Work Inspection Request (Wir) : LB2 GRC Corridor Fabricated Additional Column Material Inspection & Release For Erection

This document contains two work inspection requests for the Midfield Terminal Building project at Abu Dhabi International Airport. The first WIR is for inspecting fabricated additional column material to check for compliance before erection. The second WIR is for inspecting drilled hole depths in the GRC Corridor. Both inspections are scheduled for January 17, 2016 and involve verifying that the work meets specifications and approved drawings. The contractor and engineer will sign off on the inspections.

Uploaded by

Rejoy Baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views2 pages

Work Inspection Request (Wir) : LB2 GRC Corridor Fabricated Additional Column Material Inspection & Release For Erection

This document contains two work inspection requests for the Midfield Terminal Building project at Abu Dhabi International Airport. The first WIR is for inspecting fabricated additional column material to check for compliance before erection. The second WIR is for inspecting drilled hole depths in the GRC Corridor. Both inspections are scheduled for January 17, 2016 and involve verifying that the work meets specifications and approved drawings. The contractor and engineer will sign off on the inspections.

Uploaded by

Rejoy Baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

TAV-CCC-ARABTEC JOINT VENTURE

MIDFIELD TERMINAL BUILDING, ABU DHABI INTERNATIONAL


AIRPORT PROJECT

WORK INSPECTION REQUEST (WIR)


PROJECT DOC. NO. : FM-CQCP-1093-001-05-ATTACHMENT 05 REV NO : 03 PAGE NO: 1 of 1

Contract No. AUH.06.10.0401

DETAILS OF SCHEDULED INSPECTION BY CONTRACTOR'S CONSTRUCTION Section A


TO : ENGINEER AECOM DISCIPLINE /SUB:______ Material Inspection WIR NO. MTB/QFAB/WIR/02
SPEC./DRWG. REF:________401-JV-S-05-B2-5.00-ST-LD-002 REV 00______INSPECTION SCHEDULED TIME : 17/1/2016 REV. NO. : 0

LOCATION :_________________________________ LEVEL: FROM LB2 TO_LB2 DATE:17/1/2016

INITIAL INSPECTION ☒ FINAL INSPECTION GRID LINES


ITP NO. :MTB/Qfab/ITP/01 SYSTEM: X AXIS Y AXIS
FORM NO. : SUB-SYSTEM: K7 TO K 13 PA TO PH

DESCRIPTION LB2 GRC Corridor Fabricated Additional Column material Inspection & Release For erection
( Item No: 64,66,65,67,68,69,63,111,113,50,14,19,108106,109,110,105,22,23,26,27,29,21,20,24,28,30,135,133,132,3,4,5,6,8
,9,91,92,90,D,J,A,L,F,C)

SITE ENGINEER: SIGNATURE:

CONFIRMATION OF CONTRACTOR'S QC INSPECTION Section B


CONFIRMATION OF CO-ORDINATION & COMPLIANCE WITH SPECIFICATION /SHOP DRAWING (S)

TICK BOX YES NO NOTE : IF NO, ANY DEVIATION FROM SPECIFICATION(S),APPROVED DRAWING(S) TO BE RECORDED BELOW.

NON-CONFORMITY AND/OR REFERENCE OF ATTACHED NON-CONFORMANCE REPORT DATE : _____________


(NCR):_______________________________

CONTRACTOR QC : ____
Rejoy Baby DATE : _____________ TIME: ______________

ENGINEER'S COMMENTS Section C

DISCIPLINE CIVIL ARCH. STRUCTURAL STEEL MEP/ELECT. MEP/MECH. MEP/SPEC.SYST.

STATUS CODE 1 2 3 4 5 6
1-No Exception Taken 2-Exceptions as Noted; Revise & Resubmit for Record 3-Revise and Resubmit
4-Rejected 5-Review Not Required 6-Issued for Construction

THE ENGINEER'S COMMENTS SHALL NOT RELIEVE THE CONTRACTOR OF ANY OF HIS RESPONSIBILITIES UNDER THE CONTRACT .

ENGINEER NAME :________________________________ SIGNATURE:

DATE : ________________ COPY TO EMPLOYER'S REPRESENTATIVE :

ADAC Form ID-PD-DC-F-006-R1


TAV-CCC-ARABTEC JOINT VENTURE

MIDFIELD TERMINAL BUILDING, ABU DHABI INTERNATIONAL


AIRPORT PROJECT

WORK INSPECTION REQUEST (WIR)


PROJECT DOC. NO. : FM-CQCP-1093-001-05-ATTACHMENT 05 REV NO : 03 PAGE NO: 1 of 1

Contract No. AUH.06.10.0401

DETAILS OF SCHEDULED INSPECTION BY CONTRACTOR'S CONSTRUCTION Section A


TO : ENGINEER AECOM DISCIPLINE /SUB:______ Drilled Hole Depth Checking WIR NO. MTB/QFAB/WIR/01
SPEC./DRWG. REF:401-JV-S-05-B2-5.00-ST-LD-001 to 004 REV 00 INSPECTION SCHEDULED TIME : 17/1/2016 REV. NO. : 0

LOCATION : GRC CORRIDOR LEVEL: FROM LB2 TO_LB2 DATE:17/1/2016

INITIAL INSPECTION ☒ FINAL INSPECTION GRID LINES


ITP NO. :MTB/Qfab/ITP/01 SYSTEM: X AXIS Y AXIS
FORM NO. : SUB-SYSTEM: K7 TO K 13 PA TO PH

DESCRIPTION LB2 GRC Corridor Drilled Hole Depth Checking Inspection

SITE ENGINEER: SIGNATURE:

CONFIRMATION OF CONTRACTOR'S QC INSPECTION Section B


CONFIRMATION OF CO-ORDINATION & COMPLIANCE WITH SPECIFICATION /SHOP DRAWING (S)

TICK BOX YES NO NOTE : IF NO, ANY DEVIATION FROM SPECIFICATION(S),APPROVED DRAWING(S) TO BE RECORDED BELOW.

NON-CONFORMITY AND/OR REFERENCE OF ATTACHED NON-CONFORMANCE REPORT DATE : _____________


(NCR):_______________________________

CONTRACTOR QC : ____
Rejoy Baby DATE : _____________ TIME: ______________

ENGINEER'S COMMENTS Section C

DISCIPLINE CIVIL ARCH. STRUCTURAL STEEL MEP/ELECT. MEP/MECH. MEP/SPEC.SYST.

STATUS CODE 1 2 3 4 5 6
1-No Exception Taken 2-Exceptions as Noted; Revise & Resubmit for Record 3-Revise and Resubmit
4-Rejected 5-Review Not Required 6-Issued for Construction

THE ENGINEER'S COMMENTS SHALL NOT RELIEVE THE CONTRACTOR OF ANY OF HIS RESPONSIBILITIES UNDER THE CONTRACT .

ENGINEER NAME :________________________________ SIGNATURE:

DATE : ________________ COPY TO EMPLOYER'S REPRESENTATIVE :

ADAC Form ID-PD-DC-F-006-R1