for the
main supply (Cl.3.4)
EL 2117 Wiring Interconnection of
equipment (Cl.3.5)
EL 2118 Mechanical Stability (Cl.4.1)
properties
EL 2119 Mechanical Mechanical strength
properties (Cl.4.2)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 4 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2120 Mechanical Design and


properties construction (Cl.4.3)
EL 2121 Mechanical Protection against
properties hazardous moving parts
(Cl.4.4)
EL 2122 Thermal Thermal requirements
Properties (Cl.4.5)
EL 2123 Mechanical Openings in Enclosures
properties (Cl.4.6)
EL 2124 Fire Safety Resistance to fire
(Cl.4.7)
EL 2125 Insulating Electrical requirements
properties and simulated abnormal
conditions(Cl.5),5.1
EL 2126 Insulating Electric Strength
properties (Cl.5.2)
EL 2127 Insulating Abnormal operating and
properties fault conditions (Cl.5.3)
EL 2128 Communicating Protection of
connection telecommunication
network service
persons, and users of
other equipment
connected to the
network, from hazards
in the equipment(Cl.6.1)
EL 2129 Communicating Protection of equipment
connection users from overvoltages
on telecommunication
networks (Cl.6.2)
EL 2130 Communicating Protection of the
connection telecommunication
wiring system from
overheating (Cl.6.3)
EL 2131 Connection to Connection to cable
cable distribution distribution systems
systems (Cl.7)
EL 2132 Fire safety Tests for resistance to
heat and fire (Annex A)
EL 2133 Insulating Motor tests under
properties abnormal conditions
(Annex B)
EL 2134 Electrical Safety Transformers
(Annex C)
EL 2135 Insulating Measuring Instruments
properties For Touch-Current
Tests (Annex D)
EL 2136 Thermal Temperature Rise Of A
Properties Winding(Annex E)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 5 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2137 Electrical safety Measurement Of


Clearances And
Creepage
Distances(Annex F)
EL 2138 Electrical safety Alternative Method For
Determining Minimum
Clearances(Annex G)
EL 2139 Radiation Safety Ionizing
Radiation(Annex H)
EL 2140 Electrical Safety Table of
electrochemical
potentials (Annex J)
EL 2141 General Thermal controls
Requirements (Annex K)
EL 2142 General Normal load conditions
Requirements for some types of
electrical business
equipment (Annex L)
EL 2143 Electrical Safety Criteria for telephone
ringing signals
(Annex M)
EL 2144 Electrical safety Impulse Test
Generators(Annex N)
EL 2145 General Normative
Requirements References(Annex P)
EL 2146 General Voltage dependent
Requirements resistors (VDRs)
(Annex Q)
EL 2147 General Examples Of
Requirements Requirements For
Quality Control
Programmes(Annex R)
EL 2148 General Procedure For Impulse
Requirements Testing (Annex S)
EL 2149 Protection Guidance On Protection
against Ingress Against Ingress Of
of water Water (Annex T)
EL 2150 Wiring Insulated Winding
Wires For Use Without
Interleaved Insulation
(Annex U)
EL 2151 Electrical Ac Power Distribution
Safety Systems(Annex V)

EL 2152 Electrical Summation Of Touch


Safety Currents (Annex W)

EL 2153 Electrical Maximum Heating


Safety Effect In Transformer
Tests(Annex X)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 6 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2154 Radiation safety Ultraviolet light


conditioning test
(Annex Y)
EL 2155 Electrical Overvoltage Categories
Safety (Annex Z)

EL 2156 Mechanical Mandrel Test(Annex


properties AA)

EL 2157 Electrical Changes In The


Safety Second Edition(Annex
BB)

EL 2158 Electrical Safety Evaluation Of


Integrated Circuit (IC)
Current Limiters (Annex
CC)
EL 2159 Mechanical Requirements For The
properties Mounting Means Of
Rack-Mounted
Equipment (Annex DD)
EL 2160 Electrical Household And
Safety Home/Office
Document/Media
Shredders (Annex EE)

Certificate: It is certified that the above tests were performed and found to be passing/Failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 7 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Copy of marking plate:


Copy of marking label:

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 8 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Table – List of Attachments

Attachment No. Attachment Description No. of pages in Attachment

Attachment – 1 Photo Document xx

General remarks:
The test results presented in this report relate only to the object tested.
This report shall not be reproduced, except in full, without the written approval of the Issuing testing
laboratory.

Possible test case verdicts:


- test case does not apply to the test object ................ : N/A
- test object does meet the requirement ...................... : P (Pass)
- test object does not meet the requirement ................ : F (Fail)

Testing ......................................................................... :
Date of receipt of test item ........................................... :
Date(s) of performance of tests ................................... :
Laboratory conditions ............................................... :
Ambient Temperature ................................................... :
Ambient Humidity ......................................................... :

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 9 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Test item particulars .................................................. :


Equipment mobility .................................................... : movable hand-held transportable
stationary for building-in direct plug-in
Connection to the mains ............................................ : pluggable equipment [] type A [] type B
permanent connection
detachable power supply cord
non-detachable power supply cord
not directly connected to the mains
Operating condition ................................................... : continuous
rated operating / resting time:
Access location ......................................................... : operator accessible
restricted access location
Over voltage category (OVC) ................................... : OVC I OVC II OVC III OVC IV
other:
Mains supply tolerance (%) or absolute mains supply
values ....................................................................... : -10%, +6% <OR> ±10%
Class of equipment ................................................... : Class I Class II Class III
Not classified
Considered current rating of protective device as a
part of the building installation (A) ............................ : 16A (for India)
Pollution degree (PD) ............................................... : PD 1 PD 2 PD 3
IP protection class .................................................... : IPXX or Not rated, indoor use only
Altitude during operation (m) .................................... : Up to 2000
Altitude of test laboratory (m) ................................... : < 1000
Mass of equipment (kg) ............................................ :

Abbreviations that may be used throughout this test report:


PE/PB .............. : protective earth/protective bonding Pri .....................: primary
CB .................... : circuit breaker sec ....................: secondary
(SW)PS ............ : (switching) power supply gnd....................: ground
HV .................... : high voltage I/O .....................: input/output
PCB ................. : printed circuit (wiring) board ii ......................... : installation instruction
TIW .................... : triple insulated wire PSU ................... : Power Supply Unit
B/I ...................... : built-in application (compliance shall be guarantee in host equipment)
F/B/S/R : Functional/Basic/Supplementary/Reinforced Insulation

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 10 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

General product information:

1) Application details / Description of the product:

Max. specified ambient temperature (°C) ...... : ?? °C

Laser classification ........................... ............ : < delete this line, if not applicable >

2) Differences between the models:


(N/A, one single model)
<OR>
< describe the constructional differences in such general terms, that the informed reader can still make a
rough evaluation of their safety relevance >

Model No. tested with-in the family series . : ??

3) Options:
The equipment was tested without any optional accessory installed. Hence, this report does not cover
parameters that are influenced by the installation of optional accessory that might affect safety in the meaning
of this standard.

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 11 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to General Requirements EL 2100 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
1.5 Components* EL 2100-00
1.5.1 General: EL 2100-01
Components shall be complying
with IEC 60950-1 or relevant
component standard.
Components and subassemblies
approved for IEC 62368-1 can be
considered as complying with this
standard
1.5.2 Evaluation and testing of EL 2100-02
components
1.5.3 Thermal controls EL 2100-03
1.5.4 Transformers EL 2100-04
1.5.5 Interconnecting cables* EL 2100-05
1.5.6 Capacitors bridging insulation * EL 2100-06
1.5.7 Resistors bridging insulation EL 2100-07
1.5.7.1 Resistors bridging functional, EL 2100-08
basic or supplementary
insulation*
1.5.7.2 Resistors bridging double or EL 2100-09
reinforced insulation between a.c.
mains and other circuits
1.5.7.3 Resistors bridging double EL 2100-10
insulation or reinforced insulation
between the a.c. mains supply
and circuits connected to an
antenna or coaxial cable
1.5.8 Components in equipment for IT EL 2100-11
power distribution systems*
1.5.9 Surge suppressors EL 2100-12
1.5.9.1 General* EL 2100-13
1.5.9.2 Protection of VDRs* EL 2100-14
1.5.9.3 Bridging of functional insulation EL 2100-15
by a VDR*
1.5.9.4 Bridging of basic insulation by a EL 2100-16
VDR*
1.5.9.5 Bridging of supplementary, EL 2100-17
double or reinforced insulation by
a VDR*

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 12 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/ failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 13 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2101 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
1.6 Power interface* EL 2101-00
1.6.1 AC power distribution systems* EL 2101-01
1.6.2 Input current EL 2101-02
1.6.3 Voltage limit of hand-held EL 2101-03
equipment*
1.6.4 Neutral conductor * EL 2101-04

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/ failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 14 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Marking Requirements EL 2102 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
1.7 Marking and instructions* EL 2102-00
1.7.1 Power rating and identification
markings
1.7.1.1 Power rating marking* EL 2102-01
Rated voltage(s) or voltage EL 2102-02
ranges(s) (V)*.
Multiple mains supply EL 2102-03
connections*.
Symbol for nature of supply, for EL 2102-04
d.c. only*:
Rated frequency or rated EL 2102-05
frequency range (Hz) *:
Rated current (mA or A)*: EL 2102-06
1.7.1.2 Identification markings* EL 2102-07
Manufacturer’s name or trade- EL 2102-08
mark or identification mark *:
Model identification or type EL 2102-09
reference *:
Symbol for Class II equipment EL 2102-10
only* :
Other markings and symbols*: EL 2102-11
1.7.1.3 Use of graphical symbols* EL 2102-12
1.7.2 Safety instructions and marking* EL 2102-13
1.7.2.1 General EL 2102-14
1.7.2.2 Disconnect devices* EL 2102-15
1.7.2.3 Overcurrent protective devices* EL 2102-16
1.7.2.4 IT power distribution systems* EL 2102-17
1.7.2.5 Operator access with a tool* EL 2102-18
1.7.2.6 Ozone* EL 2102-19
1.7.3 Short duty cycles* EL 2102-20
1.7.4 Supply voltage adjustment* EL 2102-21
1.7.5 Power outlets on the equipment* EL 2102-22
1.7.6 Fuse identification (marking, EL 2102-23
special fusing characteristics,
cross-reference)
Fuse(s) shall clearly and
adequately marked with fuse
number and rating*.
1.7.7 Wiring terminals EL 2102-24

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 15 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Marking Requirements EL 2102 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
1.7.7.1 Protective earthing and bonding EL 2102-25
terminals*
1.7.7.2 Terminals for a.c. mains supply EL 2102-26
conductors*
1.7.7.3 Terminals for d.c. mains supply EL 2102-27
conductors*
1.7.8 Controls and indicators EL 2102-28

1.7.8.1 Identification, location and EL 2102-29


marking *:
1.7.8.2 Colours* EL 2102-30
1.7.8.3 Symbols according to IEC EL 2102-31
60417*:

1.7.8.4 Markings using figures* : EL 2102-32


1.7.9 Isolation of multiple power EL 2102-33
sources*
1.7.10 Thermostats and other EL 2102-34
regulating devices*
1.7.11 Durability EL 2102-35
1.7.12 Removable parts* EL 2102-36
1.7.13 Replaceable batteries* EL 2102-37
Language(s)
1.7.14 Equipment for restricted access EL 2102-38
locations*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 16 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2103 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.1 Protection from electric shock and EL 2103-00
energy hazards*
2.1.1 Protection in operator access areas* EL 2103-01
2.1.1.1 Access to energized parts EL 2103-02
Test by inspection :
Test with test finger (Figure 2A)
Test with test pin (Figure 2B):
Test with test probe (Figure 2C)
2.1.1.2 Battery compartments * EL 2103-03
2.1.1.3 Access to ELV wiring EL 2103-04
Working voltage (Vpeak or Vrms);
minimum distance through insulation
(mm)
2.1.1.4 Access to hazardous voltage circuit EL 2103-05
wiring
2.1.1.5 Energy hazards : EL 2103-06
2.1.1.6 Manual controls EL 2103-07
2.1.1.7 Discharge of capacitors in equipment
Measured voltage (V); EL 2103-08
time-constant (s):
2.1.1.8 Energy hazards – d.c. mains supply
a) Capacitor connected to the d.c. EL 2103-09
mains supply :
b) Internal battery connected to the EL 2103-10
d.c. mains supply :
2.1.1.9 Audio amplifiers to be tested EL 2103-11
according to IEC 60065, cl. 9.1.1.:
2.1.2 Protection in service access areas EL 2103-12
2.1.3 Protection in restricted access EL 2103-13
locations
*- Total number of Requirements to be observed / inspected =
Total No of applicable Requirement =
No of Requirements for which the sample passed=
Total number of tests to be conducted =
Total No of applicable Tests =
No. of tests for which the sample passed=
Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.
...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 17 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2104 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.2 SELV circuits* EL 2104-00
2.2.2 Voltages under normal conditions EL 2104-01
2.2.3 Voltages under fault conditions EL 2104-02
2.2.4 Connection of SELV circuits to EL 2104-03
other circuits* :

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 18 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2105 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.3 TNV circuits* EL 2105-00
2.3.1 Type of TNV circuits: EL 2105-01
TNV-1 / TNV-2 / TNV-3
a) Limits of TNV-1: EL 2105-02
b) Limits of TNV-2 or TNV-3: EL 2105-03
Continuous voltages,
combination of AC and DC
values, are such that :

2.3.2 Separation from other circuits EL 2105-04


and from accessible parts*
2.3.2.1 General Requirements EL 2105-05
2.3.2.2 Protection by basic insulation EL 2105-06
2.3.2.3 Protection by earthing EL 2105-07
2.3.2.4 Protection by other EL 2105-08
constructions :
2.3.3 Separation from hazardous EL 2105-09
voltages
2.3.4 Connection of TNV circuits to EL 2105-10
other circuits
2.3.5 Test for operating voltages EL 2105-11
generated externally

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 19 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2106 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.4 Limited current circuits * EL 2106-00
2.4.1 General requirements * EL 2106-01
2.4.2 Limit values EL 2106-02
2.4.3 Connection of limited current EL 2106-03
circuits to other circuits*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 20 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2107 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.5 Limited power sources * EL 2107-00
a) Inherently limited output EL 2107-01
b) Impedance limited output EL 2107-02
c) Regulating network limited EL 2107-03 (See Annex CC)
output under normal operating
and single fault condition
Use of integrated circuit (IC)
current limiters
d) Overcurrent protective device EL 2107-04
limited output
Max. output voltage (V), EL 2107-05
Max. output current (A),
Max. apparent power (VA)
Current rating of overcurrent EL 2107-06
protective device (A)

*- Total number of Requirements to be observed / inspected = 01


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted = 06


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 21 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2108 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.6 Provisions for earthing and bonding* EL 2108-00
2.6.1 Protective earthing EL 2108-01
2.6.2 Functional earthing : EL 2108-02
The Functional earthing either
separated from hazardous voltages
by double or reinforced insulation or
by protectively earthed screen or
conductive part separated by at least
basic insulation, or safely connected
to Protective Bonding Conductor.*
Use of symbol for functional EL 2108-03
earthing:*
2.6.3 Protective earthing and protective EL 2108-04
bonding conductors*
2.6.3.2 Size of protective earthing EL 2108-05
conductors
Rated current (A), cross-sectional
area (mm2),
2.6.3.3 Size of protective bonding EL 2108-06
conductors
Protective current Rating (A), cross-
sectional area (mm2)
2.6.3.4 Resistance of earthing conductors EL 2108-07
and their terminations; resistance
(), voltage drop (V), test current (A),
duration (min):
2.6.3.5 Colour of insulation*: EL 2108-08
2.6.4 Terminals
2.6.4.2 Protective earthing and bonding EL 2108-09
terminals : Rated current(A), Type,
Nominal thread diameter (mm)
2.6.4.3 Separation of the protective earthing EL 2108-10
conductor from protective bonding
conductors*
2.6.5 Integrity of protective earthing*
2.6.5.1 Interconnection of equipment* EL 2108-11
2.6.5.2 Components in protective earthing EL 2108-12
conductors and protective bonding
conductors*
2.6.5.3 Disconnection of protective earth* EL 2108-13
2.6.5.4 Parts that can be removed by an EL 2108-14
operator*
2.6.5.5 Parts removed during servicing* EL 2108-15

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 22 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

2.6.5.6 Corrosion resistance* EL 2108-16


2.6.5.7 Screws for protective bonding* EL 2108-17
2.6.5.8 Reliance on telecommunication EL 2108-18
network or cable distribution system*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 23 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2109 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.7 Overcurrent and earth fault EL 2109-00
protection in primary circuits*
2.7.1 Basic requirements: EL 2109-01
Protection in primary circuits
against overcurrents, short-
circuits and earth faults shall be
provided, either as an integral
part of the equipment or as part
of building installation.
If pluggable equipment Type B or
permanently connected
equipment relies on protective
device external to the equipment
for protection, the equipment
installation Instructions shall so
state and shall also specify the
requirements for short-circuit
protection or overcurrent
protection or, where necessary,
for both.
2.7.2 Faults not simulated in 5.3.7* EL 2109-02
need not be fitted as an integral
part of the equipment
2.7.3 Short-circuit backup protection EL 2109-03
2.7.4 Number and location of protective EL 2109-04
devices :
2.7.5 Protection by several devices* EL 2109-05
2.7.6 Warning to service personnel* : EL 2109-06

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 24 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2110 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.8 Safety Interlocks* EL 2110-00
2.8.1 General principles* EL 2110-01
2.8.2 Protection requirements EL 2110-02
2.8.3 Inadvertent reactivation EL 2110-03
2.8.4 Fail-safe operation EL 2110-04
2.8.5 Moving parts EL 2110-05
2.8.6 Overriding* EL 2110-06
2.8.7 Switches, relays and their related EL 2110-07
circuits
2.8.7.1 Separation distances for contact EL 2110-08
gaps and their related circuits`
2.8.7.2 Overload test EL 2110-09
2.8.7.3 Endurance test EL 2110-10
2.8.7.4 Electric strength test EL 2110-11
2.8.8 Mechanical actuators EL 2110-12

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 25 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2111 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.9 Electrical insulation* EL 2111-00
2.9.1 Properties of insulating materials* EL 2111-01
2.9.2 Humidity conditioning EL 2111-02
Relative Humidity : 93 ±3 %,
Temperature: t at 40 ± 2°C
Duration : 120 hours
2.9.3 Grade of insulation* EL 2111-03
2.9.4 Separation from hazardous EL 2111-04
voltages*
Method(s) used

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 26 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2112 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
2.10 Clearances, creepage distances EL 2112-00
and distances through
Insulation*
2.10.1.1 Frequency * EL 2112-01
2.10.1.2 Pollution degrees* EL 2112-02
2.10.1.3 Reduced values for functional EL 2112-03
insulation
2.10.1.4 Intervening unconnected conductive EL 2112-04
parts
2.10.1.5 Insulation with varying dimensions EL 2112-05
2.10.1.6 Special separation requirements EL 2112-06
2.10.1.7 Insulation in circuits generating EL 2112-07
starting pulses
2.10.2 Determination of working voltage EL 2112-08
2.10.2.2 RMS working voltage EL 2112-09
2.10.2.3 Peak working voltage EL 2112-10
2.10.3 Clearances EL 2112-11
2.10.3.1 General EL 2112-12
2.10.3.2 Mains transient voltages*
a) AC mains supply * : EL 2112-13
b) Earthed d.c. mains supplies* ..............................
EL 2112-14
c) Unearthed d.c. mains supplies* : EL 2112-15
d) Battery operation* : EL 2112-16
2.10.3.3 Clearances in primary circuits EL 2112-17
2.10.3.4 Clearances in secondary circuits EL 2112-18
2.10.3.5 Clearances in circuits having EL 2112-19
starting pulses
2.10.3.6 Transients from a.c. mains supply : EL 2112-20
2.10.3.7 Transients from d.c. mains supply : EL 2112-21
2.10.3.8 Transients from telecommunication EL 2112-22
networks and cable distribution
systems ................................................................
2.10.3.9 Measurement of transient voltages
a) Transients from a mains supply EL 2112-23
For an a.c. mains supply
For a d.c. mains supply
b) Transients from a EL 2112-24
telecommunication network

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 27 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

2.10.4 Creepage distances* EL 2112-25


2.10.4.1 General EL 2112-26
2.10.4.2 Material group and comparative EL 2112-27
tracking index : CTI tests*
2.10.4.3 Minimum creepage distances EL 2112-28
2.10.5 Solid insulation EL 2112-29
2.10.5.1 General EL 2112-30
2.10.5.2 Distances through insulation EL 2112-31
2.10.5.3 Insulating compound as solid EL 2112-32
insulation
2.10.5.4 Semiconductor devices EL 2112-33
2.10.5.5. Cemented joints EL 2112-34
2.10.5.6 Thin sheet material – General EL 2112-35
2.10.5.7 Separable thin sheet material EL 2112-36
2.10.5.8 Non-separable thin sheet material EL 2112-37
2.10.5.9 Thin sheet material – standard test EL 2112-38
procedure
Electric strength test as per Cl.5.2.2
2.10.5.10 Thin sheet material – alternative EL 2112-39
test procedure
Electric strength test as per Cl.5.2.2
2.10.5.11 Insulation in wound components EL 2112-40
2.10.5.12 Wire in wound components
If Peak Working voltage >71 V
a) Basic insulation not under stress EL 2112-41
b) Basic, supplementary, reinforced EL 2112-42
insulation
c) Compliance with Annex U EL 2112-43
d) Where two winding wires in EL 2112-44
contact inside wound component;
angle between 45 and 90
2.10.5.13 Wire with solvent-based enamel in
wound components
a) Electric strength test (Type test EL 2112-45
as per Cl.5.2.2)
b) Electric Strength test (Routine EL 2112-46
test as per Cl.5.2.2)
2.10.5.14 Additional insulation in wound
components
If Peak Working Voltage >71V
a) Basic insulation not under stress EL 2112-47

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 28 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

b) Supplementary, reinforced EL 2112-48


insulation
2.10.6 Construction of printed boards*
2.10.6.1 Uncoated printed boards EL 2112-49
2.10.6.2 Coated printed boards EL 2112-50
2.10.6.3 Insulation between conductors on EL 2112-51
the same inner surface of a printed
board
2.10.6.4 Insulation between conductors on
different surfaces of a printed
board*
a) Minimum Thickness of EL 2112-52
insulation: 0.4mm or
b) Confirm with one of the EL 2112-53
specification and pass the relevant
tests as per Table 2R
2.10.7 Component external terminations EL 2112-54
2.10.8 Tests on coated printed boards and
coated components
2.10.8.1 Sample preparation and preliminary EL 2112-55
inspection*
2.10.8.2 Thermal conditioning EL 2112-56
2.10.8.3 Electric strength test EL 2112-57
2.10.8.4 Abrasion resistance test EL 2112-58
2.10.9 Thermal cycling EL 2112-59
2.10.10 Test for Pollution Degree 1 EL 2112-60
environment and insulating
compound
2.10.11 Tests for semiconductor devices EL 2112-61
and cemented joints
2.10.12 Enclosed and sealed parts EL 2112-62

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted :


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 29 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Wiring EL 2113 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
3.0 Wiring, connections and supply* EL 2113-00
3.1.1 Current rating and overcurrent EL 2113-01
protection
3.1.2 Protection against mechanical EL 2113-02
damage*
3.1.3 Securing of internal wiring* EL 2113-03
3.1.4 Insulation of conductors EL 2113-04
3.1.5 Beads and ceramic insulators EL 2113-05
3.1.6 Screws for electrical contact EL 2113-06
pressure*
3.1.7 Insulating materials in electrical EL 2113-07
connections*
3.1.8 Self-tapping and spaced thread EL 2113-08
screws*
3.1.9 Termination of conductors : EL 2113-09
10 N pull test
3.1.10 Sleeving on wiring* EL 2113-10

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 30 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Wiring EL 2114 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ Verdict
observation
3.2 Connection to a mains supply* EL 2114-00
3.2.1 Means of connection
3.2.1.1 Connection to an a.c. mains supply* EL 2114-01
3.2.1.2 Connection to a d.c. mains supply* EL 2114-02
3.2.2 Multiple supply connections EL 2114-03
3.2.3 Permanently connected equipment EL 2114-04
3.2.4 Appliance inlets: EL 2114-05
Are so Located that parts at hazardous voltage are
not accessible during insertion or removal of the
connector, connector can be inserted without
difficulty and after insertion of the connector, the
equipment is not supported by the connector for any
position of normal use on a flat surface
( appliance inlets complying with IEC 60309 or IEC
60320 considered to comply with this requirement.
3.2.5 Power supply cords
3.2.5.1 AC power supply cords* EL 2114-06
Rated current (A), cross-sectional area (mm²), AWG
3.2.5.2 DC power supply cords* EL 2114-07
3.2.6 Cord anchorages and strain relief
Mass of the equipment: EL 2114-08
Pull Force (N):
b) Longitudinal displacement: 2 mm (Max) EL 2114-09
3.2.7 Protection against mechanical damage EL 2114-10
3.2.8 Cord guards
a) Diameter or minor dimension D (mm) : EL 2114-11
Test mass (g) :
b) Radius of curvature of cord : 1.5 D (Min) EL 2114-12
3.2.9 Supply wiring space EL 2114-13
*- Total number of Requirements to be observed / inspected =
Total No of applicable Requirement =
No of Requirements for which the sample passed=
Total number of tests to be conducted =
Total No of applicable Tests =
No. of tests for which the sample passed=
Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.
...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 31 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Wiring EL 2115 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
3.3 Wiring terminals for connection EL 2115-00
of external conductors*
3.3.1 Wiring terminals* EL 2115-01
3.3.2 Connection of non-detachable EL 2115-02
power supply cords
3.3.3 Screw terminals* EL 2115-03
3.3.4 Conductor sizes to be EL 2115-04
connected
Rated current (A), cord/cable
type, cross-sectional area
(mm2)
3.3.5 Wiring terminal sizes EL 2115-05
Rated current (A), type, nominal
thread diameter (mm)
3.3.6 Wiring terminal design EL 2115-06
3.3.7 Grouping of wiring terminals* EL 2115-07
3.3.8 Stranded wire EL 2115-08

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 32 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Wiring EL 2116 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
3.4 Disconnection from the mains EL 2116-00
supply*
3.4.1 General Requirement EL 2116-01
A disconnect device or devices
shall be provided to disconnect
the equipment from the mains
supply for servicing.
3.4.2 Disconnect devices* EL 2116-02
3.4.3 Permanently connected EL 2116-03
equipment*
3.4.4 Parts which remain energized* EL 2116-04
3.4.5 Switches in flexible cords* EL 2116-05
3.4.6 Number of poles - single-phase EL 2116-06
and d.c. equipment*
3.4.7 Number of poles - three-phase EL 2116-07
equipment*
3.4.8 Switches as disconnect devices* EL 2116-08
3.4.9 Plugs as disconnect devices* EL 2116-09
3.4.10 Interconnected equipment* EL 2116-10
3.4.11 Multiple power sources* EL 2116-11

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 33 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Wiring EL 2117 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
3.5 Interconnection of equipment* EL 2117-00
3.5.1 General requirements* EL 2117-01
3.5.2 Types of interconnection EL 2117-02
circuits*
3.5.3 ELV circuits as interconnection EL 2117-03
circuits *
3.5.4 Data ports for additional EL 2117-04
equipment

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 34 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2118 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4 PHYSICAL REQUIREMENTS* EL 2118-00
4.1 Stability EL 2118-01
a) A unit having a mass of 7 kg EL 2118-02
or more shall not fall over when
tilted to an angle of 10° from its
normal upright position.
Alternatively, the unit is placed in
its intended position of use on a
plane, inclined at an angle of 10°
to the horizontal, and then
rotated slowly through an angle
of 360° about its normal vertical
axis.
b) A floor-standing unit having a EL 2118-03
mass of 25 kg or more shall not
fall over when a force equal to
20 % of the weight of the unit,
but not more than 250 N, is
applied in any direction except
upwards, at a height not
exceeding 2 m from the floor.
c) A floor-standing unit shall not EL 2118-04
fall over when a constant
downward force of 800 N is
applied at the point of maximum
moment to any horizontal
surface of at least 125 mm by at
least 200 mm, at a height up to
1 m from the floor.

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 35 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2119 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4.2 Mechanical Strength EL 2119-00
4.2.1 General EL 2119-01
4.2.2 Steady force test, 10 N EL 2119-02
4.2.3 Steady force test, 30 N EL 2119-03
4.2.4 Steady force test, 250 N EL 2119-04
4.2.5 Impact test EL 2119-05
a) Fall test as per Fig. 4A EL 2119-06
b) Swing test as per Fig. 4A EL 2119-07
4.2.6 Drop test; EL 2119-08
height (mm) :
4.2.7 Stress relief test EL 2119-09
4.2.8 Cathode Ray Tubes EL 2119-10
4.2.9 High Pressure Lamps* EL 2119-11
4.2.10 Wall or ceiling mounted EL 2119-12
equipment; force(N)

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 36 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2120 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4.3 Design and Construction* EL 2120-00
4.3.1 Edges and corners* EL 2120-01
4.3.2 Handles and manual controls; EL 2120-02
force (N) ................................................................
4.3.3 Adjustable controls EL 2120-03
4.3.4 Securing of parts EL 2120-04
4.3.5 Connections by Plugs and EL 2120-05
Sockets*
4.3.6 Direct plug-in equipment EL 2120-06
Torque EL 2120-07
Compliance with the relevant EL 2120-08
mains plug standard
4.3.7 Heating elements in earthed EL 2120-09
equipment*
4.3.8 Batteries
Portable secondary sealed
cells and batteries (other than
button) containing alkaline or
other non-acid electrolyte shall
comply with IEC 62133
a) Overcharging of a EL 2120-10
rechargeable battery
b) Unintentional charging of a EL 2120-11
non-rechargeable battery
c) Reverse charging of a EL 2120-12
rechargeable battery
d) Excessive discharging rate EL 2120-13
for any battery
e) Electric strength as per EL 2120-14
Cl.5.3.9.2
4.3.9 Oil & grease* EL 2120-15
4.3.10 Dust, powders, liquids and EL 2120-16
gases
4.3.11 Containers for liquids or gases EL 2120-17
4.3.12 Flammable liquids EL 2120-18
4.3.13 Radiation
4.3.13.2 Ionizing radiation EL 2120-19
4.3.13.3 Effect of ultraviolet (UV) EL 2120-20
radiation on materials

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 37 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

4.3.13.4 Human exposure to ultraviolet EL 2120-21


(UV) radiation
4.3.13.5 Lasers (including laser diodes)
and LED’s:
4.3.13.5.1 Lasers (including laser diodes) EL 2120-22
For laser see IEC 60825-1,
respective part as applicable.
Laser class ................................
4.3.13.5.2 Light emitting diodes (LED’s) EL 2120-23
4.3.13.6 Other types* EL 2120-24

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 38 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2121 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4.4 Protection against hazardous EL 2121-00
moving parts
4.4.1 General EL 2121-01
4.4.2 Protection in operator access EL 2121-02
areas
4.4.3 Protection in restricted access EL 2121-03
locations *
4.4.4 Protection in service access EL 2121-04
areas*
4.4.5 Protection against moving fan EL 2121-05
blades
4.4.5.1 General* EL 2121-06 m=
r=
N=
K=
Not considered likely to cause EL 2121-07 =
pain or injury. a)……..….:
Is considered likely to cause EL 2121-08 =
pain, not injury. b)
Considered likely to cause EL 2121-09
injury. c)………………..……:
4.4.5.2 Protection for users* EL 2121-10
Use of symbol or warning* EL 2121-11
4.4.5.3 Protection for service persons* EL 2121-12
Use of symbol or warning * EL 2121-13

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 39 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Thermal Properties EL 2122 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4.5 Thermal Requirements* EL 2122-00
4.5.1 General EL 2122-01
4.5.2 Temperature tests EL 2122-02
4.5.3 Temperature limits for materials* EL 2122-03
4.5.4 Touch temperature limits* EL 2122-04
4.5.5 Resistance to abnormal heat EL 2122-05

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 40 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2123 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4.6 Openings in enclosures* EL 2123-00
4.6.1 Top and side openings EL 2123-01
Dimensions (mm) :
4.6.2 Bottoms of fire enclosures : EL 2123-02
Construction of the bottom,
dimensions (mm) :
4.6.3 Doors or covers in fire EL 2123-03
enclosures*
4.6.4 Openings in transportable EL 2123-04
equipment
4.6.4.1 Constructional design measures EL 2123-05
Dimensions (mm)
4.6.4.2 Evaluation measures for larger EL 2123-06
openings
4.6.4.3 Use of metallized parts EL 2123-07
4.6.5 Adhesives for constructional EL 2123-08
purposes: Compliance is
checked by examination of the
construction and of the available
data. If such data is not
available, compliance is
checked by the following tests.
a)Temperature Conditioning at : EL 2123-09
100 °C ± 2 °C for one week; or
90 °C ± 2 °C for three weeks;
or
82 °C ± 2 °C for eight weeks.
After temperature conditioning EL 2123-10
b) Leave the sample between
20°C to 30°C for 1 hour
c) Place the sample at EL 2123-11
- 40°C±2°C for 4 hours
d) Remove and allow the EL 2123-12
sample to come to any
convenient temperature
between 20 °C and
30 °C for 8 h;
e) Place the sample in a cabinet EL 2123-13
at 91 % to 95 % relative
humidity for 72 h;

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 41 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

f) Remove the sample and leave EL 2123-14


it at any convenient temperature
between 20 °C and 30 °C for 1
h;
g) Place the sample in an oven EL 2123-15
at the temperature used for the
temperature conditioning for 4 h;
h) Remove the sample and EL 2123-16
allow it to reach any convenient
temperature between 20 °C; and
30 °C for 8 h.
i) The sample is then EL 2123-17
immediately subjected to the
tests of Cl.4.2 as applicable.

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 42 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Fire Safety EL 2124 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
4.7 Resistance to fire* EL 2124-00
4.7.1 Reducing the risk of ignition and
spread of flame
Method 1, selection and EL 2124-01
application of components wiring
and materials OR
Method 2, application of all of EL 2124-02
simulated fault condition tests
4.7.2 Conditions for a fire enclosure*
4.7.2.1 Parts requiring a fire enclosure* EL 2124-03
4.7.2.2 Parts not requiring a fire EL 2124-04
enclosure
4.7.3 Materials* EL 2124-05
4.7.3.1 General* EL 2124-06
a)Class of material used* EL 2124-07
b) Where HB40 CLASS EL 2124-08
MATERIAL, HB75 CLASS
MATERIAL or HBF CLASS
FOAMED MATERIAL, is
required,
material passing the glow-wire
test at 550 °C according to IEC
60695-2-11 is acceptable as an
alternative.
c) Where it is not practical to EL 2124-09
protect components against
overheating under fault
conditions, the components shall
be mounted on V-1 CLASS
MATERIAL. Additionally, such
components shall be separated
from material of a class lower
than V-1 CLASS MATERIAL by
at least 13 mm of air, or by a
solid barrier of V-1 CLASS
MATERIAL.
4.7.3.2 Materials for fire enclosures
a) For MOVABLE EQUIPMENT EL 2124-10
having a total mass not
exceeding 18 kg, the material of
a FIRE ENCLOSURE, in the
thinnest significant wall
thickness used, shall be of V-1
CLASS MATERIAL or shall pass
the test of Clause A.2.

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 43 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

b) For MOVABLE EQUIPMENT EL 2124-11


having a total mass exceeding
18 kg and for all STATIONARY
EQUIPMENT, the material of a
FIRE ENCLOSURE, in the
thinnest significant wall
thickness used, shall be of 5VB
CLASS MATERIAL or shall pass
the test of Clause A.1.
c) Materials for components that EL 2124-12
fill an opening in a FIRE
ENCLOSURE, and that are
intended to be mounted in this
opening shall :
be of V-1 CLASS MATERIAL;
or
pass the tests of Clause A.2; or
comply with the flammability
requirements of the relevant IEC
component standard
d) Plastic materials of a FIRE EL 2124-13
ENCLOSURE shall be located
more than 13 mm through air
from arcing parts such as
unenclosed commutators and
unenclosed switch contacts.
e)Plastic materials of a FIRE EL 2124-14
ENCLOSURE located less than
13mm through air from non-
arcing parts which, under any
condition of normal or abnormal
operation,could attain a
temperature sufficient to ignite
the material, shall be capable of
passing the test of IEC 60695-2-
20.
The average time to ignition of
the samples shall be not less
than 15sec. If the sample melts
through without igniting, the time
at which this occurs is not
considered to be the time to
ignition.
4.7.3.3 Materials for components and
other parts outside fire
enclosures *

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 44 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

a) Materials shall be of : EL 2124-15


− HB75 CLASS MATERIAL if
the thinnest significant thickness
of this material is < 3 mm,
or
− HB40 CLASS MATERIAL if
the thinnest significant thickness
of this material is ≥ 3 mm,
or
− HBF CLASS FOAMED
MATERIAL.*
b) Connectors shall comply with EL 2124-16
one of the following:
− be made of V-2 CLASS
MATERIAL; or
− pass the tests of Clause A.2;
or
− comply with the flammability
requirements of the relevant IEC
component standard; or
− be mounted on V-1 CLASS
MATERIAL and be of a small
size; or
− be located in a SECONDARY
CIRCUIT supplied by a power
source that is limited to a
maximum of 15 VA (see 1.4.11)
under normal operating
conditions and after a single
fault
in the equipment (see 1.4.14).
4.7.3.4 Materials for components and
other parts inside fire enclosures
a) Inside FIRE ENCLOSURES, EL 2124-17
materials for components and
other parts shall comply with
one of the following:
− be of V-2 CLASS MATERIAL
or
HF-2 CLASS FOAMED
MATERIAL; or
− pass the flammability test
described in Clause A.2; or
− meet the flammability
requirements of a relevant IEC
component standard that
includes such requirements.
Requirements for voltage EL 2124-18
dependent resistors (VDR’s)
are in Annex Q.*

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 45 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

4.7.3.5 Materials for air filter assemblies EL 2124-19


:
Air filter assemblies shall be
constructed of V-2 CLASS
MATERIAL, or HF-2 CLASS
FOAMED
MATERIAL.
4.7.3.6 Materials used in high-voltage
components
a) High-voltage components EL 2124-20
operating at peak-to-peak
voltages exceeding 4 kV shall
either be
of V-2 CLASS MATERIAL, or
HF-2 CLASS FOAMED
MATERIAL, or comply with 14.4
of IEC 60065 or
pass the needle flame test
according to IEC 60695-11-5.
b) Compliance is checked by EL 2124-21
inspection of the equipment and
material data sheets and, if
necessary, by
− the tests for V-2 CLASS
MATERIAL or HF-2 CLASS
FOAMED MATERIAL; or
− the test described in 14.4 of
IEC 60065; or
− the needle flame test
according to IEC 60695-11-5.
c) In addition to above, the EL 2124-22
following details apply, referring
to clauses of IEC 60695-11-5:
Clause 7 - Severities
Clause 8 - Conditioning EL 2124-23
Clause 11 - Evaluation of test EL 2124-24
results

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=
Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.
...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 46 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Insulating Properties EL 2125 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
5.0 ELECTRICAL EL 2125-00
REQUIREMENTS AND
SIMULATED ABNORMAL
CONDITIONS*
5.1 Touch current and protective EL 2125-01
conductor current*
5.1.2 Configuration of equipment EL 2125-02
under test (EUT)*
5.1.2.1 Single connection to an a.c. EL 2125-03
mains supply*
5.1.2.2 Redundant multiple connections EL 2125-04
to an a.c. mains supply*
5.1.2.3 Simultaneous multiple EL 2125-05
connections to an a.c. mains
supply
5.1.3 Test circuit EL 2125-06
5.1.4 Application of measuring EL 2125-07
instrument
5.1.5 Test procedure EL 2125-08
5.1.6 Test measurements
a) r.m.s value of voltage, U2 EL 2125-09
measured using the instrument
as per Fig. D.1 or
r.m.s value of current measured
using the instrument as per Fig.
D.2
Alternatively, peak value of
voltage, U2, is measured using
the measuring instrument
described in Clause D.1
b) Measured touch current (mA): EL 2125-10
c) Calculated value of TOUCH EL 2125-11
CURRENT (mA) = U2 / 500
d ) Measured protective EL 2125-12
conductor current(mA)
e) Max. protective conductor EL 2125-13
current =5% of Input current
5.1.7 Equipment with touch current EL 2125-14
exceeding 3.5 mA
5.1.7.1 General EL 2125-15
5.1.7.2 Simultaneous multiple EL 2125-16
connections to the supply

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 47 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

5.1.8 Touch currents to EL 2125-17


telecommunication networks
and cable distribution systems
and from telecommunication
networks
5.1.8.1 Limitation of the touch current to EL 2125-18
a telecommunication network or
to a cable distribution system
Supply voltage (V)
Measured touch current (mA)
Max. allowed touch current (mA)
5.1.8.2 Summation of touch currents EL 2125-19
from telecommunication
networks
a) EUT with earthed
telecommunication ports :
b) EUT whose
telecommunication ports have
no reference to protective earth

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 48 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Insulating Properties EL 2126 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
5.2 Electric strength* EL 2126-00
5.2.1 General* EL 2126-01
5.2.2 Test procedure
a) The test voltages for electric EL 2126-02
strength for the appropriate
grade of insulation
[FUNCTIONAL
INSULATION if required by
5.3.4 b), BASIC INSULATION,
SUPPLEMENTARY
INSULATION or
REINFORCED INSULATION]
are as specified in either:
− Table 5B using the PEAK
WORKING VOLTAGE (U), as
determined in 2.10.2; or
− Table 5C using the
REQUIRED WITHSTAND
VOLTAGE, as determined in
G.4.

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 49 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Insulating Properties EL 2127 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
5.3 Abnormal operating and fault EL 2127-00
conditions
5.3.1 Protection against overload and EL 2127-01
abnormal operation
5.3.2 Motors EL 2127-02
5.3.3 Transformers EL 2127-03
5.3.4 Functional insulation: EL 2127-04
5.3.5 Electromechanical components EL 2127-05
5.3.6 Audio amplifiers in ITE : EL 2127-06
5.3.7 Simulation of faults EL 2127-07
5.3.8 Unattended equipment EL 2127-08
5.3.9 Compliance criteria for abnormal
operating and fault conditions*
5.3.9.1 During the tests EL 2127-09
5.3.9.2 After the tests EL 2127-10

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 50 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Communicating Connection EL 2128 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
6.1 Protection of telecommunication EL 2128-00
network service persons, and
users of other equipment
connected to the network, from
hazards in the equipment
6.1.1 Protection from hazardous EL 2128-01
voltages
6.1.2 Separation of the
telecommunication network from
earth*
6.1.2.1 Requirements: EL 2128-02
- Surge suppressors that bridge
the insulation shall have a
minimum rated operating
voltage Uop of
Uop =Upeak + ΔUsp + ΔUsa

Where Upeak is 360V or 180V


ΔUsp is the maximum increase of
the rated operating voltage due
to variations in component
production(If not specified by the
manufacturer, shall be taken as
10% of the rated operating
voltage of the component)

ΔUsa is the maximum increase of


the rated operating voltage due
to the component ageing over
the expected life of the
equipment(If not specified by the
manufacturer, shall be taken as
10% of the rated operating
voltage of the component)

-Insulation is subjected to
electric strength test according
to 5.2.2. The a.c test voltage is
1.5kV or 1.0kV

- Components bridging the


insulation that are left in place
during electric strength testing
shall not be damaged. There
shall be no breakdown of
insulation during electric
strength testing.

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 51 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
6.1.2.2 Exclusions EL 2128-03

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 52 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Communicating Connection EL 2129 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
6.2 Protection of equipment users EL 2129-00
from overvoltages on
telecommunication networks*
6.2.1 Separation requirements EL 2129-01
6.2.2 Electric strength test procedure EL 2129-02
6.2.2.1 Impulse test EL 2129-03
6.2.2.2 Steady-state test EL 2129-04
6.2.2.3 Compliance criteria EL 2129-05

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 53 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Communicating Connection EL 2130 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
6.3 Protection of the EL 2130-00
telecommunication wiring
system from overheating
a)If current limiting is due to the EL 2130-01
inherent impedance of the
power source, the output current
into any resistive load, including
a short-circuit, is measured. The
current limit shall not be
exceeded after 60 s of test.
Max. output current (A) :
b) If current limiting is provided EL 2130-02
by an overcurrent protective
device having a specified
time/current characteristic:
– the time/current characteristic
shall show that a current equal
to 110 % of the current limit will
be interrupted within 60 min; and
c) the output current into any EL 2130-03
resistive load, including a short-
circuit, with the overcurrent
protective device bypassed,
measured after 60 s of test, shall
not exceed 1 000/U,
where U is the output voltage
measured in accordance with
1.4.5 with all load circuits
disconnected.

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 54 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

d) If current limiting is provided EL 2130-04


by an overcurrent protective
device that does not have a
specified time/current
characteristic:
– the output current into any
resistive load, including a short-
circuit, shall not exceed the
current limit after 60 s of test;
and
– the output current into any
resistive load, including a short-
circuit, with the overcurrent
protective device bypassed,
measured after 60 s of test, shall
not exceed 1 000/U, where
U is the output voltage
measured in accordance with
1.4.5 with all load circuits
disconnected.

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 55 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Connection to cable distribution system EL 2131 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
7 Connection to cable distribution EL 2131-00
systems*
7.1 General requirements* EL 2131-01
7.2 Protection of cable distribution EL 2131-02
system service persons, and
users of other equipment
connected to the system, from
hazardous voltages in the
equipment
7.3 Protection of equipment users EL 2131-03
from overvoltages on the cable
distribution system
7.4 Insulation between primary EL 2131-04
circuits and cable distribution
systems
7.4.1 General EL 2131-05
7.4.2 Voltage surge test EL 2131-06
7.4.3 Impulse test EL 2131-07

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 56 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Fire Safety EL 2132 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
A ANNEX A, TESTS FOR EL 2132-00
RESISTANCE TO HEAT AND
FIRE
A.1 Flammability test for fire EL 2132-01
enclosures of movable
equipment having a total mass
exceeding 18 kg, and of
stationary equipment (see
4.7.3.2)
A.1.1 Samples: EL 2132-02
Wall thickness (mm):
A.1.2 Conditioning of samples; EL 2132-03
temperature (C) :
A.1.3 Mounting of samples : EL 2132-04
A.1.4 Test flame (see IEC 60695-11- EL 2132-05
3)
Flame A, B, C or D :
A.1.5 Test procedure EL 2132-06
A.1.6 Compliance criteria EL 2132-07
Sample 1 burning time (s):
Sample 2 burning time (s):
Sample 3 burning time (s):
A.2 Flammability test for fire EL 2132-08
enclosures of movable
equipment having a total mass
not exceeding 18 kg, and for
material and components
located inside fire enclosures
(see 4.7.3.2 and 4.7.3.4)
A.2.1 Samples, material: EL 2132-09
Wall thickness (mm):
A.2.2 Conditioning of samples; EL 2132-10
temperature (°C) :
A.2.3 Mounting of samples : EL 2132-11
A.2.4 Test flame (see IEC 60695-11- EL 2132-12
4)
Flame A, B or C :
A.2.5 Test procedure EL 2132-13
A.2.6 Compliance criteria EL 2132-14
Sample 1 burning time (s):

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 57 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Fire Safety EL 2132 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
Sample 2 burning time (s):
Sample 3 burning time (s):
A.2.7 Alternative test acc. to IEC EL 2132-15
60695-11-5, cl. 5 and 9
Sample 1 burning time (s):
Sample 2 burning time (s):
Sample 3 burning time (s):
A.3 Hot flaming oil test (see 4.6.2) EL 2132-16
A.3.1 Mounting of samples EL 2132-17
A.3.2 Test procedure EL 2132-18
A.3.3 Compliance criterion EL 2132-19

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 58 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Insulating Properties EL 2133 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
B ANNEX B, MOTOR TESTS EL 2133-00
UNDER ABNORMAL
CONDITIONS (see 4.7.2.2 and
5.3.2)
B.1 General requirements EL 2133-01
Position :
Manufacturer :
Type :
Rated values :
B.2 Test conditions EL 2133-02
B.3 Maximum temperatures EL 2133-03
B.4 Running overload test EL 2133-04
B.5 Locked-rotor overload test EL 2133-05
Test duration (days):
Electric strength test: test
voltage (V) :
B.6 Running overload test for d.c. EL 2133-06
motors in secondary circuits
B.6.1 General EL 2133-07
B.6.2 Test procedure EL 2133-08
B.6.3 Alternative test procedure EL 2133-09
B.6.4 Electric strength test; test EL 2133-10
voltage (V):
B.7 Locked-rotor overload test for EL 2133-11
d.c. motors in secondary
circuits
B.7.1 General EL 2133-12
B.7.2 Test procedure EL 2133-13
B.7.3 Alternative test procedure EL 2133-14
B.7.4 Electric strength test; test EL 2133-15
voltage (V) :
B.8 Test for motors with capacitors EL 2133-16
B.9 Test for three-phase motors EL 2133-17
B.10 Test for series motors EL 2133-18
Operating voltage (V) :

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 59 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 60 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2134 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
C ANNEX C, TRANSFORMERS EL 2134-00
(see 1.5.4 and 5.3.3)*
Position :
Manufacturer :
Type :
Rated values :
Method of protection:
C.1 Overload test EL 2134-01
C.2 Insulation EL 2134-02
Protection from displacement of
windings:

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 61 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Insulating Properties EL 2135 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
D ANNEX D, MEASURING EL 2135-00
INSTRUMENTS FOR TOUCH-
CURRENT TESTS (see 5.1.4)
D.1 Measuring instrument EL 2135-01
D.2 Alternative measuring EL 2135-02
instrument

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 62 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Thermal Properties EL 2136– V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
E ANNEX E, TEMPERATURE EL2136-00
RISE OF A WINDING (see
1.4.13)

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 63 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2137 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
F ANNEX F, MEASUREMENT EL2137-00
OF CLEARANCES AND
CREEPAGE DISTANCES
(see 2.10 and Annex G)

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 64 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical safety EL 2138 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
G ANNEX G, ALTERNATIVE EL 2138-00
METHOD FOR DETERMINING
MINIMUM CLEARANCES
G.1 Clearances EL 2138-01
G.1.1 General EL 2138-02
G.1.2 Summary of the procedure for EL 2138-03
determining minimum
clearances
G.2 Determination of mains EL 2138-04
transient voltage (V)
G.2.1 AC Mains supply EL 2138-05
G.2.2 Earthed d.c. mains supplies EL 2138-06
G.2.3 Unearthed d.c. mains supplies EL 2138-07
G.2.4 Battery operation EL 2138-08
G.3 Determination of EL 2138-09
telecommunication network
transient voltage (V)
G.4 Determination of required EL 2138-10
withstand voltage (V)
G.4.1 Mains transients and internal EL 2138-11
repetitive peaks
G.4.2 Transients from EL 2138-12
telecommunication networks:
G.4.3 Combination of transients EL 2138-13
G.4.4 Transients from cable EL 2138-14
distribution systems
G.5 Measurement of transient EL 2138-15
voltages (V)
a) Transients from a mains
supply
For an a.c. mains supply
For a d.c. mains supply
b) Transients from a
telecommunication network
G.6 Determination of minimum EL 2138-16
clearances

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 65 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 66 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Radiation Safety EL 2139 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
H ANNEX H, IONIZING EL 2139-00
RADIATION (see 4.3.13)

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 67 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2140 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
J ANNEX J, TABLE OF EL 2140-00
ELECTROCHEMICAL
POTENTIALS (see 2.6.5.6)*
Metal(s) used :

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 68 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to General Requirement EL 2141 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
K ANNEX K, THERMAL EL 2141-00
CONTROLS (see 1.5.3 and
5.3.8)*
K.1 Making and breaking capacity EL 2141-01
K.2 Thermostat reliability; operating EL 2141-02
voltage (V) :
K.3 Thermostat endurance test; EL 2141-03
operating voltage (V) :
K.4 Temperature limiter endurance; EL 2141-04
operating voltage (V) :
K.5 Thermal cut-out reliability EL 2141-05
K.6 Stability of operation EL 2141-06

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 69 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to General Requirement EL 2142 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
L ANNEX L, NORMAL LOAD EL 2142-00
CONDITIONS FOR SOME
TYPES OF ELECTRICAL
BUSINESS EQUIPMENT (see
1.2.2.1 and 4.5.2)*
L.1 Typewriters* EL 2142-01
L.2 Adding machines and cash EL 2142-02
registers*
L.3 Erasers* EL 2142-03
L.4 Pencil sharpeners* EL 2142-04
L.5 Duplicators and copy EL 2142-05
machines*
L.6 Motor-operated files* EL 2142-06
L.7 Other business equipment* EL 2142-07

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 70 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2143 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
M ANNEX M, CRITERIA FOR EL 2143-00
TELEPHONE RINGING
SIGNALS (see 2.3.1)
M.1 Introduction* EL 2143-01
M.2 Method A EL 2143-02
M.3 Method B EL 2143-03
M.3.1 Ringing signal EL 2143-04
M.3.1.1 Frequency (Hz) ................................
EL 2143-05
M.3.1.2 Voltage (V) .............................................................
EL 2143-06
M.3.1.3 Cadence; time (s), voltage (V) ...............................
EL 2143-07
M.3.1.4 Single fault current (mA) ................................
EL 2143-08
M.3.2 Tripping device and monitoring EL 2143-09
voltage ................................................................
M.3.2.1 Conditions for use of a tripping EL 2143-10
device or a monitoring voltage
M.3.2.2 Tripping device EL 2143-11
M.3.2.3 Monitoring voltage (V) ................................
EL 2143-12

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 71 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical safety EL 2144 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
N ANNEX N, IMPULSE TEST EL 2144-00
GENERATORS (see 1.5.7.2,
1.5.7.3, 2.10.3.9, 6.2.2.1, 7.3.2,
7.4.3 and Clause G.5)
N.1 ITU-T impulse test generators EL 2144-01
N.2 IEC 60065 impulse test EL 2144-02
generator

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 72 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to General Requirements EL 2145– V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
P ANNEX P, NORMATIVE EL 2145-00
REFERENCES

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 73 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to General Requirements EL 2146 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
Q ANNEX Q, Voltage dependent EL 2146-00
resistors (VDRs) (see 1.5.9.1)
A VDR shall comply with iec
61051-2, whether a fire
enclosure is provided or not,
taking into account all of the
following:
a) Preferred climatic categories
Lower category temperature:
-10ºC
Upper category temperature:
+85ºC
Duration of damp Test, steady
state test:21 days

b) Maximum continuous
voltage:
Atleast 1,25 times the rated
voltage of the equipment or
Atleast 1,25 times the upper
voltage of the rated voltage
range
c) Combination pulse : EL 2146-01
d) Body of the VDR shall EL 2146-02
comply with Needle flame test
according to IEC 60695-11-5
with the following test
severities:
duration of application of the
test flame: 10 s
after flame time: 5s
[This test is not required if VDR
complies with V-1 CLASS
MATERIAL]
*- Total number of Requirements to be observed / inspected =
Total No of applicable Requirement =
No of Requirements for which the sample passed=
Total number of tests to be conducted =
Total No of applicable Tests =
No. of tests for which the sample passed=
Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.
...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 74 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2147– V1.4
Tests relating to General Requirement
Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
R ANNEX R, EXAMPLES OF EL 2147-00
REQUIREMENTS FOR
QUALITY CONTROL
PROGRAMMES*
R.1 Minimum separation distances EL 2147-01
for unpopulated coated printed
boards (see 2.10.6.2)*
R.2 Reduced clearances (see EL 2147-02
2.10.3)*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 75 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to General Requirement EL 2148 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
S ANNEX S, PROCEDURE FOR EL 2148-00
IMPULSE TESTING (see
6.2.2.3)*
S.1 Test equipment* EL 2148-01
S.2 Test procedure* EL 2148-02
S.3 Examples of waveforms during EL 2148-03
impulse testing*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 76 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2149 – V1.4
Tests relating to Protection against Ingress of water
Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
T ANNEX T, GUIDANCE ON EL 2149-00
PROTECTION AGAINST
INGRESS OF WATER
(see 1.1.2)*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 77 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2150 – V1.4
Tests relating to Wiring
Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
U ANNEX U, INSULATED EL2150-00
WINDING WIRES FOR USE
WITHOUT INTERLEAVED
INSULATION (see 2.10.5.4)
U.1 GENERAL EL2150-01
U.2 TYPE TESTS EL2150-02
U.2.1 GENERAL EL2150-03
U.2.2 ELECTRIC STRENGTH EL2150-04
U.2.2.1 SOLID ROUND WINDING WIRE EL2150-05
AND STRANDED WINDING
WIRES
U.2.2.1.1 WIRES WITH NOMINAL EL2150-06
CONDUCTOR DIAMETER
UPTO AND INCLUDING
0.100MM
U.2.2.1.2 WIRES WITH NOMINAL EL2150-07
CONDUCTOR DIAMETER
OVER 0.100MM AND
INCLUDING 2.500MM
U.2.2.1.3 WIRES WITH NOMINAL EL2150-08
CONDUCTOR DIAMETER
OVER 2.500MM
U.2.2.2 SQUARE OR RECTANGULAR EL2150-09
WIRES
U.2.3 FLEXIBILITY AND ADHERENCE EL2150-10
U.2.4 HEAT SHOCK EL2150-11
U.2.5 RETENTION OF ELECTRIC EL2150-12
STRENGTH AFTER BENDING
U.3 TESTING DURING EL2150-13
MANUFACTURING
U.3.1 GENERAL EL2150-14
U.3.2 ROUTINE TESTS EL2150-15
U.3.3 SAMPLING TEST EL2150-16

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =

No of Requirements for which the sample passed=


Total number of tests to be conducted =
Total No of applicable Tests =

No. of tests for which the sample passed=

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 78 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.
...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 79 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2151 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
V ANNEX V, AC POWER EL 2151-00
DISTRIBUTION SYSTEMS
(see 1.6.1) *
V.1 Introduction* EL 2151-01
V.2 TN power distribution systems EL 2151-02
V.3 TT Power Distribution systems EL 2151-03
V.4 IT Power Distribution systems EL 2151-04

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 80 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2152 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
W ANNEX W, SUMMATION OF EL 2152-00
TOUCH CURRENTS *
W.1 Touch current from electronic EL 2152-01
circuits*
W.1.1 Floating circuits* EL 2152-02
W.1.2 Earthed circuits* EL 2152-03
W.2 Interconnection of several EL 2152-04
equipments*
W.2.1 Isolation* EL 2152-05
W.2.2 Common return, isolated from EL 2152-06
earth*
W.2.3 Common return, connected to EL 2152-07
protective earth*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 81 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2153– V1.4
Tests relating to Electrical Safety
Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
X ANNEX X, MAXIMUM EL 2153-00
HEATING EFFECT IN
TRANSFORMER TESTS
(see clause C.1)*
X.1 Determination of maximum EL 2153-01
input current*
X.2 Overload test procedure* EL 2153-02

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 82 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Radiation Safety EL 2154– V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
Y ANNEX Y, ULTRAVIOLET EL 2154-00
LIGHT CONDITIONING TEST
(see 4.3.13.3)
Y.1 EL 2154-01
Test apparatus ................................
Y.2 EL 2154-02
Mounting of test samples ................................
Y.3 Carbon-arc light-exposure EL 2154-03
apparatus ...............................................................
Y.4 Xenon-arc light exposure EL 2154-04
apparatus ...............................................................

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 83 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

EL 2155– V1.4
Tests relating to Electrical Safety
Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
Z ANNEX Z, OVERVOLTAGE EL 2155-00
CATEGORIES (see 2.10.3.2
and Clause G.2)*

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 84 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2156 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
AA ANNEX AA, MANDREL TEST EL 2156-00
(see 2.10.5.8)

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 85 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Electrical Safety EL 2158 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
CC Evaluation of integrated circuit EL 2158-00
(IC) current limiters*
CC.1 Integrated circuit (IC) current EL 2158-01
limiters*
CC.2 Test program 1 EL 2158-02
CC.3 Test program 2 EL 2158-03
CC.4 Test program 3 EL 2158-04
CC.5 Compliance EL 2158-05

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 86 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2159 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
DD Requirements for the mounting EL 2159-00
means of rack-mounted
equipment*
DD.1 General
DD.2 Mechanical strength test, EL 2159-01
variable N………………..:
DD.3 Mechanical strength test, 250N, EL 2159-02
including end stops………..:
DD.4 Compliance*………………….: EL 2159-03

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 87 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

Tests relating to Mechanical Properties EL 2160 – V1.4


Cl. No. Test / Requirement name Test Code Test result/ observation Verdict
EE ANNEX EE, Household and EL 2160-00
home/office document/media
shredders
EE.1 General
EE.2 Markings and instructions* EL 2160-01
Use of markings or
symbols*…………………………
:
Information of user instructions,
maintenance and/or servicing
instructions*……………………
……:
EE.3 Inadvertent reactivation EL 2160-02
test…………………………:
EE.4 Disconnection of power to EL 2160-03
hazardous moving parts*
Use of markings or
symbols*………………………:
EE.5 Protection against hazardous
moving parts
Test with test finger (Figure 2A) EL 2160-04
……………………:
Test with wedge probe (Figure EL 2160-05
EE1 and EE2) ……:

*- Total number of Requirements to be observed / inspected =


Total No of applicable Requirement =
No of Requirements for which the sample passed=

Total number of tests to be conducted =


Total No of applicable Tests =
No. of tests for which the sample passed=

Certificate: It is certified that the above tests were performed and found to be passing/failing in the
requirement tested.

...............................................................................
(Approving Authority)

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 88 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

1.5.1 TABLE: List of components


Object/part no. Manufacturer/ Type/model Technical data Standard Mark(s) of
trademark conformity

Supplementary information:

1.6.2 TABLE: Electrical data (in normal conditions)


U (V) I (A) Irated (A) P (W) Fuse # Ifuse (A) Condition/status

Supplementary information:

2.1.1.5 TABLE: Energy hazard measurement


Voltage (rated) Current (rated) Voltage (max.) Current (max.) VA (max.)
(V) (A) (V) (A) (VA)

Supplementary information:

2.1.1.7 TABLE: Discharge test


Condition  calculated  measured t u 0V Comments
(s) (s) (s)

Supplementary information:

2.2.2 TABLE: SELV measurement (under normal conditions)


Transformer Location Voltage (max.) (V) Voltage Limitation

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 89 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

V peak V d.c. Component

Supplementary information:

2.2.3 TABLE: SELV measurement (under fault conditions)


Location Voltage (max.) (V) Comments

Supplementary information:

2.4.2 TABLE: Limited current circuit measurement


Location Voltage Current Freq. Limit Comments
(V) (mA) (kHz) (mA)

Supplementary information:

2.5 TABLE: Limited power source measurement


Limits Measured Verdict
According to Table 2B/2C (normal condition)
current (in A)
apparent power (in VA)
According to Table 2B/2C (single fault condition)
current (in A)
apparent power (in VA)
Supplementary information:

2.6.3.4 TABLE: Resistance of earthing measurement


Location Resistance measured (m) Comments

Supplementary information: Tested current 32A.

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 90 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

<OR>
2.6.3.4 TABLE: Resistance of earthing measurement
Location Voltage drop (V) Comments

Supplementary information: Tested current 32A.

2.10.2 Table: Working voltage measurement


Location RMS voltage (V) Peak voltage (V) Comments

Supplementary information:

2.10.3 and TABLE: Clearance and creepage distance measurements


2.10.4
Clearance (cl) and creepage U peak U r.m.s. Required cl Required cr
distance (cr) at/of/between: (V) (V) cl (mm) (mm) cr (mm) (mm)

Functional:

Basic / supplementary:

Reinforced:

Supplementary information:

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 91 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

2.10.5 TABLE: Distance through insulation measurements


Distance through insulation (DTI) at/of: U peak U r.m.s. Test Required DTI
(V) (V) voltage DTI (mm)
(V) (mm)
Basic:

Supplementary:

Reinforced:

Supplementary information:

4.3.8 TABLE: Batteries


The tests of 4.3.8 are applicable only when appropriate battery
data is not available
Is it possible to install the battery in a reverse polarity position?
Non-rechargeable batteries Rechargeable batteries
Discharging Un- Charging Discharging Reversed charging
intentional
Meas. Manuf. charging Meas. Manuf. Meas. Manuf. Meas. Manuf.
current Specs. current Specs. current Specs. current Specs.
Max.
current
during
normal
condition
Max.
current
during
fault
condition

Test results: Verdict


- Chemical leaks
- Explosion of the battery
- Emission of flame or expulsion of molten metal
- Electric strength tests of equipment after completion of tests
Supplementary information:

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 92 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

4.5 TABLE: Temperature rise measurements


Temperatures were measured according cl. 1.4.5. Test in condition A and B at continuous normal operation
as for power input measurements of table 1.6.2 resulted in highest temperature values.
Temperatures are calculated according cl. 1.4.12.3 with regard to the maximum ambient operation
temperature of °C(Tma), as specified by the manufacturer.
test voltage(s) (V): A: V, Hz B: V, Hz
tamb1 (°C): A: B: tamb2 (°C): A: B:
Temperature of part/at: Measured Calculated Allowed
(measured with thermocouples) temperature rise at temperature at Tma Tmax (°C)
Tamb
A B A B
dT (K) dT (K) T (°C) T (°C)

Supplementary information:
Temperatures measured with winding resistance method: Not used
temperature T of winding: (V) R1 () R2 () T (C) allowed insulation
(winding resistance method) Tmax (C) class

Supplementary information:

4.5.5 TABLE: Ball pressure test of thermoplastic parts


Allowed impression diameter (mm) .................. :  2 mm 
Part Test temperature Impression diameter
(°C) (mm)

Supplementary information:

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 93 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

4.6.1, 4.6.2 Table: Enclosure opening measurements


Location Size (mm) Comments

Supplementary information:

4.7 Table: Resistance to fire


Part Manufacturer of Type of material Thickness Flammability Evidence
material (mm) class

Supplementary information:

5.1.6 TABLE: Touch current and protective conductor current measurement


Test voltage (V) ....................................... : AC ……..V, ………Hz 
Measurement location Polarity (normal) Polarity (reverse) Limit Comments
[mA] [mA] (mA)
(Terminal A connected to...) Switch: Switch: Switch: Switch:
ON OFF ON OFF
Earth terminal
("e" = open)
Operating Panel
("e" = close)

Supplementary information:

5.2 TABLE: Electric strength tests, impulse tests and voltage surge tests
Test voltage applied between: Voltage shape Test voltage Breakdown
(AC, DC, (V) Yes / No
impulse, surge)
Functional:

Basic / supplementary:

Reinforced:

Supplementary information:

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 94 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

5.3 TABLE: Fault condition tests


Ambient temperature (°C) ...................................... : 
Power source for EUT: Manufacturer, model/type, 
output rating ........................................................... :
Component Fault Supply Test Fuse # Fuse Observation
No. voltage time current
(V) (A)

Supplementary information:

C.2 TABLE: Insulation of transformers


Transformer part name ........................... : 
Manufacturer ........................................... : 
Type ........................................................ : 
Clearance (cl) and creepage U peak U r.m.s. Required cl Required cr
distance (cr) at/of/between: (V) (V) cl (mm) (mm) cr (mm) (mm)
Primary /input winding and
secondary/output winding
(internal)
Primary/input winding and core
(internal)
Secondary/output winding and
core (internal)
Primary/input part and
secondary/output part
(external)
Primary/input part and core
(external)
Primary/input part and
secondary/output winding
(external)
Secondary/output part and
core (external)
Secondary/output part and
primary/input winding
(external)

Description of design:
(a) Bobbin
Primary/input pins ..................................................... :
Secondary/output pins.............................................. :
Material (manufacturer, type, ratings) ...................... :
Thickness (mm) ........................................................ :

TRF No. BIS_IT/CR_IS13252_V1.2


[LAB LOGO]
Report No. xxxxxx IS 13252 (Part 1): 2010 + A1: 2013 + A2 : 2015 / Page 95 of 95
Dated: xxxxxx IEC 60950-1: 2005 + A1:2009 + A2 : 2013

(b) General
Please insert here a description of the transformer design describing:

Supplementary information:

TRF No. BIS_IT/CR_IS13252_V1.2