Equipment Evaluation Tool Based On The Manufacturing System Design Decomposition
Equipment Evaluation Tool Based On The Manufacturing System Design Decomposition
ABSTRACT
This paper presents an evaluation tool that can be used to determine how well the physical characteristics of a particular piece of
equipment (or set of machines) satisfy the functional requirements of the manufacturing system design. This evaluation tool for equipment
is based on the Manufacturing System Design Decomposition v5.1 (MSDD). The MSDD identifies a series of goals for a manufacturing
organization called Functional Requirements (FRs) and how each one of these helps to achieve the high-level business goals. The
requirements from the MSDD that affect equipment design and operation have been identified, and the evaluation tool presented here can
be used to evaluate how well a particular piece or set of equipment conforms to these requirements. This evaluation tool can be used to
ensure that equipment designs better align with overall manufacturing system objectives. The tool can also be used to identify problems
with existing equipment and to set goals for the equipment to be improved to better satisfy the requirements placed on it by the MSDD.
Keywords: Equipment Design, Machine Design, Cell Design, Production System Design Decomposition, Lean Production
efforts.
4. Provide a method to track the progress of
improvements in terms of equipment design and
operation.
5. Align equipment design with the business Quality Time Delay Operating
objectives identified by the MSDD. Variation Reduction Costs
2
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000
3
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000
The objective of the equipment evaluation tool is to sub-FRs of a particular FR affect equipment design, then
assess how well the physical attributes of a particular piece the evaluation tool will use the parent FR as the evaluation
or set of equipment satisfy the FRs from the MSDD that criteria instead of using all of its sub-FRs. The use of this
affect equipment design and operation. The previous rationale allows us to reduce the number of criteria to be
section identified the FRs from the MSDD that relate to evaluated from 22 FRs that influence Equipment design
the equipment, and those will be used as the evaluation (from the previous section) to only 13 FRs, without
criteria in the Equipment Evaluation Tool. However, in sacrificing the effectiveness of the evaluation. Figure 3
the spirit of reducing the information content of the illustrates how the FRs that affect equipment design were
evaluation tool without sacrificing its effectiveness, some consolidated into a smaller number of evaluation criteria
of the criteria were consolidated to reduce the overall using the rationale described above. It also shows how
number of FRs to be considered. The rationale used to these criteria appear in the Equipment Evaluation Tool
consolidate the FRs was: when all (or at least most) of the and how each of the criteria relates to the FRs from the
Investment
Facilities Cost
Time Delay Direct
Quality Variation Reduction Labor
machine method errors don’t recognize problems to equipment balanced sufficiently systematic added tasks wasted Minimize production
assignable assignable translate to production the right is easily with takt small run operational at each motion of facilities system
causes causes defects disruptions people serviceable time sizes delays station operators cost lifecycle
FRs used as evaluation criteria FRs driving equipment design and operation but not
directly evaluated (evaluated using their parent FRs)
Figure 3: Derivation of Criteria for Equipment Evaluation Tool from MSDD
4
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000
5
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000
# of defects # of defects # of defects Time Time Time Production Actual run Production % of % of Facilities Investment
per n parts per n parts per n parts between between id required to cycle time - size - target time lost operators’ operators’ Cost over
assignable assignable caused by occurrence of what the service takt time run size. due to time spent time spent production
to to the human error of disruption disruption is equipment Ratio of interference on NVA on wasted system
equipment process and and support #, length of changeover among tasks while motions lifecycle
# of defects
identification resource time to takt resources waiting at a
per n parts unplanned
of what the knowing time station
Metrics
assignable equipment
disruption is what it is
to operators downtime
# of defects per n parts with an Time between occurrence #, length of Inv. due to Inv. due to % of time
assignable cause and resolution of problems disruptions process run size waiting on
delay delay equipment
Process Capability % on-time deliveries Difference between mean throughput % of op. time spent on
time and customers’expected lead-time NVA motions and waiting
Sales revenue Production Costs
Return on Investment
even between different applications within the same the performance metrics for each FR to allow a
system, setting the targets is left to the user considering quantitative evaluation. Finally, the Equipment Evaluation
the particular application. Tool includes the motivation, the derivation of the FRs
being evaluated from the MSDD and the instructions and
example of evaluating a column, to make it a self-
Structure of the Equipment Evaluation Tool
contained document.
The complete Equipment Evaluation Tool is shown in
Figure 6 in a reduced view to present its format and Quality
structure. Notice that the Equipment Evaluation Tool
consists of 13 columns, each one corresponding to one of The 3 FRs from the quality branch on the MSDD that
the evaluation criteria, and they are used to assess the level affect equipment design are:
of achievement of the 22 FRs from the MSDD that relate
to the equipment. Each column describes the physical • FR-Q11 Eliminate machine assignable
characteristics of equipment at each of the six levels of causes:
achievement. The document also has a comments section Refers to the quality reliability of the equipment.
to clarify the purpose and scope of each column, as well as Assignable causes are those that cause the process to go
Equipment out of control and may be: tool wear/breakage, bearing
failures, etc. Equipment design should strive to maintain
FR: Maximize long term return on investment / DP: Manufacturing system design
FR: Maximize sales revenue / DP: Production to maximize customer satisfaction FR: Minimize prod’n costs / DP: Elimination of non-value adding sources of cost
Upper level PSD Decomposition
FR: Manufacture products to target design specifications / DP: Production FR: Reduce waste in direct labor / DP: Elimination on
FR: Deliver products on time / DP: Throughput time variation reduction FR: Meet customer expected lead time / DP: Mean throughput time reduction
processes with minimal variation from the mean non-value adding manual tasks
FR: Minimize production FR: Reduce process delay FR: Reduce run size delay FR: Eliminate operators
(FRs/DPs)
breakdowns.
operators reliability
Ensure that production Reduce time operators Minimize investment
Evaluation Ensure operator human
Eliminate machine Eliminate method Rapidly recognize Communicate problems to Ensure that equipment is cycle time is balanced Produce in sufficiently Reduce systematic spend on non-value added Eliminate wasted motion over production system
Criteria errors do not translate to
assignable causes assignable causes production disruptions the right people easily serviceable with takt time small run sizes operational delays tasks at each station of operators Minimize facilities cost lifecycle
(FRs) defects
Poor quality output from Methods call for excessively Equipment relies solely on Production disruptions are When a disruption is Access to service locations Equipment designed without Equipment can not be Equipment design forces Equipment forces operator Equipment width and Equipment is very large and Equipment dedicated to a
equipment due to unknown low tolerances/ unnecessary operator judgement/training generally not promptly identified, it is not clear to is severely limited. Many regard to takt time. changed over and is routine service activities to to wait through the entire spacing requires long requires a large area to be single part type and
1
causes of variation (unable processing due to (part and tool selection, recognized. The equipment the operator which non-standard, difficult to Equipment cycle time designed to run only one stop production completely. duration of the cycle for walking distances. clear for service access. designed to run as fast as
to hold mean). complicated material flow machine operation, etc.) to provides no feedback to resources to contact or what replace parts are used. (manual, automatic or a type of product. Different production and/or automatic operations. Excessive motions required Equipment requires special possible. No flexibility for
paths. Expected process produce high quality parts. allow operators to identify information to give them Only highly skilled combination) is greater than different service resources Operator must manually to search for tools and facilities which are costly to future design and/or volume
yields are low due to problems. about the problem. personnel can service takt time. have the same access unload parts before materials. Ergonomics provide (special power, changes. Not easily
selected methods. equipment. requirements. loading the next. are very poor. clean room, etc.) moved.
2
paths. Methods are operation but still relies on disruptions. When one is the same resource, even if Many non-standard, difficult Equipment cycle time are run in large batches to stop production completely. machine cycle. Operator walking distances. Most which are costly to provide of a single product but only
changed to improve process operator judgement/training identified the equipment can not qualified to solve the to replace parts are used. (manual, automatic or a avoid changeover. Frequent interference must manually unload parts tools and materials are (special power, controlled with major modifications, it
yields, reduce unnecessary to produce high quality only identify a general area problem, because equip. Only highly skilled combination) is greater than between different production before loading the next. located at the station but temperature, does not continuously
processes and simplify parts. as the source of the doesn’t provide personnel can service takt time. and/or different service poorly organized. clean room, etc.) support multiple parts.
material flow paths problem. detailed feedback. equipment. resources. Ergonomics are fair. Not easily moved.
identified but are still not yields that are on par with visual feedback (lights) to rapidly but the equipment the operator receives require maintenance. Many regard to takt time. is long enough to prevent production to stop for some to wait through part of the spacing requires considerable size and/or it support different part types
3
eliminated. industry standards. aid correct operation but it can only identify a general enough information from non-standard, difficult to Equipment cycle time frequent changeovers. The routine service activities. machine cycle. Operator unnecessary walking requires a large area to be but not designed to run at
Continuous efforts are made cannot prevent incorrect area as the source of the equipment to know which replace parts are used. Only (manual, automatic or a need for shorter changeover Some interference between must manually unload parts between stations. clear for service access. takt time or a range of takt
to improve process yields. operation. problem. resource to contact. No info highly skilled personnel can combination) is greater than time is recognized. different production and/or before loading the next. Ergonomic interface Some special facilities are times (no volume flexibility).
about nature of service equipment. takt time. different service between operator and required but they are Not easily moved.
4
are still unable to be standards. Continuous defects could still be can identify a specific operator to contact the right Some non-standard parts. takt time. Equipment cycle magnitude as the takt time. routine service activities. and walk away. Operator unnecessary walking. Most requires a large area to be Equipment runs at takt time
removed. efforts are made to reduce intentionally produced and machine/station as the resource with some Only skilled personnel can time (manual, automatic or Different production must manually unload parts tools, fixtures and materials clear for service access. No and allows running slower
5
stabilized and mean shifts process yields. Some making defects but it does can pinpoint the subsystem operator to contact the right locations that require Equipment cycle time feeding parts for different rear of equipment, without and walk away. When cycle walking distance. Parts, only requires a small area to takt times) and product (a
6
assignable causes of continuously improved. incorrectly. Visual aids, to the operator, along with operator to contact the right to locations that require Equipment cycle time Equipment can make parts of equipment, without and walk away. When cycle operator walking distance. space, and it needs a takt times) and product (a
variation eliminated or There is no unnecessary sensors and equipment information about the exact resources with the right maintenance. Uses only “off (manual, automatic or a for different products disrupting production. is complete the equipment Parts, tools are conveniently minimal area for service family of products) flexibility.
controlled. processing and process features prevent loading the location and nature of the information to allow them to the shelf” parts. Minimal combination) is less than immediately available when Different production and automatically unloads the located at the station to access requirements. No Equipment can easily be
yields are high. wrong part or cycling problem. start working training needed to takt time. needed. different service tasks part (Man-machine provide a highly special facilities are reconfigured and
if there is a problem. immediately. service equipment. have separate access. separation achieved). ergonomic interface. required. moved.
process to go out of control machining etc. The order equipment should prevent when they occur. It should to resolve problems when design of the machine, the automatic or a fixtures, one-touch from the rear to prevent waiting and minimize non distance. Equipment should not require special this design and have the
and may be: tool and type of operation and loading the wrong part or also be able to pinpoint the they occur. It should also simpler its maintenance. combination) can be equipment setups, and disrupting production value-adding tasks. should be designed such facilities (special power, flexibility for expected
Eliminate Eliminate Ensure Rapidly Communic. Ensure that Ensure that Produce in Reduce Reduce Eliminate Minimize Minimize
metrics for each FR may be used.
Evaluation
•Indicate how equipment can satisfy the requirements machine method human recognize problems to equipment produc. rate sufficiently systematic time ops. wasted facilities production © MIT 2000
from the MSDD (future objectives). assignable assignable errors don’t production the right is easily is balanced small run operational spend tied motion of cost investment 4. As changes are implemented, the
6
•Provide a method to track the progress of DATE FILENAME PAGE OF PAGES
causes causes translate disruptions people serviceable with takt sizes delays to operators impact on the metrics and design
6
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000
loading a part. Equipment will not cycle if there is a products. Quick-change fixtures, one-touch equipment
problem. setups, and quick changeover of material supply should be
considered to reduce the changeover time.
Time Variation
• FR-T5 Reduce systematic operational delays:
The 3 FRs from the time variation branch on the Equipment should allow access for routine service
MSDD that influence equipment design are: operations (lubrication, chip removal, coolant flush, etc.)
from the rear of the station to prevent disrupting
• FR-R11 Rapidly recognize production production activities. Access points for different
disruptions: production activities should be separate.
Equipment should be designed to help operators identify
production disruptions immediately when they occur.
Equipment should also be able to pinpoint the location
and the exact nature of the problem. Lights, display
screens and other feedback systems help to recognize
production disruptions rapidly.
Delay Reduction
7
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000
Direct Labor MSDD affect equipment design and operation and which
physical characteristics the equipment should have to
The 2 FRs from the direct labor branch on the MSDD satisfy these requirements. The Equipment Evaluation
that influence equipment design are: Tool allows a qualitative evaluation of the equipment in a
gradient of 6 levels of achievement by comparing the
• FR-D11 Reduce time operators spend on non- physical attributes of the equipment to the descriptions
value added tasks at each station: under each one of the levels. The Equipment Evaluation
When automation is advantageous the equipment should Tool also allows a quantitative evaluation by using the
be designed to prevent tying the operator to the station performance metrics for each FR being assessed.
waiting for an automatic cycle to be completed. The
equipment should allow the operator to load a part, start The Equipment Evaluation Tool can be very valuable
the cycle and walk away, and the equipment will unload the to a manufacturing enterprise since it serves as a measure
part automatically when finished. of how well the current design and operation of
equipment supports the manufacturing system design.
• FR-D2 Eliminate wasted motion of operators: The tool can also be very useful in providing a guideline or
The width and spacing of stations/equipment should be set of objectives for the improvement of current
kept to a minimum to reduce the operators’walking equipment or the design of new equipment. Another
distance. Equipment should be designed such that application is to track the progress of a system as the
fixtures, tools and materials are located to minimize equipment design changes.
wasted operator motions.
It is important to note that although the authors have
made every attempt to make the concepts and descriptions
Facilities Cost and Production Investment in the Equipment Evaluation Tool general in nature, they
might not apply exactly to every industry or every
The 2 FRs from the facilities cost and production
manufacturing operation. When using the Equipment
investment branches on the MSDD that affect equipment
Evaluation Tool it might be useful to alter some of the
design are:
descriptions and/or metrics to suit the particular industry
or system under evaluation.
• FR123 Minimize facilities cost:
Equipment should be designed with the smallest possible
footprint to minimize overhead cost. It should not require REFERENCES
special facilities (special power, controlled temperature,
clean room, large chip removal systems, etc.) whenever Arinez, Jorge F. and David S. Cochran. “Application of a
possible. Production System Design Framework to Equipment
• FR13 Minimize investment over production Design”. Proceedings of the 32nd CIRP International
system lifecycle: Seminar on Manufacturing Systems. Leuven, Belgium,
Investment decisions are largely dependent on how the May 24-26, 1999.
system is designed. Equipment should support the system
design and have the flexibility for expected volume Carrus, Brandon J. and David S. Cochran. “Application of
changes, design changes and layout reconfiguration a Design Methodology for Production Systems”.
changes (cycle time/product flexible and small/movable Annals of the 2nd International Conference on
machines). Engineering Design and Automation. Maui, HI, July
1998.
8
Equipment Evaluation Tool Based on The Manufacturing System Design Decomposition
The Third World Congress on Intelligent Manufacturing Processes & Systems
Cambridge, MA – June 28-30, 2000