JOB HAZARD ANALYSIS - Cable Tray
JOB HAZARD ANALYSIS - Cable Tray
JOB HAZARD ANALYSIS - Cable Tray
RISK
BASIC JOB STEPS POTENTIAL HAZARDS
LIKELIHOOD
EFFECT
SEVERITY
RPN
A. Site Access / 1. Uninformed 2 1. Unable to start 1. All workers, including subcontractors must have
Plant induction workers - unaware operation completed the Induction training;
of the hazards and 2. Unauthorized 2. Advise workers and other persons on the site of the
dangers at the site / and incompetent
4 2 8 work to be carried out. 2 2 4
work area / plant. personnel to do
2. Not knowing and work 3. Conduct a site specific induction for all project workers
understanding of 3. Unorganized and have them sign a site induction attendance
emergency and unplanned including but not limited to:
procedures. work will expose Hazard specific to the site of the work to be
3. poor / no / personnel to carried out.
miscommunication hazard
between workforce Safety controls and revised SWMS (Safe Working
and supervisor. Method Statement)
Use and maintenance of Personal Protective
Equipment (PPE);
Emergency and Evacuation procedures; and
Location of amenities and first aid facilities.
B. Prepare PTW 1. Non-compliance on 2 1. Unable to start 1. Follow establish Linde permit system and make sure
Linde permit operation all precautions are followed prior commencing work.
system 3 2. Unauthorized 2. Competent personnel to perform the task being
Page 2 of 10
and
8. Check for any items that may cause slips, trips and
falls and remove or secure them as required
E. Load / unload 1. Manual Lifting / 2 1. Back injury 1. Identify approved material lay-down area
& transport manual handling 2. Property 2. Assess lift, lift within capabilities, use correct lifting
Tools & 2. Traffic / Site access 3 damage procedure, 1
3 9 2 2
Materials to 3. Damage / injury 3. Fatality 3. 2-man lift or mechanical aid (Skates, etc.), if required.
work area and due to crane or 4. Work loss 4. Ensure correct manual handling techniques, warm up
unload boom truck / forklift 5. Hand injury & stretch to avoid strains / sprains.
failure or 6. Cuts and 5. Do not carry long or awkward materials on your own.
incompetent abrasion 6. Review prospective route of access prior to carrying
operator 7. Personal injury materials to work area with consideration given to any
4. Ergonomic Hazard obstacles / trip or slip hazards.
5. Tripping and 7. Stick to designated pathways as much as possible.
Slipping hazard 8. Use gloves to protect hands.
6. Pinch point 9. Supervisor shall ensure personnel involved at work
have attended safe manual lifting and handling training
10. Ensure equipment are placed firmly on floorings, and
load is evenly distributed.
11. Seek help; ensure adequate manpower to carry the
items.
12. Discuss correct manual lifting method and work posture
during toolbox meeting.
13. Take rest breaks for repetitive task.
14. Avoid working in awkward position / posture.
15. Ensure tools and equipment used only for its intended
purpose and according to proper handling technique or
manufacturer recommendation.
16. Co-ordinate delivery / site access with site controller
17. Loads projecting beyond vehicle must be flagged
18. Park vehicle in a stable position, in gear with
handbrake on
19. Operators / helpers must be competent and qualified.
20. Plant and lifting equipment must be in serviceable
condition and have documented maintenance records.
21. Wear gloves during all manual handling
22. Ensure material is carried in small quantity to
23. Minimize the weight carried.
24. Use of mechanical aid if necessary
25. Keep access and egress routes clear and segregate
the work area from others and vehicles in access
Page 4 of 10
areas.
26. remove any items that may obstruct the work activity;
and
27. Check for any items that may cause slips, trips and
falls and remove or secure them as required.
28. Maintain good housekeeping at work area.
29. Educate worker on proper hand placement
30. Buddy buddy system
31. Proper communication and coordination before lifting
tubular pipes.
32. Provide an awareness training regarding line of fire and
hand finger safety.
33. Ensure hand gloves is worn in any operation
F. Preparation of 1. Poor access and 2 1. Back injury 1. Make sure all access and egress, access ladders,
work area egress 2. Property steps and ramps are safe and secure.
2. Poor or bad 3 3 9 damage 2. All personnel to have read and understood the RA that 1
2 2
weather condition 3. Fatality is specific for their area of work.
4. Work loss 3. RA is to be modified where and when necessary to
5. Hand injury reflect the changing work area.
6. Cuts and 4. Personnel to wear mandatory PPE's on site such as
abrasion but not limited to hardhat, safety glass, safety shoes,
7. Personal injury and earplug/earmuff.
5. Immediately cease work in hazardous weather
condition such as:
1. strong winds that may cause loss of balance
2. Rain is causing a slippery work surface.
G. Fabricate 1. Injury due to unsafe 2 1. Fatality 1. All power tools are to have a current test tag attached.
Cable tray or incorrectly used 2. Serious Injury 2. Ensure pre checks are carried out on all equipment prior to
support and hand / power tools 3 4 12 3. Personal Injury use 3
2 6
bracket 4. Hand injury 3. Only use equipment with guards and auxiliary handles in
place.
4. Ensure that when changing drill bits, grinding / cutting
discs or adjusting the grinder guard that the power is
disconnected (i.e. plug is disconnected from the power
source). If a portable grinder is being used engage the
‘switch lock’.
5. • When carrying the portable grinder engage the ‘switch
lock’ to prevent the unit from being accidentally switched
on.
6. • Prior to grinding or drilling work ensure that the piece to
Page 5 of 10
to unnecessary hazards/risks.
11. Hard barriers should be used wherever possible.
12. Correctly store all equipment not being used.
1. Manual Handling 2 1. Physical injury 1. Identify approved material lay-down area
and lifting 2. Ergonomics 2. Assess lift, lift within capabilities, use correct lifting
4 5 20 3. Back injury procedure 3
2 6
4. Hand injury 3. 2-man lift or mechanical aid (Gattic lifters etc.), if
5. required
4. Barricade unloading area as required
5. Ensure correct manual handling techniques, warm
up & stretch to avoid strains / sprains.
6. Do not carry long or awkward materials on your
own.
7. Review prospective route of access prior to
carrying materials to work area with consideration
given to any obstacles / trip or slip hazards.
8. Stick to designated pathways as much as
possible.
9. Use gloves to protect hands
8. 1. Work at heights 1. Serious Injury 1. Secure Work at Height permits and WAH clearance
2. Fall from Height 2. Fatality 2. Barricade area around
3. Falling of tools / 3. Work loss 3. Always use approved platform ladder / scaffolding
materials 4. Property 4. Wear fall protection equipment (Full Body Harness)
4. Pinch point / sharp damage 5. Do a visual inspection on the ladder prior to use.
edges 5. Fracture 6. Use correct sized ladder for the task.
6. Hand injury 7. Ensure ladder is correctly and securely set up on
even ground for specific tasks
8. When working off a ladder, always have feet facing
forward on the platform.
9. Maintain 3 points of contact.
10. Ensure 4:1 ratio
11. Ensure correct use of appropriate ladder for the task.
12. Set ladder up on a level surface and do not stand
more than 3 steps from the top rung. Ensure 3 points
of contact at all times.
13. Supervisor shall ensure personnel involved at work
Page 9 of 10
2. Housekeeping 1. Scattered material 2 1. Personnel 1. Working area should be clear of unnecessary material
2. Slip and trip injury and waste
3. Obstruction to other 2 3 6 2. Fracture 2. Walkway should be maintained without tripping caused 3
2 6
trade contractor material
3. When work finishes, housekeeping shall be
implemented
4. Supervisors need to inspect the area before dismissal of
work
5. Isolate or remove all tripping hazards in the workplace
and passage area.
6. Remove any items that may obstruct the work activity;
and
7. Check for any items that may cause slip, trip and falls
and remove or secured them as required.
8. Ensure all material off cuts and rubbish are removed as
they are generated and disposed of in appropriate
receptacles.
9. Ensure all materials/tools and equipment is removed
from the work area when departing.
10. Cleanup work area and dispose of all rubbish in bins.
11. Maintain good housekeeping practices before, during
and after the activity.
12. Only competent personnel to do the task.
NOTE: 1. THIS JHA/MS SHOULD BE DISCUSSED, UNDERSTOOD AND SIGNED BY ALL PERSONNEL INVOLVE IN THE ACTIVITY.