Quality Systems Manual Method Statement
Quality Systems Manual Method Statement
METHOD STATEMENT
Table of Contents
1. Revisions Status
2. Scope/Objectives
3. References
5. Responsibilities
6. Procedures /Method to be Employed
7. Manpower Requirements
8. Material Requirements
9. Equipment Requirements
The scope of this method statement covers the installation of steel door frames and shutters.
The purpose of the documentation emanating from this statement is to ensure that quality
control objectives are maintained and accurate records are established for all related activities.
The objective is to ensure that the construction plan is executed, controlled and documented in
compliance with the contract drawings and specifications.
3.0 REFERENCES
• Contract Specifications
• Contract Drawings
• Program of Works
• Material & Drawings Submittal Schedule
Specific safety measures have to be follow ed as applicable. All safety measures are covered
separately in the project safety plan.
5.0 RESPONSIBILITIES
• The steel door frame and shutter works activities are carried out according to
specifications and drawings.
• Work progress is carried out according to the planned program and all the equipment
required to execute the works are available as per the project planning and are in good
condition.
• Coordination with the Consultant, Site Engineer, Safety Engineer and Subcontractors for
the safe and proper execution of the work.
• Specific attention is paid to all safety measures and quality control in coordination with
Safety Engineer and QC Engineer and in line with HSE plan and Quality plan.
• Coordination with the Safety Engineer to ensure that the works are carried out in a safe
working atmosphere.
• Coordination with the QC Engineer for test s to be carried out and initiate for the
inspection for the finished works.
• The implementation of any request that might be raised by the Consultant.
• Efficient daily progress has been obtained from all the equipment and manpower
engaged in the work and check the same against the daily report received from the
Foremen.
• The pass age of all the revised information to the Foreme n and ensure that it’s being
carried out properly.
• Coordination with the surveyor and plan the survey works in advance as per the work
sequence.
• The carrying out of the works as per the specifications and the related quality procedures.
• Inspection of the completed works and requesting for the Consultant’s approval.
• Maintena nce of complete inspe ction and test records for any further reference.
• The implementation of all safety measures in accordance with the HSE plan and that the
whole work force is aware of its proper implementation.
• The implementation of safety measures is adequate to maintain a safe working
environment on the site.
• Inspection of all the site activities and training personnel in accident prevention and its
proper reporting to the Project Manager and the Consultant.
• The site is maintained in a clean and tidy manner.
• The carrying-out the work and the proper distribution of all the available resources in
coordination with the Site Engineering on a daily basis.
• Daily reports of the works are achieved and coordinated for the future planning with the
site Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned Engineer.
• Meeting with any type of unforeseen incident or requirement and reporting the same to
the Site Engineer immediately.
QUALITY SYSTEMS MANUAL PAGE : 6 of 9
METHOD STATEMENT DOCUMENT NO : REV
• Door shall be hung on the doorframes using the specified hinges. Plumb and level
shall be checked.
• All steel doors shall be provided with a complete set of ironmongery as indicated
on the ironmongery schedule.
• All screws used for the doors shall be counter sunk and dressed flush after
installation and painted.
• The doors shall be covered properly after installation to protect them from
damage.
6.4 Ironmongery
• Approved Ironmongery, standard hinges, locks and handles shall be delivered
and fixed along with the door shutter and frame.
• Master key cylinder shall be delivere d for the appropriate doors.
• Approved panic bars shall be used for the appropriate doors.
• Approved door closers & stoppers shall be fixed to the appropriate doors.
• Charge hands
• Masons
• Carpenters
• Unskilled labors
• Mason’s tools
• Light projectors
• Stand-by generator
QUALITY SYSTEMS MANUAL PAGE : 8 of 9
METHOD STATEMENT DOCUMENT NO : REV
• All the safe practices will be adopted during the steel door frame and shutter works.
• Special work permits, wherever required, shall be obtained before commencing work.
• All necessary personal protective equipment must be used.
• Full body harness shall be provided for the labors on working platforms above 2m in
height.
• Proper access for the labor and equipment sha ll be provided for the works.
• All machinery shall be checked for maintenance records.
• The site shall be cleaned from all the debris, steel waste, nails etc
• All the quality control documentation related to the steel door frame and shutter works
should be approved before commencing the work. And as follows:
Ø QCP for the steel door frame and shutter works
Ø ITP for the steel door frame and shutter works
Ø Project Quality Plan
Ø Project HSE plan
Ø Check list sheets for the steel door frame and shutter works
Ø All material approva l
QUALITY SYSTEMS MANUAL PAGE : 9 of 9
METHOD STATEMENT DOCUMENT NO : REV
Approved