Method Statement FOR: 0.0 For Review QA/QC Dept. Project Manager Operation Manager

The document provides a method statement for installing a plumbing system for a domestic water system. It outlines the scope of work, materials used including PPR pipes and fittings, applicable locations inside buildings, and methods for storage, installation, and testing. The installation method includes fabricating pipes in the workshop, determining locations, installing supports, fusion joining using heated welding heads, and pressure testing the system before operation.

Uploaded by

Walid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views6 pages

Method Statement FOR: 0.0 For Review QA/QC Dept. Project Manager Operation Manager

The document provides a method statement for installing a plumbing system for a domestic water system. It outlines the scope of work, materials used including PPR pipes and fittings, applicable locations inside buildings, and methods for storage, installation, and testing. The installation method includes fabricating pipes in the workshop, determining locations, installing supports, fusion joining using heated welding heads, and pressure testing the system before operation.

Uploaded by

Walid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

METHOD STATEMENT

FOR

Plumbing System
Domestic water system

0.0 For review QA/QC Dept. Project Manager Operation Manager

REV DATE DESC. PREPARED BY CHECKED BY APPROVED BY

Page 1 of 6
CONTENTS

1. Scope of work

2. Material

3. Applicable Location

4. Method

5. Installation

6. Testing

1.0 Scope

Page 2 of 6
The scope of this method statement is to cover the water supply work
procedure for the PP-R water pipe systems.

.
2.0 Material

2.1 For pipeline

PPR pipes and Fittings PN 20.

2.2 Equipment

1-Welding Machine 2-Cutting machine

3-Saw

3.0 Applicable Location

Inside buildings

4.0 Method

4.1 Storage

4.1.1 When offloading pipes shall be lowered to the ground either manually
or with mechanical aid like crane depending on the quantity of the pipe
and should not be dropped to the ground. Refer – Manufacturer’s
instruction for transport, handling and storage.

4.1.2 Pipes shall be stacked on a flat surface free from any sharp objects.

4.2 Installation

Page 3 of 6
A. Pipe fabrication:

 Fabricate pipe as much as you can in the workshop according to sizes as per
drawings to be ready for installation.

 The location of pipe will be determined according to approved shop


drawings.

 After the completion of marking points ,fix the line with the
required levels.

 Install the supports and hangers that will hold up the pipes as
per project specifications and drawings.

 The pipe shall be clean from the dust, loose particles and other foreign matters.

 Before beginning the fusion process, you will be need to check the welding
heads to verify that they've reached a temperature of approximately 500 degrees
Fahrenheit or 260 degrees Celsius +/-10 degrees Celsius.
 Once the iron is ready, prepare the pipe for fusion. Always cut the pipe squarely
using a sharp cutter.

Page 4 of 6
 Put the pipe and fitting straight off the iron and slide them squarely together.

 Quickly adjust the pipe to ensure the proper alignment.

 the pipe and fitting cool, the connection is ready for full
system pressure

5. Testing

 The whole system shall be tested before put the system in operation by 1

Page 5 of 6
1/2 operating pressure but not exceed any system component rating
pressure.
 Provide temporary blind flanges at all ends of the risers to prevent
leakage.
 If any leakage or pressure drop found the test must be repeated.

Page 6 of 6