Introduction:
This method of statement for electrical work for the gypsum partition offices work shall help
you understand the requirements before and during the cables and wire pulling process.
Below is the list of equipment / Tools required for installation of cables and wires as per project
requirement:
Tools/ Equipment’s:
Measuring tape
Cutting plier
Box Spanner set
Bending spring
Pipe Wrench
Drilling Machine
Crimping tool
Screw Driver
Pulling spring
Hammer
Common Tools.
Manpower:
Engineeing Staff & Charge hand:
Site Engineer:
To ensure that the works are carried out according to the contract specifications.
To provide all necessary information and distribute responsibilities to his construction
team.
To monitor the progress of work in relation with the work program and to report to the
project manager.
To co-ordinate with the safety officer and to ensure that the works are carried out in
safe practicing methods.
Temporary works:
Temporary works includes Scaffolding with working platforms, toe board etc.
Double Volume areas to be staged by main contractor and certified by the main
contractor safety.
Date: 24/07/2020
Sign: