Norsok Standard E-001: Draft For Edition 5, March 2006
Norsok Standard E-001: Draft For Edition 5, March 2006
Norsok Standard E-001: Draft For Edition 5, March 2006
Electrical systems
This NORSOK standard is developed with broad petroleum industry participation by interested parties in the
Norwegian petroleum industry and is owned by the Norwegian petroleum industry represented by The Norwegian
Oil Industry Association (OLF), The Federation of Norwegian Industry, Norwegian Shipowners’ Association and
The Petroleum Safety Authority Norway. Please note that whilst every effort has been made to ensure the accuracy
of this NORSOK standard, neither OLF nor The Federation of Norwegian Industry or any of their members will
assume liability for any use thereof. Standards Norway is responsible for the administration and publication of this
NORSOK standard.
Standards Norway Telephone: + 47 67 83 86 00
Strandveien 18, P.O. Box 242 Fax: + 47 67 83 86 01
N-1326 Lysaker Email: [email protected]
NORWAY Website: www.standard.no/petroleum
Copyrights reserved
NORSOK standard E-001 Draft for Edition 5, March 2006
Foreword 3
Introduction 3
1 Scope 4
2 Normative and informative references 4
2.1 Normative references 4
2.2 Informative references 6
3 Terms, definitions and abbreviations 6
3.1 Terms and definitions 6
3.2 Abbreviations 6
4 General requirements and conditions (see IEC 61892-1) 7
4.1 General (see IEC 61892-1, 4.1) 7
4.2 Acceptance of substitutes or alternatives (see IEC 61892-1, 4.4) 7
4.3 Environmental conditions (see IEC 61892-1, 4.7) 7
4.4 Materials 7
4.5 Power supply system characteristics (see IEC 61892-1, 4.9) 7
4.6 Electrical apparatus for explosive gas atmospheres (see IEC 61892-1, 4.10) 8
4.7 Clearance and creepage distances (see IEC 61892-1, 4.12) 8
4.8 Insulation (see IEC 61892-1, 4.13) 8
4.9 Maintenance and inspection (see IEC 61892-1, 4.14) 8
4.10 Cable entries (see IEC IEC 61892-1, 4.15) 8
4.11 Location of electrical equipment in units (see IEC 61892-1, 4.17) 8
4.12 Spaces and compartments (see IEC 61892-1, 4.18) 9
4.13 Spare requirements for future modifications 9
4.14 Mechanical protection (see IEC 61892-1, 4.19) 9
4.15 Protection from heat, water, steam and oil (see IEC 61892-1, 4.20) 9
5 System design (see IEC 61892-2) 9
5.1 Sources of electrical power (see IEC 61892-2, Clause 4) 9
5.2 System earthing (see IEC 61892-2, Clause 5) 13
5.3 Distribution systems (see IEC 61892-2, Clause 6) 15
5.4 Distribution system requirements (see IEC 61892-2, Clause 7) 16
5.5 Diversity (demand) factors (see IEC 61892-2, Clause 8) 16
5.6 System study and calculations (see IEC 61892-2, Clause 9) 16
5.7 Protection (see IEC 61892-2, Clause 10) 18
5.8 Lighting (see IEC 61892,2, Clause 11) 20
5.9 Control and instrumentation (see IEC 61892-2, Clause 12) 21
5.10 Degrees of protection by enclosures (see IEC 61892-2, Clause 13) 22
6 Equipment (see IEC 61892-3) 22
6.1 General 22
6.2 Generators and motors (see IEC 61892-3, Clause 4) 22
6.3 Transformers for power and lighting (see IEC 61892-3, Clause 5) 25
6.4 Switchgear and control gear assemblies (see IEC 61892-3, Clause 6) 27
6.5 Electrical indicating instruments 29
6.6 Semiconductor convertors (see IEC 61892-3, Clause 7) 30
6.7 Secondary cells and batteries (UPS) (see IEC 61892-3, Clause 7 and Clause 8) 35
6.8 Luminaires (see IEC 61892-3, Clause 9) 36
6.9 Heating and cooking appliances (see IEC 61892-3, Clause 10) 36
6.10 Trace and surface heating (see IEC 61892-3, Clause 11) 36
6.11 Communication (see IEC 61892-3, Clause 12) 36
6.12 Underwater systems and appliances (see IEC 61892-3, Clause 13) 36
6.13 Control and instrumentation (see IEC 61892-3, Clause 14) 36
6.14 Accessories (see IEC 61892-3, Clause 15) 37
7 Cables (see IEC 61892-4) 37
8 Mobile units (see IEC 61892-5) 38
8.1 General 38
8.2 Limits of inclination of the unit (see IEC 61892-5, Clause 5) 38
9 Installation (see IEC 61892-6) 38
Foreword
The NORSOK standards are developed by the Norwegian petroleum industry to ensure adequate safety,
value adding and cost effectiveness for petroleum industry developments and operations. Furthermore,
NORSOK standards are, as far as possible, intended to replace oil company specifications and serve as
references in the authorities’ regulations.
The NORSOK standards are normally based on recognised international standards, adding the provisions
deemed necessary to fill the broad needs of the Norwegian petroleum industry. Where relevant, NORSOK
standards will be used to provide the Norwegian industry input to the international standardisation process.
Subject to development and publication of international standards, the relevant NORSOK standard will be
withdrawn.
The NORSOK standards are developed according to the consensus principle generally applicable for most
standards work and according to established procedures defined in NORSOK A-001.
The NORSOK standards are prepared and published with support by The Norwegian Oil Industry Association
(OLF), The Federation of Norwegian Industry, Norwegian Shipowners’ Association and The Petroleum Safety
Authority Norway.
Annex A is normative.
Introduction
This NORSOK standard is based on equipment and practices which are in current use, but it is not intended
in any way to impede development of new or improved techniques.
1 Scope
This NORSOK standard contains provisions for electrical installations at all voltages and is intended to enable
safety in the design of electrical systems, selection, and use of electrical equipment for generation, storage,
distribution and utilization of electrical energy for all purposes in offshore units which are being used for the
purpose of exploration or exploitation of petroleum resources.
This NORSOK standard does not apply for the electrical installations in rooms used for medical purposes or
in tankers.
Each clause in this NORSOK standard refers to the equivalent clause in the IEC 61892 series of standards.
This NORSOK standard applies to all installations. The installation may be permanent, temporary,
transportable or hand-held, to AC installations up to and including 35 000 V and DC installations up to and
including 1 500 V.
NOTE This NORSOK standard is applicable for the voltages stated above, even if a different voltage limit may be given in some of the
parts in the IEC 61892 series of standards. It is expected that the voltage levels in the IEC 61892 series of standards will be corrected
as part of the maintenance cycle of this IEC standard.
3.1.2
should
verbal form used to indicate that among several possibilities one is recommended as particularly suitable,
without mentioning or excluding others, or that a certain course of action is preferred but not necessarily
required
3.1.3
may
verbal form used to indicate a course of action permissible within the limits of this NORSOK standard
3.1.4
can
verbal form used for statements of possibility and capability, whether material, physical or casual
3.2 Abbreviations
AC alternating current
AF forced air cooled
AN naturally air cooled
ASDS adjustable speed drive system
ATEX Atmosphere EXplosible
AVR automatic voltage regulator
BDM basic drive module
BSL Bestemmelse for sivil luftfart
CENELEC European Committee for Electrotechnical Standardization
DC direct current
DOL direct on line
Du/Dt high frequency harmonic filter
EMC electromagnetic compatibility
ESD emergency shut down
EU European Union
Ex explosion proof
FCR field current regulator
HV high voltage, U≥1kV
IE Instrument earth
IEC International Electrotechnical Commision
IFEA Industriens Forening for Elektroteknikk og Automatisering
I/O input/output
IP international protection
IS intrinsically safe
ISO International Organization for Standardization
IT isolated power system
LCI load commutated inverter
LV low voltage, U<1kV
MCC motor control centre
MCT multi cable transit
NEK Norsk Elektroteknisk Komite
PCS process control system
• Directive 89/336/EC;
• Directive 94/9/EC;
• Directive 98/37/EC;
• Directive 73/23/EC.
NOTE The use of this NORSOK standard will normally ensure compliance with the Ptil Regulations.
In the event of other solutions being used than those recommended in the comments to a provision contained
in the Ptil regulations, the party responsible shall be able to provide documentary proof that the solution
chosen fulfils the requirements of the regulations. To obtain the best possible understanding of the level that
it is desired to achieve through the regulations, the regulations and the comments need to be viewed
collectively. Norms that are recommended in the comments will be central factors in interpreting the individual
requirements of regulations and when establishing the level for health, working environment and safety.
Combinations of parts of norms should be avoided, unless the party responsible is able to document that an
equivalent level in relation to health, working environment and safety is achieved.
4.4 Materials
All equipment and materials shall have low halogen content.
Equipment enclosures located outdoor, in naturally ventilated areas and wash down areas, shall be made of
proven sea water resistant material or protected by a coating system according to NORSOK M-501.,
Electrical/electronic equipment in panels shall be protected against hydraulic leakage.
To ensure EMC (electromagnetic compatibility) between equipment it is important that the emission from one
component do not exceed the susceptibility level of other equipment. For complex installations, an EMC
analysis should be performed to detect if additional measures (shielding/filtering) is required to ensure that
EMC is achieved between all equipment.
4.6 Electrical apparatus for explosive gas atmospheres (see IEC 61892-1, 4.10)
Electrical equipment required to be suitable for installation in hazardous areas shall comply with the
requirements of the Norwegian ”Forskrift om utstyr og sikkerhetssystem til bruk i eksplosjonsfarlig område”.
Doors to high voltage rooms shall open out from the room. Hinged doors shall be provided with “panic
opening device” which can be opened without using the hands.
In order to avoid installation of major electrical equipment in hazardous areas or in exposed environments, all
major electrical equipment shall be installed inside equipment rooms with a controlled atmosphere.
All power supply and control equipment for foghorn and navigational lights shall be located indoors at a
location suitable for maintenance activities. The integrated power supplies shall be galvanically isolated from
the mains.
Location of electrical equipment shall be selected to avoid interference with escape routings, walkways, other
equipment, pipes etc. and obstruction against activities related to transport and lifting operations.
Equipment should not be supported on pipe work, handrails, access ladders or cable ladders. Lighting
fixtures may, however, be mounted underneath cable ladders or as integrated part of handrail support
arrangement.
Equipment such as public address flashing lights, loudspeakers, junction boxes, splitters and tap-off, may be
located on the support for cable ladders and trays or on the side rail of the cable ladders.
Equipment shall not be mounted on blastwalls/explosion relieves. Equipment can, however, be installed on
the support frames for the blast walls if the integrity of the blast wall is not interfered.
Equipment located in areas which do not allow for maintenance accessibility as required, should as shown on
typical drawing be installed such that the equipment can be rotated, raised or lowered into areas where
maintenance can take place without the need for scaffolding.
NOTE Regarding separation of main and emergency power and fire divisions for rooms containing electrical equipment, reference is
made to the Facilities Regulations, sections 29 and 37.
• relevant area interface cabinets, junction boxes, cabling etc. to meet a 10 % increase,
• main cable ladders to meet a 10 % increase.
4.15 Protection from heat, water, steam and oil (see IEC 61892-1, 4.20)
Full scale testing of deluge system may take place. Selection and installation of equipment should be such
that adverse effects to the equipment due to testing is minimised.
Equipment located in areas where deluge testing will take place shall have degree of protection at least IP 56.
The main power supply may be arranged locally, with subsea cables from another offshore unit, from shore
or with a combination of the alternatives.
When local power generation is provided, the generators shall be grouped in a central power plant. The unit
rating and number of generating sets shall be adapted to the load profile of the systems served over the
entire lifetime of the unit.
The main power generator auxiliary consumers shall be supplied from both the main and the emergency
system. If an essential source of power is available, these consumers shall be supplied from the main and
the essential system. A change over system shall be provided.
The configuration of the main power distribution system shall depend on the regularity requirements of the
production process.
IEC 61892-2 requires at least two main generators. If one main generator can supply the total maximum load
at the plant, and the regularity requirements do not require “2 x 100 %”, the second generator can be an
essential generator.
See IEC 61892-2, 4.2.2
The regulations do not allow connecting other consumers than emergency consumers to the emergency
switchboard. Therefore an essential power system with essential generator(s) should be evaluated. Criteria
for essential power system should be sufficient power for utilities necessary for accommodation (normal
conditions of habitability), and power for turnaround periods. See additional requirement to 4.3.6.
The emergency power supply systems shall comprise a combination of UPS, and, if necessary, a diesel
engine driven generator. Alternatively to diesel engine driven generator, power cable from another
independent plant may be considered.
The emergency power supply system shall be independent of the main supply systems. Main and emergency
distribution equipment shall be located in separate rooms. Sub distribution boards may be located in the
same room as main supply systems.
If the emergency power is supplied from a diesel driven emergency generator it shall be a capable of
supplying the consumers with emergency power for at least 18 h.
UPSs shall be provided for emergency services and non-emergency services requiring continuous AC or DC
power supply in case of main power failure blackout or electrical disturbances. Equipment sensitive to
electrical disturbances (e.g. voltage transients and harmonic distortion should be supplied from UPSs.
Reference is also made to NORSOK S-001, EN ISO 13702. Annex C.1, and IMO 1989 MODU Code section
5.3.10.
Each UPS should be provided with facilities for battery capacity test including logging of test values. Inverter
feeding battery energy back to the grid is preferred.
Analysis shall be carried out to demonstrate the availability and reliability of the UPS.
The UPS system shall at least consist of two independent and redundant units to provide two independent
power sources to critical consumers such as critical control systems and control voltages listed above. Such
consumers shall have two power supplies (duty-stand by) with automatic power transfer change over.
Redundant UPS supply shall be fed from fully independent UPS units without any common mode failure
elements. This means that redundant units (e.g. UPS and battery) should be located in separate rooms.
Each UPS main distribution board section shall be equipped with earth fault detection and common alarm.
The earthfault detection system shall as a minimum be of a type that enables manual fault finding of each
outgoing circuit. Space shall be provided for fault finding of the outgoing circuits with a portable apparatus.
Selection and coordination of protection devices shall ensure selectivity in all modes of operations.
Emergency batteries shall have a capacity to supply emergency power for a minimum period of 30 min, see
ISO 13702, Table C.1.
Note ISO 13702, Table C.1 is not applicable for emergency escape lights, see. 5.8.2.
The emergency switchboard shall be designed for disconnecting of power supply for a short period, without
affecting production or essential function, to be able to test automatic starting arrangement of emergency
generator.
The requirement for starting arrangement of essential generator is the same as for emergency generator
described in 4.9, except those concerning locations.
Other detailed design requirement for essential power system will be the same as for the main power system.
5.1.4 Additional requirements for periodically unattended machinery spaces (see IEC 61892-2, 4.4)
See IEC 61892-2, 4.4.1
All production platforms shall be designed for normally unattended machinery spaces.
All testing, manual operation, starting, transfer of power and stopping of emergency generator, and testing
shall be possible to be performed by one operator at one location (emergency generator control panel).
The emergency switchboard and the emergency source of power (emergency generator) can be located in
separated rooms close to each other.
Emergency sub switchboards should not be located in the same room as main power switchboards.
Emergency main distribution board for lighting and small power shall be located in an emergency switchboard
room or similar. There is no such restriction concerning sub emergency distribution panels.
5.1.7 Additional requirement for electrical emergency power system (see IEC 61892-2, 4.8)
See IEC 61892-2, 4.8.1
The prime mover for emergency generators can be stopped automatically in the event of
NOTE Item a) and c) do not apply to emergency generator(s) supplying fire pump(s).
In test or manual mode, the prime mover for the emergency generator shall be equipped with automatic stop
functions as a normal stand-by generator.
In cases where fire pumps are fed from the emergency power system, the driver of the emergency generator
is regarded as prime mover for the fire pumps and thus will have to fulfil the requirements for firewater pumps
prime mover.
5.1.8 Starting arrangement for emergency generators (see IEC 61892-2, 4.9)
See IEC 61892-2, 4.9.1
The generator(s) shall start automatically and operate directly on the emergency bus bar in case of failure of
main system. The normal starting time until the emergency switchboard is energized shall not exceed 45 s.
The emergency generator prime-mover shall have temperature controlled jacket water heating.
This should be considered where a significant number of power sources could be connected to the same
system voltage, see 5.5.1.
5.2.2 Neutral earthing for system up to and including 1000V (see IEC 61892-2, 5.4)
See IEC 61892-2, 5.4.1
The system earthing methods for the different low voltage levels are shown in Table 2.
The neutral shall be earthed through a resistance with numerical value equal to or somewhat less than 1/3 of
the capacitive reactance between phase and earth.
The resistive current shall for all voltage levels be limited to the maximum values given in Table 3.
5.2.3 Neutral earthing for system up above 1000V (see IEC 61892-2, 5.5)
See IEC 61892-2, 5.5.1
The system earthing methods for the different voltage levels are shown in Table 3. For high voltage levels,
the system earthing shall be performed as “High resistance earthed neutral”.
The neutral shall be earthed through a resistance with numerical value equal to or somewhat less than 1/3 of
the capacitive reactance between phase and earth.
The resistive current shall for all voltage levels be limited to the maximum values given in Table 3.
5.3.1 Direct current (DC) distribution systems (see IEC 61892-2, 6.1)
The following voltage levels shall be used:
• UPS 48V DC (shall only be used as distribution voltage for telecommunication systems)
• UPS 60V DC (shall only be used as distribution voltage for telecommunication systems)
Local isolated system (e.g. separate control voltage in a cabinet) does not require insulation monitoring
devices, provided the circulation current does not exceed 30 mA under the most unfavourable conditions.
5.3.2 Alternating current (AC) distribution systems (see IEC 61892-2, 6.2)
The following voltage levels and frequency shall be used:
11 kV, 3-phase Generation and distribution voltage. Should be used when total installed generator
capacity exceeds 20 MW. Should be used for motors from 400 kW and above for DOL
starting.
6,6 kV, 3-phase Generation and distribution voltage. Should be used when total installed generator
capacity is between 4 MW to 20 MW. Should be used for motors from 400 kW and above
for DOL starting.
690 V, 3-phase Generation and distribution voltage. Should be used when total installed generator
capacity is below 4MW. Should be used for DOL starting of motors, below 400kW and as
primary voltage for converters for drilling motors.
400/230 V TN-S system shall be used as distribution voltage for 3-phase + N lighting and small
power, and for heaters below 3 kW, including heat tracing. For living quarter, kitchen and
laundry 400 V 3-phase may be used as supply voltage to consumers. The system shall be
symmetrically loaded.
UPS 230 V IT system shall be used as distribution voltages for instrumentation, control, tele-
communication and safety systems.
UPS dedicated for a special purpose can be solidly earthed.
Frequency 50 Hz.
Where the control circuits require a DC voltage, two independent rectifiers (2 x 100 %) with separate supplies
shall supply the circuits in parallel. Each rectifier shall be equipped with fault alarm.
NOTE If the electrical load data are well defined in the early phases, lower factors may be used.
The maximum symmetrical root mean square (rms) value of the sub transient fault current should not exceed
the following values:
The relay coordination study shall be carried out according to the requirements of the "Guidelines for the
documentation of selectivity (discrimination) in AC systems (IFEA)." The establishing relay setting tables and
logarithms current versus time curves shall be a part of the study report.
5.6.5 Calculations of harmonic currents and voltages (see IEC 61892-2, 9.7)
The detailed harmonic voltage acceptance limits shall correspond to IEC 61000-2-4, class 2, on a bus bar of
any voltage.
• nominal current,
• voltage drop, stationary and transient, according to Table 4,
• short circuit withstands capability, mechanical and thermal.
Type of cable to be used for which purpose and area shall be described, i.e. mud/oil resistant, fire resistant
etc.
The voltage drop in cables should not exceed the following values measured from the last distribution board
with regulating facilities, i.e. supplied by a transformer with tappings or a generator.
Total voltage drop at motor terminals during start shall be maximum 20 % (typical power factor 0,2)
Relays with data communication features should be employed in large, centrally controlled systems.
• frequency relay,
Input to load shedding system.
• arc detection relay.
An arc detection system shall be installed either alone or in combination with a current relay. Detection
shall sectionalize the bus bar and trip incomer(s). This does not apply for single-phase air or gas (SF6
=sulphur hexachlorid) insulated switchboards.
690 V sub distribution feeder shall have a common alarm to PDCS per feeder.
Each 230 V main or sub distribution boards shall at least have common alarm to PDCS for each board
indicating tripped circuits. Common alarm for emergency lightings shall be separated as described in IEC
61892-2, 11.4. Heat tracing circuits should also have separate common alarms to PDCS.
5.8.1 General
The following clauses govern the design and functional requirements of the general lighting system.
Other lighting systems (e.g. navigation aids, helideck lighting, marking systems and aviation obstruction
lighting) shall be designed according to the requirements of statutory regulations.
Lighting calculations shall be performed, and a maintenance factor shall be applied, reflecting the
environmental conditions and maintenance intervals.
It should be noted that lighting equipment with electronic starter may cause interference with radio
communication. A study shall be performed to investigate the extent of the problem and propose solutions.
Local sub distribution boards shall be provided for power distribution to the lighting system within each
functional area.
The general lighting system shall be designed with fluorescent luminaries. The fluorescent tubes shall be of
the two pins, slim long life type.
Floodlights, with high pressure sodium lamp, shall be used for general lighting of open deck areas, inside big
open modules where an acceptable mounting height is achievable, on cranes, flare booms, sea surface
below boat and raft stations.
Floodlights and control gear for flood lights shall be mounted in locations where they can be easily maintained
and mounted in groups for a particular area.
Floodlights shall be provided with an extra safeguarding against falling down if the screwed connections
loosen.
Incandescent luminaries shall not be used. For comfort lighting within the living quarter and office areas, low
energy lighting sources like compact/mini tubes should be used.
It shall be possible to vary the lighting level within control rooms and common recreation areas.
Battery operated hand lamps with battery chargers shall be provided. The hand lamps shall be certified for
use in zone 1.
Emergency escape lighting shall be supplied from a battery source, and sited according to EN 1838. Other
emergency luminaries (e.g. floodlights) shall be supplied from a UPS system with a battery back up for 60
min.
The battery charger for battery operated hand lamps shall be fed from the emergency distribution system.
For emergency light fittings with integral batteries, the batteries shall be located such that they are not subject
to excessive heating from the light fitting. It should be possible to replace the batteries without dismantling the
light fitting.
Electrically powered lighting or photo luminescent indicators (low level lighting) shall be placed at points of the
escape to readily identify all escape routes when the normal emergency lights are less efficient due to smoke.
The type to be used depends upon the type of area. These luminaries shall meet zone 1 requirements.
For emergency distribution boards, Ex-certification shall be evaluated in each case depending on the
location.
5.9.1 Power distribution control system (PDCS) (see IEC 61892-2, 12.13)
A PDCS shall be established and include as a minimum the following functions:
• VDU mimic of the electrical network with circuit breaker and isolator status;
• control of all main breakers in the electrical network;
• status and alarm monitoring of all main breakers;
• alarm from all relevant sub distribution boards and UPSs;
• event recording of all alarms and status changes.
The PDCS shall be an independent functional unit with interface to the PCS, either as a part of the SAS
hardware or as an independent unit with data communication to the PCS.
Alarm and control signals shall be collected from each switchboard to the PDCS by use of local control units,
distributed I/O units or intelligent units with communication.
Data communication with standard protocols and electrical interface should be used.
The event recording function shall enable printing of all events sequentially with the proper identification, time
and date tagging. The time resolution for the main distribution system shall be maximum 20 ms while I/O
units for motors and sub-systems shall be maximum 1s. Time tagging shall preferably take place on the
lowest level (I/O-unit). All time tagging shall be time synchronised with the SAS or corresponding time
reference.
The total response time from operation of main breaker from VDU to reached status change, shall not
exceed 3 s, see NORSOK I-002 , Annex 2.
Where implemented, the load shedding system shall be an independent software module within the PDCS.
Care shall be taken to ensure that the response time is sufficient to enable the load shedding system to
perform its function and maintain a stable electrical system.
• For outdoor, in naturally ventilated areas and wash down areas: IP 56 (see NOTE)
• Dry indoor areas: IP 20
• Other areas: IP 44
Above represents minimum requirements. It should be noted that regulations may contain more stringent
requirements and shall be consulted.
NOTE IP 56 is required where equipment is placed in open deck exposed to water from heavy seas or in areas exposed to water
projected jets, elsewhere IP 55 is required.
6.1 General
The following definition of major electrical equipment for permanent installation apply:
All electrical MCC and distribution boards/panels, all 3 phase motor starters and feeders including contactors
and breakers, all 3 phase transformers, battery chargers, and frequency converters. In addition control panels
containing PLC, transformers fuses etc. should be avoided in hazardous areas or in exposed environments.
The terminals and the earthed frame of high voltage motors shall be provided with contact bolts for
application of mobile earthing apparatus.
High voltage motors shall have preformed and vacuum impregnated windings and shall be star connected.
TEFC motors may be used on open deck provided embedded temperature detectors for trip upon blocking or
destroying of fan blades protect the motor.
Control stations shall be standardized according to IEC 60073 with respect to symbols, colours and lettering
on pushbuttons, indication lights, and selector switches, etc. throughout the unit.
6.2.1.4 Testing
Tests shall be performed according to IEC 60034 (all parts).
All HV motors shall be routine tested according to Table 11. These routine tests shall be considered to be the
minimum test requirements for HV motors and shall, if not otherwise agreed, be performed by the motor
supplier. If other tests are required, additional tests shall be specified in the motor data sheet.
6.2.2.1 General
The generator shall be designed for operation in parallel with units of equal and unequal ratings.
The stator winding shall be star connected and star point and main terminals brought out to terminal boxes
on the outside of the generator hood.
The generator should preferably be delivered with a neutral resistor as an integral part of the generator. If the
neutral resistor by practical reasons not can be attached to the generator, it will still be the generator
supplier’s responsibility to supply the neutral resistor. The resistor shall be rated in accordance with the data
sheet.
Minimum two temperature resistance sensors shall be embedded in each phase of the stator winding.
The exciter shall be of the brush less type and directly connected to the main rotor winding. The exciter and
rectifier assembly shall be rated minimum 10 % above the nominal value required when the generator is
running at rated load and power factor.
Facilities shall be provided for continuous monitoring of exciter and field winding insulation resistance.
Facilities shall be provided for monitoring of the rectifier diodes. Alarms shall be given for failed shorted
diodes.
The electronic AVR shall have adequate protection against voltage surges, shall be free of voltage drifting, be
insensitive to temperature changes, vibration and shall maintain regulation accuracy for frequency variations
of +/-10 % of rated value.
The voltage regulation system shall consist of a double AVR system. It shall be possible to manual regulate
the field by a manual FCR.
One AVR shall be the main while the other AVR shall be in “hot” stand-by
This shall ensure voltage stability upon transfer between the main AVR and stand-by AVR.
Automatic transfer from main to stand-by channel shall take place for faults influencing the regulation.
Each bearing shall be provided with temperature detectors (one spare) for alarm and shutdown purposes.
The lubrication oil system shall operate during spin-down of the generator in a black out situation, preferably
by gravity fed lube oil supply.
The terminals and the earthed frame of high voltage generators shall be provided with contact bolts for
application of mobile earthing apparatus.
6.2.2.2 Testing
Tests shall be performed according to IEC 60034.
All generators shall be routine tested according to Table 12. These routine tests shall be considered to be the
minimum test requirements for generators and shall, if not otherwise agreed, be performed by the generator
supplier. If other tests are required, additional tests shall be specified in the generator data sheet.
6.3 Transformers for power and lighting (see IEC 61892-3, Clause 5)
High voltage power transformers of rated nominal power up to and including 2500 kVA (AN) shall be
prepared for forced cooling rated 140 % (AF). For high voltage power transformers with rated nominal power
above 2 500 kVA (AN) the AF rating shall be minimum 125 %, if not otherwise stated in the power
transformer data sheet. Increased AF rating will have significant impact on the sound level.
All HV transformers shall have a rated lightning impulse insulation level according to List 2, if not other lower
requirement (List 1) is stated in the power transformer data sheet.
High voltage power transformers should be of the cast resin dry type.
Low voltage (LV/LV) transformers may be dry types without cast resin insulation.
Insulation class shall be minimum F.
Reference is made to IEC 60726.
Neutral resistor may be an integrated part of the transformer, including current transformer.
All transformers shall for each project be subjected to the tests in Table 13.
These tests shall be considered to be the minimum test requirements for transformers and shall, if not
otherwise agreed, be performed by the transformer supplier. If other tests are required, additional tests shall
be specified in the power transformer data sheet.
6.4 Switchgear and control gear assemblies (see IEC 61892-3, Clause 6)
6.4.1.1 General
Spare space of approximately 30 % at the time of delivery of the equipment should be provided. Spare
panels and compartments shall facilitate future installation without shutting down the switchboard.
Status for main circuit breakers shall be shown on the breaker front (on, off, trip).
Starters shall be designed for direct on-line starting of type AC3 according to IEC 60947-4-1.
The control voltage for motor starters should be supplied from a common control voltage transformer for
each motor starter cubicle or each bus bar section. Protection shall be provided individually for each motor
starter circuit.
The control voltage shall be supplied from an UPS at 230 V AC. For air circuit breakers and other critical
consumers other than motor starters, see 5.1.3.
The starters shall have a test possibility when disconnected from the main circuit.
Starters should be grouped into motor control centres located in switchboard rooms, free standing motor
starters in outdoor location is not acceptable. Combined switchboards including switchgear and MCC are
acceptable.
Pad locking facilities shall be provided for all incoming and outgoing circuits. This shall apply for all voltage
levels including 230V.
Internal segregation shall for 690 V switchgears be according to IEC 60439-1, form 4b.
Internal segregation shall for 690 V MCC be according to IEC 60439-1, form 3b.
Air circuit breakers and motor starters shall be of the withdrawable type.
All low voltage switchboards shall for each project be subjected to the tests in Table 14. These tests shall be
considered to be the minimum test requirements for low voltage switchboards and shall, if not otherwise
agreed, be performed by the switchboard supplier. If other tests are required, additional tests shall be
specified in the low voltage switchboard data sheet.
6.4.2.1 General
The switchboard and cubicles shall be metal enclosed according to IEC 62271-200. Separate low voltage
compartments shall be located in the front of the switchboard.
All circuit breakers and contactors shall be of either vacuum or SF6 type.
The circuit breakers and contactors shall be equipped with facilities for testing when disconnected from the
mains. The control voltage shall be supplied from an UPS of 230 V AC.
For air insulated switchgears the high voltage compartments should be provided with pressure relief.
Surge arrestors or other protection devices shall be used where switching voltage escalation may exceed the
insulation level. A switching/equipment insulation study should be performed in order to specify the correct
equipment insulation levels and if additional protections are required. The study shall identify where the
protection equipment shall be located, if any. Insulation levels and the requirements for surge arrestors or
other protection device shall be given in the applicable equipment data sheet.
The switchgear room shall allow for extension of the switchgear in at least one end.
All circuit breakers and contactors shall be withdrawable for air insulated switchboards. Circuit breakers,
contactors, and earthing switches shall be provided with padlocking facilities.
Mechanical interlock between circuit breaker, contactor, and earthing switch in the same cubicle shall be
provided. Where mechanical interlock is not possible (i.e. closing of earth switch on live main bus bar), other
interlock system shall be provided.
Routine tests shall be performed according to IEC 62271-200. High voltage switchboards shall be type tested
according to IEC 62271-200, annex A, for arcing due to internal faults. The duration of the arc shall be 1s.
6.5.1 General
Panel instruments should be of class 1.5.
Voltage transformers shall have 110 V secondary voltage. Shunts used on DC current metering shall be
60 mV.
Where synchronizing can take place, the following instruments shall be provided for manual synchronizing:
• synchronoscope;
• double voltmeter;
• double frequency meter;
• check synchronizing relay.
6.5.2 Requirement
Electrical indicating instruments shall be according to Table 16.
6.6.1.1 General
These additional requirements are valid for adjustable speed AC motor drives with a motor nominal power
larger than 100kW.
Generally the PDS shall be designed, manufactured and tested by the same supplier.
The different parts of the PDS might be installed in locations separated from each other. The supplier shall
specify the maximum acceptable cable lengths between the different parts.
Selection of cables, earthing of equipment, and other installation requirements shall be subjected to BDM
supplier’s installation manuals.
Transients
The PDS shall be able to operate with voltage and frequency transients that occur in maritime installations.
Reference is made to transient limits as given in IEC 61892-1.
Harmonic distortion
Generally a harmonic distortion analysis is required when installing a PDS. On the PCC (point of coupling,
normally primary side of the converter transformer) the voltage THD should not exceed limits as given in this
NORSOK standard, 4.5 and 5.6.5.
The harmonic distortion analysis at the PCC should normally be done by the PDS supplier. This analysis
should focus on the worst case scenario. It shall be based on the minimum short circuit power at the PCC
when the PDS is in operation, and the maximum required motor shaft power. This information should
normally be given by the purchaser.
The PDS/BDM supplier shall advice the critical speeds in his bid and if any inside the operating range he shall
document how to avoid these critical speeds.
Pulsating torque
For drives equal and larger than 2 MW nominal motor rating the PDS/BDM supplier shall give information
about any pulsating torque in the low speed range as well as in the operating speed range. For LCI drives,
the inter-harmonic frequencies supplied to the grid shall also be given.
If the PDS shall be used for special duties (e.g. intermittent duty, short time overload, etc.) the special duty
class shall be given in the ASDS Data Sheets. If no duty class information is given then Duty Class 1
(continuous full load) shall be applied. Duty class definitions are given in IEC 60146-1-1.
The equipments shall be able to operate under the movements (roll and pitch) and vibrations that are normal
in a floating vessel. If not other requirements are given in the data sheets, the equipment shall meet the
ambient requirements as given in IEC 61892-1.
Motor
The insulation shall be class F. The temperature rise at specified load in the entire speed range should be
limited to class B. Higher insulation classes may be agreed upon.
The supplier is free to choose motor voltage, frequency and pole pairs unless otherwise stated in the data
sheet. The required speed range is stated in the data sheet.
Unless otherwise stated in the data sheet the motor neutral shall be isolated.
The motor shall be designed for operation with the applicable BDM and take into account all additional losses
and the actual load.
All HV motors shall be dynamically balanced according to the limits in IEC 60034-14, Vibration Grade B.
For LCI drives with HV synchronous motors, the motor windings shall consist of two three-phase systems
o
with 30 electrical phase shift in order to minimise torque pulsations. The windings shall be star connected
and isolated. The exciter shall be of the brushless type. The rotor winding and the diodes shall withstand any
symmetrical or asymmetrical fault occurring in the stator windings.
The BDM shall provide proper protection for the PDS against overload, over-voltage, under-voltage and short
circuit, asymmetric currents as well as inability to start and over-speed.
If a by-pass switch is required, this shall be stated in the ASDS converter data sheet. If required, the by-pass
shall be manually operated and provided with mechanical interlocks to prevent paralleling of the PDS and the
by-pass power supply.
Serial link for communication to platform control system (e.g. SAS, PCS, etc.) shall be included unless other
requirement is given in the data sheet. A separate hard wired 24 V DC interface for external emergency shut
down (PSD/ESD) shall in addition be provided.
The control system shall be able to control the drive by speed ramp, torque or power. The normal control
mode is indicated on the data sheet.
If the reference signal is lost the drive shall either decelerate to minimum speed/torque/power or down to
standstill as stated in the data sheet.
As a minimum the following potential-free output signals shall be provided and wired to terminals:
• Ready to start
• Running
• Stop - when stopped by process system or PDS protection devices
• Stop - when stopped by emergency push-button
During normal operation after decelerating the motor to standstill, it shall be possible to de-energise the motor
by blocking gate/base signals to the power semiconductors, leaving line transformer and converter input
circuit energised.
When automatic restart is specified in the data sheet this shall also be possible with a rotating motor. This is
called "flying restart".
Measures shall be taken that HV cubicles/compartments can be completely de-energised, isolated and
earthed. Earth bolts accessible from the front, for portable earthing apparatus, shall be provided in HV
converters.
In cubicles, which can be accessible during normal operation (open front door), all components with
potentials above 50 V shall have a degree of protection of at least IP20.
If special tools and/or software are required for operation or maintenance it shall be supplied by the BDM
supplier.
Du/dt filter may be required when voltage source converter technology is used, i.e. insulated gate bipolar
transistor technology or integrated gate commutated thyristor technology. It is within the responsibility of the
PDS supplier to include and design a du/dt filter, out-put reactor, select the correct motor winding insulation,
and if specified, to have the PDS system EEx certified.
Feeding section
Converter transformers (if any) shall normally be of the dry cast resin type. These transformers shall meet the
requirements in IEC 60146-1-3 and IEC 60726.
If no converter transformer is to be used the BDM supplier shall evaluate whether an input reactor is
necessary or advisable in order to fulfil proper BDM function and acceptable level of supply current distortion.
If required, this reactor shall be part of the BDM supplier's scope of supply.
The selection of the converter transformer/reactor reactance shall be the responsibility of the PDS supplier. It
shall be ensured a reactance adequate for proper function and short circuit protection of the BDM. The short
circuit level on the primary side of the converter transformer/reactor shall be informed by the purchaser.
Converter transformers shall be equipped with temperature sensors in secondary windings and all legs of iron
core.
Low voltage/low voltage transformer windings are accepted as dry type without cast resin insulation. The
transformer shall meet the requirements in IEC 60726 and IEC 60146-1-3.
6.6.1.5 Testing
Transformer test
ASDS transformers shall be subjected to the same tests requirements as distribution transformers, see 6.2.2.
If additional tests are required, these tests shall be specified in the power transformer for ASDS data sheet.
Motor test
ASDS motors shall be subjected to the same tests requirements as other motors, see 6.1.1.4. If additional
tests are required, these tests shall be specified in the motor for ASDS data sheet.
A PDS system test shall be carried out for verification of all components that are part of the PDS scope of
supply are functioning in accordance to specifications.
Test Field
Project Scope
of Supply
~ ~
Power
~ Flow ~
The PDS supplier is responsible for such test and shall in the bid attach a single line diagram showing how
the PSD supplier intends to carry out this test. PDS supplier shall attach a PDS system test plan in the bid..
The measurements carried out during the PDS system test are for determination and proof of particular PDS
operational data, especially of the guaranteed values. As a minimum, the PDS system test should contain
topics as listed in Table 18.
1 Visual Inspection and check of wiring and dimensions according to project drawings.
2 Insulation test.
3 Functional test including all auxiliaries and test of remote signals.
4 Checking co-ordination of protective devices.
Load characteristic test.
5
Efficiency
6
Power factor.
7
Line-side current distortion content.
8
Motor vibration.
9
Torque pulsation.
10
11 Dynamic performance test.
Audible noise.
12
13 Shaft current/bearing insulation.
14 Overcurrent capability.
String test
For drives, where string tests including driven equipment (e.g. compressor, pump, thrusters, etc) have been
specified, the string test will normally replace the PDS system test. However, the PDS system properties
should also be proven during a string test. String test plan has to be discussed and agreed upon for each
project.
6.7 Secondary cells and batteries (UPS) (see IEC 61892-3, Clause 7 and Clause 8)
6.7.1 General
The UPS unit shall meet the requirement in EN 50091-1 and EN 50091-2.
The UPS unit shall have internal fault supervision facilities to verify operational properties for the system. The
fault supervision shall including battery discharge test without closing down the supply to the consumers. The
UPS shall have a separate battery discharge alarm.
To obtain isolation from all power sources at ESD, all battery breakers shall have a remote trip function.
Reference is made to NORSOK S-001, Figure 9.1. Means shall be provided to enable closure of the battery
breaker after a trip without utilising external auxiliary voltage or temporary links.
UPS batteries should be located in separate battery rooms if the battery capacity exceed 20 kW (battery
AH*UN). Batteries with capacities between 5 kW and 20 kW may be located in boxes or panels with separate
ventilation.
All UPS shall be equipped with a manual by-pass circuit for maintenance purpose and a static switch for
automatic and uninterrupted transfer of load from the inverter to the by-pass supply. Retransfer of the load
from the manual bypass switch to the inverter shall be manually operated.
The UPS unit should include interlocks to prevent black-outs caused by operational mistakes, i.e. safe
operational command software.
The UPS unit should have a mimic diagram on front showing operational modes and
voltage/amps/frequency.
6.7.2 Testing
UPS and batteries shall for each project be subjected to the standard test in Table 19. These tests shall be
considered to be the minimum test requirements for UPS and batteries and shall, if not otherwise agreed, be
performed by the UPS supplier. If other tests are required, additional tests shall be specified in the
uninterruptible power system data sheet.
6.9 Heating and cooking appliances (see IEC 61892-3, Clause 10)
6.10 Trace and surface heating (see IEC 61892-3, Clause 11)
6.10.1 General
Heat tracing shall be applied for frost protection, condensation prevention and process temperature
maintenance.
Design, material and installation should be according to the guidelines issued by IFEA "Veiledning for
varmekabelanlegg i industri og offshore".
6.10.2 Design
The heat tracing cables should be of the self-limiting type.
Temperature control devices like RTD, thermostats etc. should not be used. For specific applications,
however, where the self-limiting characteristic of the heating cable is unsuitable regarding response or
temperature limitations, temperature control device control shall be used. Temperature control devices shall
be installed if excessive temperature will cause corrosion on pipes and tubing.
Each of the circuits shall be equipped with an automatic trip, 30 mA earth fault relay. Trip indication shall be
provided for each circuit. Common alarm shall be given to a central alarm system for each sub distribution
board.
Sub distribution boards shall be provided for local power distribution to the heat tracing system in each
functional area. The distribution boards should not be located in hazardous areas or in exposed
environments.
6.12 Underwater systems and appliances (see IEC 61892-3, Clause 13)
See IEC 61892-3, 13.1
For remote operated vehicle (ROV) equipment reference is made to NORSOK U-001 and NORSOK U-102.
General requirements and environmental and supply conditions should also be valid for SAS.
6.13.2 Environmental and supply conditions and testing (see IEC 61892-3, 14.3)
The sockets shall be rated 63 A, 400/230 V, 3 phases + neutral. Ex-certified equipment should be used in
naturally ventilated areas.
A small power convenience socket outlet system shall be designed such that any area can be reached with a
25 m flexible cord without passing through doors.
In control rooms, local equipment rooms and offices approximately 20 % of the convenience outlets shall be
fed from the local emergency sub distribution board limited to essential equipment that has to be available
during a shutdown situation.
Convenience socket outlets shall be rated 16 A. Circuits dedicated for socket outlets shall have no other
consumers connected.
Mud resistant cables shall be used where cables are routed through areas exposed to mud/oil.
Multicore cables with collective screen shall be standard, individual screens shall only be used when required.
• general instrumentation;
• fire and gas;
• ESD;
• telecommunication.
Cables without armour may be used in the accommodation part of the living quarter, offices and control
rooms.
8.1 General
IEC 61892-5 is not relevant for fixed offshore units.
Machines and apparatus for emergency and life support systems shall operate satisfactory under all
conditions with the unit upright and when inclined up to 25° .
Earth bars shall be located in front of equipment and junction boxes to allow easy access for usage,
inspection and maintenance. All earthing bars and terminals shall be visible and possible to be checked also
after termination of cables.
If aluminium is used for any part of the main structure, attention shall be given to ensure that continuity in the
structural earth is maintained at aluminium/steel interface points.
The main earth reference points shall be earth bosses welded to the structure as close as possible to the
cabinet/equipment. Alternatively, earth bars mounted on earth bosses welded to structure may be used.
There shall be a separate main earth reference point for PE and IE.
For PDS applications separate high frequency bonding shall be installed based on recommendation from
PDS supplier.
The distance between the PE and IE reference points shall be minimum 1 000 mm.
For power cables where the braid armour does not have sufficient cross section, the equipment shall be
earthed through a separate earthing conductor in the cable.
Equipment supplied by single core cables shall be connected to PE by a separate earth cable. The separate
earth cable shall run alongside the power cables to form a "cable system" and be terminated to the field
equipment earth terminal as well as feeding end earth bar/terminal.
The copper braid of the single core cables shall be earthed at one end, isolated in the other end. Where
hazardous areas are involved, the copper braid shall be earthed in the hazardous area.
Ex d electrical equipment with direct entry, shall be connected to the PE system by a separate earth
conductor in the cable.
The PE earth cables or braids armour of cables, connected to a switchgear, cabinet, equipment etc.,
shall be connected to a PE earth bar as close as possible to the cable entry of the switchgear, cabinet,
equipment, etc.
Enclosures of high voltage equipment located in hazardous areas shall be connected to PE and bonded to
the main structure.
The IE screen shall be left floating in the field end. It shall be electrically continuous from the field equipment
and be connected to IE bar in the central cabinet.
The screen shall be connected to one IE bar only for signal cables between two control cabinets.
PE bars shall be connected to the nearest convenient main structure point through an insulated earth
conductor or through the supply/feeder cable.
IE bars shall be isolated from the enclosure and connected to the nearest convenient main structure point
through an insulated earth conductor.
Where earth bosses are used, each earth boss shall only have one connection. After connection, the whole
assembly shall be sealed in accordance with the NORSOK M-501. Bonding bosses in outdoor and exposed
areas to be coated to prevent corrosion.
Cable ladders installed horizontally shall have sufficient space to facilitate cable pulling and cleating/strapping
It shall be minimum 300 mm free space between top of one ladder edge to bottom of next ladder edge, and
from top ladder edge to roof.
Instrumentation and telecommunication cables may be routed on system 2 cable support systems when
minimum 300 mm distance between the individual systems are kept.
System 2 and system 3 cables can be installed on same field tray from branch to single equipment when this
is not in conflict with the type of signals in the cable.
Considerations shall be taken during installations of cables entering and leaving field type of equipment like
smaller packages, minor modules, crane pedestals etc. related to segregations as listed in 9.2.2.
Non-IS and IS instrument cables should be routed on the same cable ladders/trays. If routed on same
ladder/tray, the IS and non-IS cables, which contain both armour and screen can be tied together in same
bundle.
Trunking or conduits may be used for special mechanical protection of single field routed cables for shorter
distances (approximately 5 m). Where conduits are used, they shall be installed with open ends.
A computer based cable routing system reflecting the layout of the main cable support system (i.e. cable
ladders with width 300 mm and above) represented by ladder segment references, transit numbers etc. and
necessary describing information related to the individual cable including its route, shall be used in the
design.
Field cables may utilize the main cable support system provided the route of the individual cable is being
registered in the routing system and the filling and loading of the main cable support system is acceptable.
The cable ladders should not be filled so the height of the cable ladder side rail is exceeded.
Redundant cable systems shall be routed separately as shown on Figure 2, room N1.
Field routing inside rooms in safe locations may be on same cable rack/ladder if this is not in conflict with the
redundant coverage of the area as shown on Figure 2, room N2.
Once a cable has been cut, a protective cap/sealing shall be applied on the end, when being exposed to
humid atmosphere.
All cable entries to equipment located outdoors and in wash down areas should be from below. Top entry is
not allowed and side entry shall be provided with drip nose.
Sufficient cable spare length shall be provided for equipment that needs future adjustments (e.g. floodlights,
loudspeakers, etc.) or where equipment has to be dismounted for maintenance and calibration without
disconnecting the cable.
Single core cables for 3-phase AC shall run in trefoil formation. The braided armour shall be earthed in one
end. For equipment installed in hazardous areas, the braid shall be earthed at the hazardous end. When
using single core cables, additional cables for earthing have to be installed.
Single core cables shall not be installed separately through openings surrounded by magnetic materials. Non-
magnetic stainless steel separation walls and stay plates shall be used in multi cable transits utilised for
single core cables.
The minimum permissible bending radius specified by supplier shall be adhered to.
Ultra violet resistant plastic straps may be used for horizontal runs indoor.
Stainless steel AISI 316 straps shall be used for vertical runs and for horizontal runs in the vertical plane both
indoor and outdoor. For strapping of fibre-optical and coaxial cables, supplier guidelines shall be adhered to.
Trefoil cable cleats for single core power cables shall be approved for the potential short circuit stress. The
cleats shall outdoors, in naturally ventilated areas and wash down areas, be made of stainless steel AISI 316.
The distance between trefoil cleats for single core cables shall be as specified by the cable manufacturer
based on the calculated short circuit level.
Cable splicing should be avoided.
Any splicing should be agreed with the company for the installation in question.
Temporary cables should not be pulled through multi cable transits intended for permanent cables.
Plastic enclosures (relevant for field cables). Plastic for size below M32.
Plastic enclosures, reinforced with a metal gland Brass
plate for support of large supply- and multi core
cables.
Metal enclosures (except aluminium). Brass/stainless steel (AISI 316).
Aluminium enclosures. Stainless steel/nickel plated brass.
The certifications of the cable glands, blanking and drain plugs shall comply with the certification of the
equipment in which the glands and plugs are connected.
Ex d gland only to be used on Ex d direct entry equipment. The gland shall be suitable for braided cable, were
the braid is terminated inside the gland. All other glands shall be of the through type.
Instrument and telecommunication cables with both braid armour and screen shall have inner and outer heat
shrink sleeves as follows:
• the inner sleeve shall be drawn over the inner bedding, i.e. passed under the braiding providing insulation
between braiding and screen;
• the outer sleeve shall be fitted over the complete cable make-off;
• the inner sleeve may be excluded at termination's providing a minimum of 50 mm inner bedding.
Where the screen shall be left disconnected (e.g. applicable for field instrument) it shall be sealed and
isolated with an isolating cap, which allows for insulation testing without any disconnecting.
To minimize the extent of hot work sleeves of type self vulcanizing-tape may be used on units in operation.
High voltage cables should be fitted with compression lugs, unless other termination type is specified.
All cable conductors shall be terminated by use of compression lugs or ferrules dependent upon the type of
termination, unless the terminal is of a type designed to be used without ferrules. The compression ferrule
should be the type where the conductor strands are inserted through the whole ferrule and reach the bottom
of the terminal.
In switchboards and distribution boards, adequate space shall be provided for the use of a clip-on ampere
meter without causing undue stress on the cable conductors or connections.
The braid armour and the screen shall be separated from each other as well as from the conductors, twisted
and fitted as required. This shall be done without any reduction of the cross sectional area.
Only one conductor is allowed in each terminal of a terminal block/row for external connections. This is not
related to terminals approved for two conductors for internal components, e.g. relays, contactors.
Two conductors may in certain cases be used in one approved type ferrule connected to one terminal.
In cabinets all spare conductors shall be marked with terminal number and connected to terminals linked
together by solid terminal links, which shall be connected to the relevant earth bar.
Spare cores in instrument and telecom cables shall be connected to IE earth in supply end only.
If there are no spare terminals left in the cabinet, all spare conductors shall be covered with yellow/green
sleeves and marked with relevant cable number and connected directly to the relevant earth bar.
Cable ladders installed horizontally shall have sufficient space to facilitate cable pulling and fixing (minimum
300 mm free space on top of ladder).
Cable support systems shall be located to leave sufficient space for surface protection of adjacent structure.
In offices and living quarters where multidiscipline socket outlets are grouped together, multipurpose cable
channels designed for recessed installed outlets should be used.
Kick plate shall be fitted around penetrations in floor where cables/tubing are exposed to mechanical
damages.
Protection shield (minimum 500 mm above the floor) shall be installed where cables can be exposed to
physical damages.
Cable ladder systems shall be protected from danger of dropped object due to crane handling or similar.
Equipment brackets and supports should not be installed on removable deck, grating, panels, handrails,
pipes or other removable equipment.
9.5 Switchgear and control gear assemblies (see IEC 61892-6, Clause 8)
9.5.2 Space at the rear and passageways (see IEC 61892-6, 8.5)
Minimum space for maintenance of 690 V switchgear and control gear should be not less than 0,8 m.
9.6 Secondary cells and batteries (see IEC 61892-6, Clause 10)
Access (see IEC 61892-3, 10.3.1)
Floodlights shall be installed on solid and adjustable brackets which ensure stability in all directions.
9.7.3 Lighting installation for navigational aid and platform identification sign
For reference to lighting installation for navigational aid and platform identification sign, see
9.8 Trace and surface heating (see IEC 61892-6, Clause 13)
The heat tracing cable should be protected against damage by applying an aluminium tape/foil on top of the
cable when cellular glass is used as insulation material.
9.12.1 General
All marking shall be in accordance with NORSOK Z-DP-002.
All electrical equipment shall be marked with function, supply panel and circuit/cubicle.
High voltage cable ladders, shall be marked with warning labels in accordance with the national regulations.
9.12.3 Equipment
Internal in serial produced equipment with power electronics (i.e. like UPS, ASDS) supplier's standard for
internal wiring and marking shall be accepted.
All labels shall be fabricated and installed in accordance with the following requirements:
• labels shall be readable from deck or access platform. Label text to be sized accordingly;
• labels should not be mounted on removable parts;
• labels should be fixed by AISI 316 screws, rivets or suitable glue (only in dry areas);
• separate label brackets, if used, shall be made of AISI 316;
• labels shall be of engraved traffolyte, marked as follows:
• black letters on white background, letter size 10 mm to 20 mm;
electrical, instrumentation and telecommunication systems withservice description in Norwegian;
• white letters on red background, letter size 10 mm to 20 mm.
Instrument ESD systems, Fire & Gas systems and warning labels with
service description in Norwegian and English language.
In panels fuses shall be clearly marked. A fuse list shall be provided inside of panel.
All emergency lighting fixtures with integral batteries shall in addition to normal labelling be marked to identify
that integral batteries are present and to identify which light source is battery backed.
9.12.4 Cables
Each cable shall be marked with indelible and non-corrosive cable markers indicating the cable number. The
cable markers shall be clearly visible after cleating and strapping. Outdoors, in exposed- and wash down
areas the cable markers shall be of stainless steel.
Cable core identification shall be according to one of the alternatives listed in NEK 606. The alternative which
is referred to CENELEC in NEK 606 is the preferred solution.
AC systems:
Bus bar: Cable:
Phase 1 L1 Black
Phase 2 L2 Grey
Phase 3 L3 Brown
Neutral N Blue
Protective earth PE Yellow/Green
Protective earth/neutral PEN Yellow/Green + Blue
Conductors in single phase cables, from distribution boards in three phase four wire system (3ph + N), can,
inside light fixtures, socket outlets, junction boxes etc., have conductor colour as cable core colours (normally
black and white). Black is always used for the phase.
DC systems:
Positive pole (+) Black
Negative pole (-) Blue (White)
9.12.6 Colour coding of earth conductors, earth bars and cable screen
9.12.6.2 Bonding
Static earth conductors shall be coloured yellow/green.
When junction boxes are installed in exposed areas, drain plugs shall be installed. Anti condensation heating
should be provided in boxes containing active components.
Junction boxes shall be designed with sufficient space for the expected number of cables and cable make-
offs.
Location shall also be where it is practical for operation, i.e. close to gangways etc.
Anti condensation heating should be provided in control stations containing active components.
Cable protection shields shall be made in the same material as the cable support system in the area.
Equipment brackets shall be fabricated from the same material as the cable support system in the area.
Junction box stands shall be fabricated from the same material as the cable support system in the area.
On cable racks/trays etc. nuts with integrated washer or manufacturer standard to be used.
10.1 General
Until ATEX harmonized IEC standards is available the latest version of IEC 60079-0), IEC 60079-2, IEC
60079-1,IEC 60079-7 and EN 50020 shall be used for design and marking of electrical equipments including
parts.
10.2.1 General design of electrical systems shall be according to Clause 4 and Clause 5.
10.3.1 General
Requirements for equipment are stated in Clause 6.
In order to avoid installation of major electrical in hazardous areas or in exposed environments, all major
electrical equipment shall be installed inside equipment rooms with a controlled atmosphere.
All EX equipment shall have the ex labeling located so they are readable also when installed on site. Labels
shall be designed and fastened to withstand environmental stresses (included high pressure cleaning with
salt water) for the certified equipments expected lifetime.
Compression type gland may be accepted if the equipments ATEX certificate cover gland and installed cable
type, actual gas group and EX d compartment size (normally under 2 liter.)
Compression type gland may also be accepted if gland and cable is covered in the ATEX certificate for actual
equipment.
10.3.2 Ex requirements
Ex-certified equipment should be selected in accordance with the following:
All Exn equipment shall, if not else accepted, be disconnected with gas detection in the equipment location
area. Ex n high voltage equipment shall not be located in zone 2 areas.
NOTE The requirement means that “American conduit systems” among others is not permitted in hazardous areas. However, use of
conduits as mechanical protection for cables is permitted.
For package equipment it may also be accepted to use vendor standardized conduit system if alternative
cable installation is not recommended.
However, such installation shall end in a termination box designed to a connect conduit system to a cable
system. The total installation shall be certified and fulfil requirements according to IEC 61892, all parts.
Annex A
(Normative)
Data sheets
Bibliography
[1] IEC 60298, A.C. metal-enclosed switchgear and controlgear for rated voltages above 1kV and
up to and including 52kV. (1990-12)
[2] IEC 60076, Power transformers.
[3] IEC 60551, Determination of transformer and reactor sound levels.
[4] IEC 61136-1, Semiconductor power converter - Adjustable speed electric drive systems -
General requirements Part 1: Rating specifications, particularly for d.c. motor
drives.
[5] IEC 61800-2, Adjustable speed electrical power drive systems, Part 2: General requirements
Rating specifications for low voltage adjustable frequency AC power drive
systems.
[6] ISO 1680, Acoustics Test code for the measurement of airborne noise emitted by rotating
electrical machines,
[7] NORSOK S-002, Working environment