We 6 RFP 050
We 6 RFP 050
the underground water level is at about 95 m above the vertical rods under the first and third ring and 12 vertical
sea level, which is about 15 m below the TPS designed rods under the inner ring. In the present design, all of the
floor level. The corresponding pH value is about 7.1 and vertical rods are 30 m long. There is possibility to use 15
the chloride ion density is about 2.2 ~ 15.3 mg/L. It m vertical rods under the third ring. As for the second ring,
should not have erosive and worsening effects on the beside 2 vertical rods for the extracting and injecting
electrodes. kickers, there is no other vertical ground electrode. The
electrodes in the outside ring are mainly for the
DESIGN OF GROUND GRID equipments in the beam-lines and laboratories. The
second ring is for the equipments in the accelerator tunnel.
Estimation of Soil Resistivity The third ring is for the control and instrumentation areas,
In order to calculate the resistance of ground grid, the and the inner ring is for other equipments which are used
soil resistivity at the construction site is essential. The to accelerate the electron beam inside the accelerator.
soil resistivity can not be determined easily due to the There will be also a ground grid under the new utility
complexity of the formation of earth strata. The soil building. The design of its ground grid is a simple
boring log at the construction site from the previous rectangular horizontal type (7×6) with 3 m vertical rods
geological exploration, Fig. 2, can be used to estimate the under the horizontal grid.
soil resistivity. At the same time, the resistivity image
profiling of direct current electrical resistance has been
done at the construction site, Fig. 3. After carefully
investigating the data, we estimate that 15 m under the
surface the resistivity is mostly at between 100 Ω⋅m and
300 Ω⋅m, with some local areas having higher resistivity
up to 500 Ω⋅m. The resistivity at depth between 15 m and
30 m below the TPS floor is estimated between 50 Ω⋅m
and 100 Ω⋅m. Since there is underground water 15 m
below the TPS floor, we would estimate the soil
resistivity is around 70 Ω⋅m or lower.
about 1.2 Ω. The ground resistance of TPS ground grid is Further Improvements
about 0.21 Ω. These two ground grid will be combined The ground resistance reduction agents have been
together to give a total ground resistance about 0.19 Ω, proven to be able to decrease the ground resistance. It has
Fig. 5a and 5b. This result will meet our designed goal. the function to increase the diameter of electrode by
From the geological consideration, the underground water modifying the soil surrounding the electrode. In 2002 the
may further reduce the lower level resistivity to lower improvement of ground grid of TLS was to add nine 30 m
than 80 Ω. In this situation, we will expect that the value vertical electrodes around the TLS building and add
of ground resistance becomes even lower. Besides bentonite as ground enhancement material. It decreases
obtaining a lower than 0.2 Ω ground resistance, the guide the TLS ground resistance to about 0.2 Ω. During the
line described in the “IEEE Std 80-2000” [3] are followed installation of TPS ground grid, we also intend to add
in the design of the TPS ground grid. ground enhancement material with resistivity lower than
0.2 Ω⋅m to further reduce the ground resistance. Also, at
least 12 chemical ground electrodes with length 30 m will
be used for the vertical electrodes to improve the
performance of TPS ground grid.
CONCLUSION
The TPS grounding system is being designed to have a
ground resistance lower than 0.2 Ω. Our design principle
is to follow the guidelines described in “IEEE Std 80-
2000”. Beside the general function of providing the safety
to the personnel during normal and fault conditions, it
assures correct operation of electrical and electronic
devices and also to prevent their damages. Some other
effects which relate to the electromagnetic interference
are also been studied in hopes of minimizing this type of
Figure 5a: The TPS ground grid design used in the
problems.
computer simulation. The rectangular grid is for the new
utility building and the circular one is for the TPS
building. ACKNOWLEDGEMENT
The authors are appreciated the assistance of members
of the Construction Management Group to provide the
information about the site geological exploration data.
Special thanks should give to J. C. Hsu for his
explanation of the geological data and also providing a lot
of geological information.
REFERENCES
[1] NSRRC and China Engineering Consultant Inc.,
“Technology Services of Site Geology Exploration
and Micro-vibration Measurement”, (Dec. 2005).
[2] CYMGrd 6.3, rev. 7, CYME International T&D Inc.
(2006) .
[3] IEEE Std 80-2000.