The Productivity From Week 3 To Week 4 Increased by 10%

The document provides productivity data for 4 weeks including output, workers, material used, and calculates total cost and productivity for each week. Productivity is measured as output per 40 hours. From week 3 to week 4: - Output increased from 50,000 to 55,000 units - Workers and hours remained the same at 6 workers working 40 hours - Material used increased slightly from 480 to 500 lbs - Productivity increased from 1,250 to 1,375 units per 40 hours, a 10% increase.

Uploaded by

Rain Dayrit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views2 pages

The Productivity From Week 3 To Week 4 Increased by 10%

The document provides productivity data for 4 weeks including output, workers, material used, and calculates total cost and productivity for each week. Productivity is measured as output per 40 hours. From week 3 to week 4: - Output increased from 50,000 to 55,000 units - Workers and hours remained the same at 6 workers working 40 hours - Material used increased slightly from 480 to 500 lbs - Productivity increased from 1,250 to 1,375 units per 40 hours, a 10% increase.

Uploaded by

Rain Dayrit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PRODUCTIVITY ASSIGNMENT

Compute the multifactor productivity measure for each of the weeks shown. Assume 40-hour
weeks and hourly wages of Php 50. Overhead is 1.2 times weekly labor cost. Material cost is Php
300 per pound.

Week Output (units) Workers Material (lbs)

1 40000 5 420

2 45000 6 490

3 50000 6 480

4 55000 6 500

Answer here--------

Week Output Labor Material Overhead Total Cost Productivity


Cost Cost Cost

1 40 000 10 000 126 000 12 000 148 000 0.27

2 45 000 12 000 147 000 14 400 173 400 0.26

3 50 000 12 000 144 000 14 400 170 400 0.29

4 55 000 12 000 150 000 14 400 176 400 0.31

1. How much is the increase or decrease in productivity from week 3 to 4?


____________________________________

Week 3 = 50 000 ÷ 40 = 1 250

Week 4 = 55 000 ÷ 40 = 1 375

Change in productivity = [(1 375–1 250) ÷ 1 250] x 100 = 10%

The productivity from Week 3 to Week 4 increased by 10%.