0% found this document useful (0 votes)
236 views4 pages

Assignment Earned Value Analysis

Project earned value analysis measures the health of a project by comparing planned costs and schedule to actual costs and work completed. It provides metrics like cost variance, schedule variance, and performance indexes to indicate if a project is on budget and on schedule. The example project is significantly behind schedule based on its average performance index being below 1.

Uploaded by

Ali Mustafa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
236 views4 pages

Assignment Earned Value Analysis

Project earned value analysis measures the health of a project by comparing planned costs and schedule to actual costs and work completed. It provides metrics like cost variance, schedule variance, and performance indexes to indicate if a project is on budget and on schedule. The example project is significantly behind schedule based on its average performance index being below 1.

Uploaded by

Ali Mustafa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Definitions

Project Earned Value Analysis


Project Earned Value Analysis measures the health of a project by looking at cost information and schedule information concurrently. It tells you whether the project is
on schedule and on budget, as well as whether the project is on budget for the amount of work done so far.

Metric Abbrev. Description Formula/Value


Budget at Completion BAC Baseline cost for 100% of project. N/A
Actual Cost AC Total costs actually incurred so far. N/A
Amount of budget earned so far based on physical work
Earned Value EV accomplished, without reference to actual costs. N/A
The budget for the physical work scheduled to be completed by
Planned Value PV the end of the time period. N/A
Measure of cost overrun. The difference between the budget for Earned Value–Actual Cost
Cost Variance CV the work actually done so far and the actual costs so far. EV–AC
Earned Value/
Cost efficiency ratio. A CPI of 1.00 means that the costs so far Actual Cost
Cost Performance Index CPI are exactly the same as the budget for work actually done so far. EV/AC
Measure of schedule slippage. The difference between the
budget for the work actually done so far and the budgeted cost Earned Value–Planned Value
Schedule Variance SV of work scheduled. EV–PV
The schedule efficiency ratio. An SPI of 1.0 means that the Earned Value/Planned Value
Schedule Performance Index SPI project is exactly on schedule. EV/PV
Estimate at Completion–Actual Cost
Estimate to Completion ETC The expected additional cost to complete. EAC–AC
Budget at Completion/Cost Performance
Index
Estimate at Completion EAC Expected total cost based on the current cost efficiency ratio. BAC/CPI
Budget at Completion–Estimate at
Completion
Variance at Completion VAC Estimated cost overrun at the end of project. BAC–EAC
(Cost Performance Index+Schedule
Performance Index)/2
Status Average of CPI & SPI. (CPI+SPI)/2
GREEN = On track >1.0
YELLOW = Slightly behind schedule or budget >0.85
RED = Needs immediate attention >0.65
BLACK = Killed or Restore <0.65

Page 1 of 4
Source Data

Project Earned Value Analysis


Software Application Development Project
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Budget at Completion (BAC) $1,230 $1,230 $1,230 $1,230 $1,400 $1,400 $1,400 $1,400 $1,400 $1,400
Earned Value (EV) $150 $200 $300 $450 $725 $800 $1,125 $1,200 $1,400 $1,400
Actual Cost (AC) $150 $215 $350 $600 $800 $950 $1,200 $1,350 $1,475 $1,525
Planned Value (PV) $150 $230 $400 $500 $700 $925 $1,150 $1,300 $1,425 $1,500
Cost Variance (CV)
Schedule Variance (SV)
Cost Performance Index (CPI)
Schedule Performance Index (SPI)
Estimate to Completion (ETC)
Estimate at Completion (EAC)
Variance at Completion (VAC)
Average Index 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Status based on Average Performance
BLACK BLACK BLACK BLACK BLACK BLACK BLACK BLACK BLACK BLACK
Index
Comments

Page 2 of 4
Trend Analysis

Earned Value Analysis

$1,800
$1,600
$ (000)

$1,400
$1,200
$1,000
$800
$600
$400
$200
$0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Period

Budget at Completion (BAC) Actual Cost (AC)


Earned Value (EV) Planned Value (PV)

Performance Index

9.60
Efficiency

8.90
8.20
7.50
6.80
6.10
5.40
4.70
4.00
3.30
2.60
1.90
1.20
0.50
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Period

Cost Performance Index (CPI) Schedule Performance Index (SPI)

Page 3 of 4
Trend Analysis

Variance Analysis

$12

$10
$ (000)

$8

$6

$4

$2

$0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Period

Cost Variance (CV) Schedule Variance (SV) Variance at Completion (VAC)

Estimate at Completion
$1,500

$1,400
$(000)

$1,300

$1,200

$1,100

$1,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct

Period

Budget at Completion (BAC) Estimate at Completion (EAC)

Page 4 of 4

You might also like