Grease Installation&Maintenance
Grease Installation&Maintenance
Grease Installation&Maintenance
The policy contained herein describes specific policy information and purchaser
requirements for grease interceptors. Other Jensen Precast company policies, including
shipping, terms and conditions, ordering instructions, and others also apply. Contact
Jensen Precast for complete information.
In general, Jensen Precast provides delivery and setting of the interceptor and sealing
of the tank components in accordance with the provisions of this policy. In a situation
where our truck cranes cannot set the tank(s) for whatever reason, we will provide a
representative to supervise in the proper setting of the interceptor and then seal the
components as specified herein.
Jensen Precast accepts responsibility for proper setting, assembly, and sealing of the
tank when installed or supervised by Jensen Precast or an authorized representative. A
A grease interceptor handled, moved, or installed without Jensen Precast supervision,
nullifies the responsibility of Jensen Precast.
The grease interceptor must be set on a properly prepared base to insure against
movement of either the tank or the inlet and outlet lines. The excavation shall be the
proper width and length to accept the model selected and shall have enough extra width
and length to allow for safe installation and sealing of the components. Suitable native
soil or sub-base shall be prepared to handle anticipated loads.The excavation shall be
bedded with suitable granular material and shall be compacted to 90% maximum dry
density, or to the requirements of the project geotechnical engineer. The bottom of the
excavation shall be graded level.
On battery tank systems with capacities in excess of 5,000 gallons, redwood grade
boards shall be used to insure a level and stable tank joint. A minimum of two 2" x 6"
grade boards, laid flat, running the full length of the main tank directly under the outside
walls shall be used. The top of compacted fill material shall match top of redwood grade
boards prior to setting the tank(s).
The owner, customer, contractor, or others shall be responsible for the following:
5. Completing the entire installation and all other site work not specified herein.
Jensen Precast requires assistance from the customer or contractor in setting, sealing,
and placing the tank (generally one or two laborers). Access and setting location for our
boom truck or other equipment must be acceptable to our driver or representative.
Tanks 4000 gallons and larger require extreme caution due to the weight of the product.
There may be situations where an outside crane may be needed to set the product.
Contact Jensen Precast for details.
Since site conditions, products, and delivery equipment vary tremendously, the logistics
must be carefully considered to determine the best possible approach for setting,
including but not limited to:
1. The capacity of the Jensen Precast boom truck (truck crane) to be used.
2. The maximum product weight relative to the setting distance from the center
of the crane to the center of the excavation which cannot exceed our truck
crane's rated capacity.
3. The type of terrain, site slope, and ground conditions for outrigger footing.
ANY of the above could prevent Jensen Precast from setting the interceptor.
NOTE: If for any reason Jensen Precast cannot set the interceptor, Jensen
Precast will not be responsible or charged for setting by any other means.
The owner, customer, contractor, or others shall be responsible for the following:
2. Grouting, sealing, setting and adjusting of grade rings, risers, frames, covers, and all
other hardware and appurtenances.
12/11/2003 2
4. Sealing above the top of the tank.
Any and all permits, licenses, tests, or approvals from any administrative authority, etc.
that are required for installation of the grease interceptor.
VENTILATION
The grease interceptor is vented as prescribed by the Uniform Plumbing Code (UPC)
unless local regulations supercede. The tank is provided with inlet & outlet tee’s which
allow gases to escape the tank atmosphere into the building plumbing / ventilation
system. Failure to provide proper ventilation for the tank could result in an odor problem
or in extreme cases siphoning into the sewer. Please consult the Uniform Plumbing
Code and local regualtions for additional information.
Jensen Precast will seal the tank only. The tank must be dry in order for the sealant to
bond properly to the concrete. Once applied, the sealant must cure for a period of 24
hours before water testing. Jensen Precast is not resonsible for grouting or sealing of
grade rings, risers, frames, and covers.
The tank must be tested to insure that the system as a whole is watertight. Watertight
testing must be completed and approved after installation, but before the tank is put into
service. All tanks of 2000 gallon capacity or greater and all battery tanks must be
backfilled to the outlet pipe when water testing to levels up to the underside of the top
slab. Backfilling is required on the larger tanks to support sidewalls. Warning: Water
testing tanks with a liquid capacity of 2000 gallons or greater without backfilling
could result in structural damage. If water testing above the top of any tank is
required, please contact Jensen Precast.
WATER TESTING
Jensen Precast’s standard tanks are designed to be watertight below the liquid
operational level (invert of outlet pipe). The tank shall be filled to the operational liquid
level with water and allowed to stand to achieve complete concrete absorption, then
refilled to the same level. Once refilled, there shall be no measurable liquid loss in the
following hour. (Ref. ASTM C-1227-02b 9.2.2) For areas requiring prevention of
infiltration above the operational level, a tank with a sealed lid is required. Contact
Jensen Precast for more details.
The owner, customer, contractor, or others shall be solely responsible for the following:
12/11/2003 3
2. Providing water and means to pump or evacuate water for testing or any
subsequent retesting.
Warning: Water tests conducted above the lid of the tank may have structrual
implications. Any water test conducted 2 feet above the top slab of the tank
could exceed the structural design of the tank. Contact Jensen Precast for
complete details.
VACUUM TESTING
Seal the empty tank and apply a vacuum of 4 in. (100 mm) of mercury. Hold the
vacuum for 2 minutes. There should be no more than a 10% loss in vacuum at the end
of 2 minutes. (Ref ASTM C-1227-02b 9.2.1)
The owner, customer, contractor, or others shall be responsible for the following:
PRE-TEST INSPECTION
Before any applicable tests are performed and before the tank is placed into service, a
visual inspection is to be performed to insure that the tank is free of trash and debris
that could prevent the tank from functioning properly. All foreign objects such as rocks,
trash, tools, construction materials, etc left inside the tank from the installation process
should be removed at this time.
12/11/2003 4
PRECAUTIONARY NOTE
Interceptors, utility vaults, manholes, septic tanks, and other similar type enclosures are
confined spaces and entry is not recommended as the atmosphere may be hazardous.
If entry is necessary, enter only with the proper equipment and follow O.S.H.A. confined
space entry procedures.
Jensen Precast recommends that all applicable O.S.H.A. recommendations are read
and followed, including the current section on confined spaces and “Permit Required
Confined Space”.
This warning is presented for precautionary safety advise only. Owners, users,
installers, contractors, etc. are responsible for safety on the job and O.S.H.A.
compliance.
ACCEPTANCE
Jensen Precast's reponsibility for the grease interceptor installation and sealing shall be
considered finished and accepted once any of the following occurs:
BACKFILLING
Failure to comply with proper backfill procedures could result in structural damage or
leakage from pipe connections, or tank, due to settling, point loading, inpacting, etc.
Backfill shall be suitable material and shall be laid in lifts and adequately compacted
from bottom to top to prevent movement or settling under the pipe or fittings.
12/11/2003 5
JENSEN PRECAST GREASE INTERCEPTOR OPERATION AND MAINTENANCE
Disposal of Intercepted Materials: Grease and other waste matter that has been
removed from the interceptor should not be introduced into any drain, sewer, stormdrain
or natural body of water. All material should be disposed of according to local
regulations. Contact your city official for information.
12/11/2003 6
12/11/2003 7