Design Calculation - STP
Design Calculation - STP
1.16912510328913
-0.198
0.005175912924258
d2' 1.29103693242854 m
V2' 0.550 m/s
Headloss through 50% clogged Screen 0.134 m OK
Total Width of Screen Chamber 2.5 m
Total Depth of Screen Chamber 1.700 m
Screen Chamber Dimensions W: 2.5 m D: 1.7 m
Grit Chamber
No. of Grit Chamber 4 No.
Particle size to be removed 0.15 mm
Specific Gravity of Particle 2.65
Temperature 15 Degree
Kinematic viscosity 1.14E-06 m2/s
Applying Stoke's law, Settling velocity Vs 0.018 m/s
Check for Reyold's Number R 2.34
Settling Velocity 0.0168 m/s
Surface Overflow Rate (SOR) 0.0168 m/s
1451.68 m3/m2/day
Assumed Efficiency of grit Chamber 75.00%
Measure of settling performace,n 0.125
Actual Surface Overflow Rate 959.05 m3/m2/day
Plan Area 156.4 m2
Area of each grit chamber 39.1 m2
Length to Width ratio 4
Length 12.8 m
Width 3.2 m
Water Depth 1.1 m
Total Depth of grit Chamber 1.6 m
Grit Chmaber Dimensions L: 12.8 m W: 3.2 m D: 1.6 m
Detention Period at Average Flow 103.81 sec
Critical displacement Velocity Vc 0.16 m/s k 0.04
Horizontal Velocity Vh 0.12 m/s f 0.03
Design of Prpoportional Weir
Peak Flow through each werir 0.43402777778 m3/s
Base width of weir 0.80 m C 0.61
a 35
Assuming values of y, x y x
0.035 0.4
0.35 2.18278336758184
0.7 0.3062290659286
1.05 0.6024859631659
Parshall Flume
Peak Design Flow 1736.111 lps
Discharge through Parshall Flume Q 1736.111 lps
Throat Width W 0.3 m
Channel at D 0.831 m
Liquid Depth at low Flow 1.869476 m
Liquid Depth at high flow m
Velocity at mouth, low flow 1.117523 m
Velocity at mouth, high flow m
Approach channel, liquid depth 1.869476 m
Approach channel width 0.831 m
Approach channel liquid depth m
width of throat 0.3 m
Complete Mix Activated Sludge Process
Aeration Tank Inlet Parameters
Inlet BOD mg/L BOD 140
Thickener Overflow return MLD sBOD 70
Thickener overflow BOD mg/L COD 300
Centrate from dewatering unit Flow MLD sCOD 132
Centrate from dewatering unit BOD mg/L TSS 70
Influent BOD to aeration Tank 140 mg/L VSS 60
Y 0.4 g VSS/g bCOD TKN 35
µm 3.5 g VSS/g VSS.d NH4-N 25
Kd 0.088 g VSS/g VSS.d TP 6
SRT 5 day bCOD/BOD 1.6
fd 0.15 bCOD 266
Px,vss 3911.73 kg VSS/day nbCOD 34
Px,tss 6102.03 kg TSS/day sCODe 20
Mass of MLSS 30510.16 kg nbVSS 20
Mass of MLVSS 24558.64 kg iTSS 10
Assume Aeration tank MLSS 3000 mg/L S 1.793275
Volume of Aeration tank 10170.0536 m3 Ks 20
Aeration Tank Detention Time 4.88 hrs
MLVSS/MLSS Ratio 0.8
MLVSS 2400 mg/L Outlet Parameters
F/M 0.287 kg/kg-day BOD 10
Volumetric BOD loading 0.69 kg/m3/day COD 50
No. of Aeration Tank 2 No. TSS 10
Volume of Aeration tank 5085.03 m3 TKN 5
Liquid Depth 6.5 m TP 2
Width to Depth Ratio 2
Width 13 m
Area Required 782.312 m2
Length 60.18 m
Dimensions L: 60.18m W: 13m D: 6.5m
Sludge Calculations
Specific Yield 0.61 kg/kg BOD removed
BOD removed 6500 kg/day
Total sludge Generated 3965 kg/day
t Parameters
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
g bCOD/m3
et Parameters
mg/L
mg/L
mg/L
mg/L
mg/L
Extended Aeration
µn
Design of Clarifier
Return sludge Mass concentration, Xr 8000 mg/L
Recycle Ration, R 0.6
Hydraulic Application Rate 22 m3/m2/day
Area Required 2272.727272727 m2
No. of Clarifier 4 Nos
Area of each clarifier 568.1818181818 m2
Dia of Clarifier 27.00 m
Solid Loading Rate 104.8465308904 kg MLSS/m2/hr
Depth of Clarifier 4m
Weir Loading Rate 98.29362270976
Dimensions Dia: 27m Depth: 4 m
Chlorine Contact Tank
Contact Time 30 min
Volume required 1041.667 m3
No. of Chlorination Channels No.
Volume of each channel m3
mg/L
dosage 10 min
Detention time 30
L/W 40
Gravity Thickener
Air Requirement
No. of Tanks 1 No.
A Volume of Sewage Treated 50000 m3/day
B Theoretical kg O2 required per kg BOD 1.2
C Inlet BOD 250 mg/L
D Outlet BOD 10 mg/L
E BOD removed 240 mg/L
F kg of BOD removed in a day 12000 kg/day
G kg O2 required for BOD load 14400 kg/day
H Inlet Kjealdahl Nitrogen 30 mg/L
I Outlet Ammonical Nitrogen 5 mg/L