Examples: Project Planning Techniques Network Analysis Critical Path Method (CPM)
Examples: Project Planning Techniques Network Analysis Critical Path Method (CPM)
Network analysis
Critical Path Method (CPM)
Examples
Examples
Ex1: Determine the critical path by using CPM of the following Table
(project),
Duration
Activities Path (day) Description
A 1─2 3
B 2─3 3 وصف
C 2─4 1 مختصر لكل
D 3─5 2.5 فعالية
E 4─5 2
Ans:
Critical path =3+ 3+ 2.5= 8.5 days
Ex2: Determine the critical path by using CPM of the following Table
(project),
Duration
Activities Path (week) Description
A 1─2 1
B 1─3 4
C 3─5 3
وصف مختصر
D 3─4 5
لكل فعالية
E 2─4 2
F 5─6 3
G 4─6 6
Critical path= 4+ 5+ 6= 15 weeks
Example .
A project to manufacture a product is composed of the following
activities:
Project network
Example:
Draw the network diagram for the following activities and find:
1. The critical path CPM
2. Find the free float time
3. Find the total float
Activities Preceding Act. Duration (week)
A - 3
B - 2
C B 2
D A 3
E A 2
F C,D 3
G C,D 2
H C,D,E 7
I C,D,E 5
J H,F 6
Solution:
3 6
3 1 6
0
1 8 Tf
0 2 4 8 Ff
E=2
0
0
A=3 H=7
0 I=5 19
D=3 1 L
19 E
13
0 0 4 0
0 4 0 J=6
5 6
B=2
2
F=3
0 C=2
1 3 11
G=2
11
4 2
6
2 2
6