8-Transformer Protection
8-Transformer Protection
Issue B1 Issue B1
Last Release : March 2011 Last Release : March 2011
PROGRAM PROGRAM
D t il off transformer
Details t f protections
t ti and
d constraints
t i t D t il off transformer
Details t f protections
t ti and
d constraints
t i t
Conclusion – Typical
yp schemes Conclusion – Typical
yp schemes
Need to reduce looses and conductor Need to reduce looses and conductor
sizes
i Industrial Consumer Résidential,... sizes
i Industrial Consumer Résidential,...
Exemple : thermal power plant 660 MVA 20kV/225kV Cable overheating consideration Exemple : thermal power plant 660 MVA 20kV/225kV Cable overheating consideration
Without transf. P=UI3 => 660000 = 20. I. 3 => I = 19000 A Cross Section = 17800mm² =150mm Without transf. P=UI3 => 660000 = 20. I. 3 => I = 19000 A Cross Section = 17800mm² =150mm
With transf.
transf 225. II. 3 => I = 1690 A
P=UI3 => 660000 = 225 Cross Section = 1500mm²
1500mm =44mm With transf.
transf 225. II. 3 => I = 1690 A
P=UI3 => 660000 = 225 Cross Section = 1500mm²
1500mm =44mm
V1 Ep n1 n2 Es V2 V1 Ep n1 n2 Es V2
Practically, primary and secondary windings are placed together arround the same Practically, primary and secondary windings are placed together arround the same
magnetic core, in order to reduce magnetic loses magnetic core, in order to reduce magnetic loses
I1 generates a flux Ø = BS with B= 4 10-7 nI (Weber) I1 generates a flux Ø = BS with B= 4 10-7 nI (Weber)
I1/I2 = V2/V1 = n1/n2 I1/I2 = V2/V1 = n1/n2
A a A a
A2 A1 a1 a2 A2 A1 a1 a2
Example : Example :
Transformer : Dy11 Transformer : Dy11
B b B b
B2 B1 b1 b2 B2 B1 b1 b2
HV Winding HV Winding
MV Winding MV Winding
C c C c
Vector Group C2 C1 c1 c2 Vector Group C2 C1 c1 c2
A a a2 A a a2
The secondary winding is C1 A2 The secondary winding is C1 A2
30° leading with the a1 30° leading with the a1
primary winding c1 b primary winding c1 b
A1 b1 b2 A1 b1 b2
C2 C2
C B1 B2 B c2 C B1 B2 B c2
c c
Schneider Electric 6 Schneider Electric 6
Vector group Vector group
Ho to find back the terminals connection
How Ho to find back the terminals connection
How
Winding Winding
Insulation Insulation
Fire Fire
Protection Protection
Example 1 Example 1
400MVA 400MVA
(Hyundai) (Hyundai)
Example 2 Example 2
650MVA 650MVA
(ABB) (ABB)
I1 I2 I1 I2
P1 P1 P1 P1
U2 U2
I2 U2 I2 U2
U1 I1 U1 I1
U1 I1- I2 U1 I1- I2
P2 S2 P2 S2 P2 S2 P2 S2
Advantage Advantage
Reduction of Magnetic circuit and size Reduction of Magnetic circuit and size
> Cost
=> C t reduction,
d ti ffor th i l t power
the same equivalent > Cost
=> C t reduction,
d ti ffor th i l t power
the same equivalent
Disadvantage Disadvantage
No perfect insulation between primary and secondary winding No perfect insulation between primary and secondary winding
> Overvoltages
=> bet een primary
O er oltages can be transferred between primar and secondar
secondary. > Overvoltages
=> bet een primary
O er oltages can be transferred between primar and secondar
secondary.
Use Use
=> Mainly used when voltages at HV and MV sides are similar => Mainly used when voltages at HV and MV sides are similar
(400 / 225 kV in France and up to 765 kV in other countries (400 / 225 kV in France and up to 765 kV in other countries
TSA TSA
TSA TSA
RPN RPN
HT B ou HT A HT B ou HT A
HT B HT B
225 Kv 225 Kv
HT B HT B
40 HT A 40 HT A
HT A HT A
but but
Transformer faults not cleared Transformer faults not cleared
cause large damage with long cause large damage with long
repair time repair time
Overfluxing
g Protection Overfluxing
g Protection
Surge
g Arrestors Surge
g Arrestors
Effect of Overload on Transformer Insulation Life Effect of Overload on Transformer Insulation Life
Relative rate Relative rate
of using life of using life
100 100
With ambient of 20 C. With ambient of 20 C.
H t spott rise
Hot i off 78 iis H t spott rise
Hot i off 78 iis
design normal. design normal.
A further rise of 6 C A further rise of 6 C
10 d bl rate
doubles t off 10 d bl rate
doubles t off
using life. using life.
1.0 1.0
Trip Trip
I load I load
Alarm Alarm
TD TD
setting setting
On On
Top oil of I load Fan Top oil of I load Fan
power control power control
transformer Off transformer Off
On On
Pump Pump
control control
Off Off
Heater Temp. indication Heater Temp. indication
Local Local
Thermal p
Temperature Remote Thermal p
Temperature Remote
replica sensing resistor replica sensing resistor
Schneider Electric 29 Schneider Electric 29
Ti
Time ((s)) Ti
Time ((s))
t2 t1 t2 t1
Time (s) Time (s)
t1 t1
t2 Thermal withsatnd t2 Thermal withsatnd
Current Current
Schneider Electric IR I1 I2 30 Schneider Electric IR I1 I2 30
Thermal Overload Protection Thermal Overload Protection
Overfluxing Protection Overfluxing Protection
Differential Protection Differential Protection
Phase Overcurrent Protection Phase Overcurrent Protection
Earth Fault Overcurrent Protection Earth Fault Overcurrent Protection
B hh l
Buchholz B hh l
Buchholz
Overfluxing Overfluxing
Definition : overfluxing = excessive magnetic flux = saturation of magnetic circuit Definition : overfluxing = excessive magnetic flux = saturation of magnetic circuit
Application
A li i : High Power Plant Step-up Transformer Application
A li i : High Power Plant Step-up Transformer
Origin : Origin :
Overvoltage situation (ex : loss of an important load in the network) Overvoltage situation (ex : loss of an important load in the network)
Under-frequency situation (ex : generator excitation at low speed when Under-frequency situation (ex : generator excitation at low speed when
start up with AVR in service)
start-up start up with AVR in service)
start-up
Consequences : Consequences :
R R
Correct application
pp of differential protection
p requires
q CT ratio and Correct application
pp of differential protection
p requires
q CT ratio and
winding connections to match those of transformer. winding connections to match those of transformer.
CT secondary circuit should be a “replica” of primary system. CT secondary circuit should be a “replica” of primary system.
Consider : Consider :
(1) Difference in current magnitude (Main Transformer + CT), (1) Difference in current magnitude (Main Transformer + CT),
(2) Phase shift, (2) Phase shift,
(3) Zero sequence currents, caused by an external fault, (3) Zero sequence currents, caused by an external fault,
(4) The influence of the tap changer if any. (4) The influence of the tap changer if any.
Schneider Electric 37 Schneider Electric 37
Differential
ff Protection Application Differential
ff Protection Application
Yd11
d Yd11
d
D 1( 30 )
Dy1(-30 R D 1( 30 )
Dy1(-30 R
R R
R R
Vector and Ratio correction by interposing CT Vector and Ratio correction by interposing CT
Schneider Electric 41 Schneider Electric 41
Vector Group Correction - Static Relays Vector Group Correction - Static Relays
Yd11
d Yd11
d
R R
R R
R R
Vector and Ratio correction by CT Connection Vector and Ratio correction by CT Connection
Schneider Electric 42 Schneider Electric 42
Vector Group Correction - Numerical Relays Vector Group Correction - Numerical Relays
Example Example
Vector Group Correction : Transformer Yd5 (MiCOM P63x algorithm) Vector Group Correction : Transformer Yd5 (MiCOM P63x algorithm)
-I0 -I0
87 87
Vector and Ratio Vector and Ratio Vector and Ratio Vector and Ratio
correction correction correction correction
Zero sequence current compensation Zero sequence current compensation
(stability for external single phase faults) (stability for external single phase faults)
Phase, TC ratio and zero sequence current corrections by Software Phase, TC ratio and zero sequence current corrections by Software
(no added Hardware and no Interposing CTs) (no added Hardware and no Interposing CTs)
Differential
Diff ti l Differential
Diff ti l
Current I1 - I2 Current I1 - I2
OPERATE OPERATE
no
o Trip
p no
o Trip
p
Differential
Diff ti l Differential
Diff ti l
Current I1 - I2 Current I1 - I2
OPERATE OPERATE
no
o Trip
p no
o Trip
p
Differential
Diff ti l Differential
Diff ti l
Current I1 - I2 Current I1 - I2
OPERATE OPERATE
no
o Trip
p no
o Trip
p
current(x In)
current(x In)
Bias characteristic Principe : Bias characteristic Principe :
Operate Operate
• sensibility = Starting element • sensibility = Starting element
Vectoriall somme
Vectoriall somme
Id = | I1 + I2 + I3 + I4 |
Id = | I1 + I2 + I3 + I4 |
2 2
• 1st slope : 30% from 0 up to In_max • 1st slope : 30% from 0 up to In_max
Gives a correct sensitivityy for Gives a correct sensitivityy for
Différentiel
Différentiel
in zone faults up to the max 1 in zone faults up to the max 1
permanent load current Block permanent load current Block
Compensation of errors due to Compensation of errors due to
extreme position of the tap extreme position of the tap
D
0 1 2 3 4 0 1 2 3 4
changer (15%) and CT (5%) changer (15%) and CT (5%)
Bias current (x In) Bias current (x In)
p : 80% after In_max
• 2nd slope _ p : 80% after In_max
• 2nd slope _
Ib = ( I1 + I2 + I3 + I4 ) / 2 Ib = ( I1 + I2 + I3 + I4 ) / 2
insure the stability is case of through fault current insure the stability is case of through fault current
(with CT saturation) Magnitude sum (with CT saturation) Magnitude sum
● Appears on one side of transformer only ● Appears on one side of transformer only
- Can make maloperation of Zero sequence relay at primary - Can make maloperation of Zero sequence relay at primary
Twice Twice
Normal Normal
Flux Flux
Normal Normal
Flux Flux
Normal Normal
No Load Current No Load Current
IR IR
P1 P2 P1 P2
IS S1 S2 IS S1 S2
P1 P2 P1 P2
IT S1 S2 IT S1 S2
P1 P2 P1 P2
S1 S2 S1 S2
IR + IS + IT = 3Io = 0 IR + IS + IT = 3Io = 0
Schneider Electric 54 Schneider Electric 54
Exemple of Transformer Magnetizing curve Exemple of Transformer Magnetizing curve
Autotransformer 275/400 kV 650 MVA (ABB) Autotransformer 275/400 kV 650 MVA (ABB)
Effect of magnetizing
g g current Effect of magnetizing
g g current
Requirements Requirements
● Fast operation for primary short circuits ● Fast operation for primary short circuits
● Discrimination with downstream protections ● Discrimination with downstream protections
● Operation within transformer withstand ● Operation within transformer withstand
● Non-operation for short or long term overloads ● Non-operation for short or long term overloads
● Non-operation for magnetising inrush ● Non-operation for magnetising inrush
HV HV
Source LV Source LV
50 50
51 51
50 set to 1.2 - 1.3 x through fault level 50 set to 1.2 - 1.3 x through fault level
Schneider Electric 61 Schneider Electric 61
Tank protection
p Tank protection
p
Protection will only operate in case of Protection will only operate in case of
Internal earth fault with tank Internal earth fault with tank
=> Network must be solidely grounded => Network must be solidely grounded
Objective : protect the transformer against: Objective : protect the transformer against:
internal insulation faults between windingg and tank internal insulation faults between windingg and tank
Bushing insulation fault (fault not detected by Buccholz relay) Bushing insulation fault (fault not detected by Buccholz relay)
Principle : use of a neutral core CT between tank and ground Principle : use of a neutral core CT between tank and ground
=> in
i case off iinsulation
l ti fault
f lt (at
( t primary
i or secondary
d side),
id ) the
th fault
f lt currentt will
ill => in
i case off iinsulation
l ti fault
f lt (at
( t primary
i or secondary
d side),
id ) the
th fault
f lt currentt will
ill
flow through the earth cable flow through the earth cable
Relay familly : single phase over current relay Relay familly : single phase over current relay
Disadvantage
g : Disadvantage
g :
to incease its sensitivity and selectivity, the tank and all accessories (LV control to incease its sensitivity and selectivity, the tank and all accessories (LV control
box,…) must be isolated from ground (basement with concrete or wood) box,…) must be isolated from ground (basement with concrete or wood)
the relay must not operate for an external earth fault => relay with low the relay must not operate for an external earth fault => relay with low
sensitivity sensitivity
Special Application: when the distance between the transformer and the busbar is Special Application: when the distance between the transformer and the busbar is
very short, using unipolar cables, very short, using unipolar cables,
principle : the cable screen is isolated at one side and connected to the tank at the principle : the cable screen is isolated at one side and connected to the tank at the
other side other side
B B B B
A A A A
IA,a 0 k 1 IA,a 0 k 1
2 k Nb 2 k Nb IY,b 2 k Nb 2 k Nb IY,b
I A, a = I Y, b = k I G/F, max I A, a = I Y, b = k I G/F, max
3 Na 3 Na 3 Na 3 Na
Na Na
and with 1: and with 1:
Nb Nb
2 2 2 2
I A, a = k I G/F, max I A, a = k I G/F, max
3 3
2 Id,G = I Y,b = k IG/F, max 2 Id,G = I Y,b = k IG/F, max
I d = I A, a = k 2 I G/F, max I d = I A, a = k 2 I G/F, max
3 3
B B B B
A A A A
IA,a 0 k 1 IA,a 0 k 1
Na N Na N
I A,b = k I = k a k I G/F, max I A,b = k I = k a k I G/F, max
N b Y, a Nb IY,b N b Y, a Nb IY,b
Na 1 Na 1
and with : and with :
Nb 3 Nb 3
1 1
I A,b = k 2 I G/F, max I A,b = k 2 I G/F, max
3 3
1 1
2 k 2 I G/F, max 2 k 2 I G/F, max
I C,b IB, b 2 I A,b 3 = 2 k2 I I C,b IB, b 2 I A,b 3 = 2 k2 I
Id = = = G/F max
G/F, Y a = k I G/F,
Id,G = I Y, G/F max Id = = = G/F max
G/F, Y a = k I G/F,
Id,G = I Y, G/F max
3 3 3 3 3 3 3 3
1.0 1.0
x
0.9 Star Side x
0.9 Star Side
0.8 0.8
Delta Side Delta Side
0.7 0.7
06
0.6 06
0.6
Phase R Phase R
Overcurrent 0.5 Overcurrent 0.5
0.4 0.4
0.3 0.3
0.2 0.2
01
0.1 01
0.1
p.u.. p.u..
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
1.0 1.0
x
0.9 Star Side x
0.9 Star Side
0.8 0.8
Delta Side Delta Side
0.7 0.7
06
0.6 06
0.6
Phase R Phase R
Overcurrent 0.5 Overcurrent 0.5
0.4 0.4
0.3 0.3
The star Winding fault 0.2 The star Winding fault 0.2
cannot be detected by 01
0.1 cannot be detected by 01
0.1
Phase overcurrent at the p.u.. Phase overcurrent at the p.u..
primary (Delta) side primary (Delta) side
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
1.0 1.0
0.9 0.9
x x
0.8 0.8
Star Side Star Side
0.7 0.7
06
0.6 Delta Side 06
0.6 Delta Side
Phase R Phase R
Overcurrent 0.5 Overcurrent 0.5
0.4 0.4
0.3 0.3
0.2 0.2
01
0.1 01
0.1
p.u.. p.u..
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
1.0 1.0
0.9 0.9
x x
0.8 0.8
Star Side Star Side
0.7 0.7
06
0.6 Delta Side 06
0.6 Delta Side
Phase R Phase R
Overcurrent 0.5 Overcurrent 0.5
0.4 0.4
0.3 0.3
The star Winding fault 0.2 The star Winding fault 0.2
cannot be detected byy 01
0.1 cannot be detected byy 01
0.1
Phase overcurrent at the p.u.. Phase overcurrent at the p.u..
primary (Delta) side primary (Delta) side
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
IF IF
Differential Protection Setting % of Star Winding Protected Differential Protection Setting % of Star Winding Protected
x x
Phase Phase
Overcurrent Overcurrent
Phase Phase
Overcurrent Overcurrent
Phase Phase
Overcurrent Overcurrent
P1 S1 P1 S1
P2 S2 P2 S2
Use of high
g impedance
p earth fault p
principle
p Use of high
g impedance
p earth fault p
principle
p
A B C N A B C N
LV restricted E/F protection trips both HV and LV breaker LV restricted E/F protection trips both HV and LV breaker
Recommended setting : 10% rated Recommended setting : 10% rated
pp
Attention : Not applicable when grounding
g g system
y is earthed pp
Attention : Not applicable when grounding
g g system
y is earthed
76 mm typical 76 mm typical
Transformer Transformer
P t
Petcock
k P t
Petcock
k
Alarm bucket Alarm bucket
To oil To oil
conservat conservat
or or
From From
transformer Trip bucket transformer Trip bucket
Buchholz Relay
y Buchholz Relayy
Bucholz relay tripping inhibited during suitable Bucholz relay tripping inhibited during suitable
period period
CT CT
E E
Shorted Load Shorted Load
turn turn
Nominal turns ratio : 11,000 / 240 Nominal turns ratio : 11,000 / 240
CT CT
E E
Shorted Shorted
turn turn
Nominal turns ratio : 11,000 / 240 Nominal turns ratio : 11,000 / 240
60 60
40 40
20 20
Turn short
short- Turn short
short-
circuited circuited
5 10 15 20 25 5 10 15 20 25
(percentage of (percentage of
Schneider Electric Schneider Electric
winding) 93
winding) 93
Interturn Fault Current / Number of Interturn Fault Current / Number of
Turns Short Circuited Turns Short Circuited
Primary current Primary current
(multiples of (multiples of
rated current) rated current)
100 100
20 20
Primary phase current very low Primary phase current very low
5 10 15 20 25
Not detected by 5 10 15 20 25
Not detected by
Schneider Electric
current operated 94 Schneider Electric
current operated 94
relays relays
Details of transformer protections and constraints Details of transformer protections and constraints
Conclusion – Typical
yp schemes Conclusion – Typical
yp schemes
51 50 51 50
200/5 51 50 N N 200/5 51 50 N N
1MVA 1MVA
1500/5 1500/5
3.3/0.44kV 3.3/0.44kV
51 51
N N
64 1500/5 64 1500/5
1 - 5MVA 1 - 5MVA
11kV 11kV
51 50 P121 51 50 P121
64 64
5MVA 5MVA
1000/5 1000/5
11/3.3kV 11/3.3kV
51 51
N N
64 1000/5 64 1000/5
Schneider Electric
3.3kV 97 Schneider Electric
3.3kV 97
Above 5MVA Above 5MVA
Phase faults : case study with Phase faults : case study with
overcurrent relays
y overcurrent relays
y
Setting criteria : Setting criteria :
Radial transformer Coordination
C di ti b between
t primary
i and
d Radial transformer Coordination
C di ti b between
t primary
i and
d
secondary faults secondary faults
insensibility to inrush current insensibility to inrush current
PROTECTION TRANSFORMATEUR - CRITERES DE REGLAGES & SELECTIVITE PROTECTION TRANSFORMATEUR - CRITERES DE REGLAGES & SELECTIVITE
100
IEC extremely inverse 100
IEC extremely inverse
t (en s)
Tenue thermique transformateur Tenue thermique transformateur
1 1
Icc tri D1 Icc tri D1
Icc bi D1 Icc bi D1
Icc tri D2 Icc tri D2
Icc bi D2 Icc bi D2
0.1 0.1
In transformateur In transformateur
Nominal apparent power of the transformer Nominal apparent power of the transformer
Inrush Current Inrush Current
Advantage : Low cost solution (no circuit breaker) Advantage : Low cost solution (no circuit breaker)
Disadvantage : Disadvantage :
tripping characteristic must not operate for inrush current => high set tripping characteristic must not operate for inrush current => high set
no overload protection no overload protection
not sensible to resistant faults occuring at secondary side (common for LV not sensible to resistant faults occuring at secondary side (common for LV
sides) sides)
selectivity with upstream relay = high set overcurrent setting on the upstream selectivity with upstream relay = high set overcurrent setting on the upstream
relay relay
Full load Rated Operating time at Full load Rated Operating time at
kVA kVA
current (A) current (A) 3 x rating(s) current (A) current (A) 3 x rating(s)