Change Order Procedure (Project Standards and Specifications)

This document outlines KLM Technology Group's change order procedure for construction projects. It defines key terms like field instruction request, field instruction, change order proposal, and change order. It describes the process for requesting, evaluating, and approving changes through these documents. Contractors are responsible for issuing field instruction requests and change order proposals, while the company is responsible for reviewing and approving or rejecting the requests. The appendices provide template forms for the various change-related documents.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
132 views4 pages

Change Order Procedure (Project Standards and Specifications)

This document outlines KLM Technology Group's change order procedure for construction projects. It defines key terms like field instruction request, field instruction, change order proposal, and change order. It describes the process for requesting, evaluating, and approving changes through these documents. Contractors are responsible for issuing field instruction requests and change order proposals, while the company is responsible for reviewing and approving or rejecting the requests. The appendices provide template forms for the various change-related documents.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Page : 1 of 16

KLM Technology
Group Rev: 01

Project Engineering
Standard
July 2013
www.klmtechgroup.com

KLM Technology Group


#03-12 Block Aronia, CHANGE ORDER PROCEDURE
Jalan Sri Perkasa 2
Taman Tampoi Utama
81200 Johor Bahru (PROJECT STANDARDS AND SPECIFICATIONS)
Malaysia

TABLE OF CONTENT

SCOPE 2

DEFINITIONS 2

PROCEDURES 2

SPECIAL REQUIREMENTS 7

RECORDS 7

APPENDICES 8

Appendix I Field Instruction Request 9

Appendix II Field Instruction 10

Appendix III Change Order Proposal 11

Appendix IV Cost Estimation Sheet 12

Appendix V Change Order 13

Appendix VI Change Order Register 16


Page 2 of 16

KLM Technology
CHANGE ORDER PROCEDURE
Rev: 01
Group
Project Engineering Standard
(PROJECT STANDARDS AND
July 2013
SPECIFICATIONS)

SCOPE

This Project Standards and Specifications cover the basic requirements for handling
all changes in the CONTRACT. This procedure addresses the basic requirements for
processing changes to the CONTRACT that may affect the cost or the time required to
complete the project either due to addition or deletion lo the WORKS.

DEFINITION

FIR - field Instruction Request


Fl - Field Instruction
COP - Change Order Proposal
CO - Change Order
WORKS - As defined in the Contract Form
CONTRACT - As defined in the Contract Form
SMCD - Scheduled Mechanical Completion Date

PROCEDURE

1. Changes

A CONTRACTOR shall anticipate that as the WORKS progress, the Company may
request for changes to the WORKS the changes can be addition or deletion to
the WORKS.

B As the WORKS progress, the company reserves the right to request changes in
the WORKS and may request CONTRACTOR to quote, source and examine the
feasibility of the change before issuing the Field CONTRACTOR on its own
initiative shall reply within the given duration, specifying the validity of the
quotation, for the companies evaluation

C CONTRACTOR shall refer to the Figure I below for the responsibility of handling
the changes in the CONTRACT.
Page 3 of 16

KLM Technology
CHANGE ORDER PROCEDURE
Rev: 01
Group
Project Engineering Standard
(PROJECT STANDARDS AND
July 2013
SPECIFICATIONS)

CONTRACTOR'S COMPANY REMARKS


RESPONSIBILITY RESPONSIBILITY
REVIEW AND CONTRACTOR to record the
ISSUE FIR
TWO ORIGINALS
EVALUATE FIR FIR in the FIR Register.
COMPANY will acknowledge
receipt and return one original
CLOSE FIR APPROVAL to CONTRACTOR

CONTRACTOR to record the


ACKNOWLEGE RECEIPT ISSUE FI (TWO Fl in CO Register
& RETURN ONE ORIGINAL ORIGINAL)
COMPANY

COMPANY will acknowledge


receipt and return one original
REVIEW AND
ISSUE COP (TWO
EVALUATE COP
to CONTRACTOR.
ORIGINALS)

CONTRACTOR to
update/record the COP in CO
INCORPORATE COMMENT
AND RESUBMIT TWO
APPROVAL Register
ORIGINALS

CONTRACTOR to record the


ISSUE CO (TWO
ACKNOWLEDGE RECEIPT ORIGINAL) CO in CO Register
OF THE CO & RETURN ONE
ORIGINAL TO COMPANY

CLOSE FIR/CO?

Figure I - Flowchart for FIR/Fl/COP/CO.


Page 4 of 16

KLM Technology
CHANGE ORDER PROCEDURE
Rev: 01
Group
Project Engineering Standard
(PROJECT STANDARDS AND
July 2013
SPECIFICATIONS)

D If at any time CONTRATOR believes that any act or instruction by COMPANY


constitutes a change to the WORKS. and it is not covered under Fl from
COMPANY by forwarding the FIR

E COMPANY reserves the right to specify which Schedule in the Exhibit III of the
CONTRACT shall be utilized to compute the cost for such change

2. Field Instruction Request (FIR)

A If at any time CONTRACTOR believes that there has been a change in the Scope
of` Work and/or change in the Scope of Work is needed CONTRACTOR may
request COMPANY to issue a Fl by completing and forwarding two copies of
signed FIR (see Appendix I) with detailed justification indicating the cost or
schedule impact of the change.

B Upon receipt of the FIR,. THE COMPANY will evaluate the request and at its
discretion may approve or reject the request. If COMPANY agrees with the
request, then a Fl will be issued.

C CONTRACTOR shall maintain a running reference number for the FIR but it may
not necessarily be the same number as the FI.