Method of Statement For Power Cables: Owner/Client Consultant Contractor
Method of Statement For Power Cables: Owner/Client Consultant Contractor
OWNER/CLIENT
CONSULTANT
CONTRACTOR
Signature:
Date:
Signature:
Designation:
Date:
1|Page
METHOD OF STATEMENT
FOR POWER CABLES
AURA ENGINEERING LLC
Contents
1.0 Purpose 03
2.0 Scope 03
5.0 Emergency 07
6.0 Records 07
2|Page
METHOD OF STATEMENT
FOR POWER CABLES
AURA ENGINEERING LLC
1.0 Purpose
This document describes in detail the method statement to be adopted for testing of 33kV and
11kV power cables.
2.0 Scope
The purpose of this method statement is to set procedures to ensure that the above
activity is performed in strict accordance with the OES requirements and norms.
3.0 Testing Procedures
As per the OES 2 section 3.13, Page no.7 the following tests shall be conducted at site.
1. Continuity Test.
2. Insulation Resistance Test.
3. High Voltage Test.
During the testing, team should be divided as two and placed at either end of the Terminated
Power cable. Appropriate Communication system shall be established between the team
members.
The Check list and measurements shall be entered in the format enclosed with this statement.
1. Continuity Test (Phase identification):
The purpose of the test is to ensure that continuity of the installed cable. This test will be
performed in presence of client/consultant after completing all cable installation works as per
drawing and specification.
Equipment/Instruments:
- Multi meter
Testing procedures:
i) The continuity of the cable checked for end to end through Armour and conductors.
ii) The remote end of conductor of the cable under test is connected to Armour.
iii) The phase of tested cable connected properly at remote end and check whether the
phase identification mark is properly done at both ends.
iv) Repeat the test for other phases and verify the correctness of phase marking at both
ends.
Schematic Layout:
3|Page
METHOD OF STATEMENT
FOR POWER CABLES
AURA ENGINEERING LLC
MULTIMETER
R Y B B Y R
4|Page
METHOD OF STATEMENT
FOR POWER CABLES
AURA ENGINEERING LLC
Schematic Layout:
IR TESTER (5kV)
+ -
R Y B B Y R
5|Page
METHOD OF STATEMENT
FOR POWER CABLES
AURA ENGINEERING LLC
Test Procedure:
1. Connect the HV test equipment to the cable under test through test termination.
2. The far end of the cable must be isolated from the other parts of the system.
3. Assemble the test equipment as per the instruments manual near termination of the cable
under test.
4. The area around the test set to cable under test should be barricaded.
5. Connect HV DC test set to cable under test through test bushing and ground all other
phases.
6. Verify and cross check all the instrument connection & ground connections are done
properly and tighten.
7. Switch on instrument and gradually increase test voltage to required level and monitoring
the charging current and note it.
8. After completion of test duration without breakdown, reduce voltage to zero and allowed
to discharge the cable by discharge rod.
9. Repeat the test procedure on other phases and record the readings in approved format
Schematic Layout:
DC HIPOT KIT
R Y B B Y R
6|Page
METHOD OF STATEMENT
FOR POWER CABLES
AURA ENGINEERING LLC
1. Objective:
To ensure the installation of equipment’s and laying of cables are to be completed in a safe
and controlled manner.
2. Scope of work:
Testing of cables.
3. Permit to Work system:
All activities are to be carried out in accordance with OES and DCRP Standards.
4. Tool box meeting:
Before starting the job, Site/Testing Engineer should conduct a toolbox meeting about
the scope of the work, hazards and control measures at work location.
5. PPE:
All the persons should wear minimum PPEs like Coveralls, Safety shoes and Helmets
etc.
Any others, depending on the requirement.
5.0 Emergency
In case of Emergency,
Stop the work.
Switch off the equipment’s/tools.
Alert the nearby workers to reach to the nearest assembly point
Do not to get panic and do not run.
Inform the site HSE officer and other key personnel from the emergency
contacts numbers displayed in the site.
Call emergency services if required.
HSE officer shall make head count and report.
6.0 Records
Quality Records (Check lists)
Inspection forms
SAT(Site acceptance test) reports
As built documents
7|Page