0% found this document useful (0 votes)
45 views1 page

Tuto 8

The document contains two problems. The first problem asks to calculate the total time, speedup factor, efficiency, and instruction throughput for a 15-stage pipeline CPU executing 75 instructions. The second problem asks to write efficient ARM assembly code to compute a value z based on values of x, y, and conditions on x.

Uploaded by

rosestrikes
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views1 page

Tuto 8

The document contains two problems. The first problem asks to calculate the total time, speedup factor, efficiency, and instruction throughput for a 15-stage pipeline CPU executing 75 instructions. The second problem asks to write efficient ARM assembly code to compute a value z based on values of x, y, and conditions on x.

Uploaded by

rosestrikes
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Tutorial 8

[1]. Consider 15-stage pipeline CPU having delay of 3ns per stage. (a) Calculate total time to execute 75
instructions by this pipeline CPU. Calculate Speed up factor, Efficiency and Instruction throughput
(inst./ns and inst./clock) neglect latch delay.

[2]. Write an efficient ARM assembly code to compute following where x,y and z are signed numbers.
Assume that x and y are available in registers R0 and R1 and z is to be stored in R2.
if (x < 11 ) z = x + (y/64);
else if (x= =11) z = z – (y*4);
else z = (32* y) – x ;

Ans 1:
No. of stages k=15
Number of instructions n=75
Pipe line clock period tc=3 ns
(a) It will require (15+74) clock cycle to execute 75 instructions in pipeline CPU
Total time in pipeline CPU is Tk= 89 tc => Tk= 267 ns
(b) Speed up factor Sk= Total time in Non-pipeline / Total time in pipeline
= n k tc / [k+(n-1) tc] = 3375/267 = 12.64
- Efficiency Ek = Sk /k => Ek = 0.84
- Instruction throughput of pipeline Hk = n/ Tk => Hk=0.28 inst/ns
Hk= 0.28 inst./ns = 0.84 inst./3ns = 0.84 inst./clock

Ans 2:

CMP R0, #11


ADDLT R2, R0, R1 LSR #6 ; z = x+ y/64
SUBEQ R2, R2, R1 LSL #2 ;z= z- (y*4)
RSBGT R2, R0, R1 LSL #5 ;z=32y-x