Drainage Testing Report
Drainage Testing Report
A Draiange Testing done for all shops and outside Drainage lines
B Water Flushing done in all shops floor drains , out side Manholes and Main lines
The following Comments noted in each Block and outside drainage lines:
S.No Block:13
Total Shops :08
Total No of Manholes:01
1 Ground Clean Out (GCO)missing on both side of B-13 line
2 All floor Drains steel cover to be cleaned and fixed
Block:14,15
Total Shops :15
Total No of Manholes:0
1 All floor Drains steel cover to be cleaned and fixed
Block:16
Total Shops :24
Total No of Manholes:02
1 Manhole MH-F-04 missing
2 If no need for Manhole then Ground clean out (GCO) must be there which is missing
3 All floor Drains steel cover to be cleaned and fixed
4 Manhole MH-D-08 blocked
Block:17
Total Shops :18
Total No of Manholes:03
1 All floor Drains steel cover to be cleaned and fixed
Block:18
Total Shops :40+Toilets Area
Total No of Manholes:06
1 All floor Drains steel cover to be cleaned and fixed
Toilets Area
1 All Arabic W.Cs have drainage problem
2 one english w.c is damage (broken)
3 All Flush valves not working
4 wash basin (W.B) have water supply problem
5 floor Drains blocked in Handicap toilet
6 floor Drains blocked in W.B contained bathroom
7 Hand Sprays missing in all toilets
8 Handicap W.C cover missing
9 Ablution Area 3-Tap mixers not working
10 Ablution area 1 floor Drain blocked
Block:19
Total Shops :46 ( 23 shops in front side & 23 in Back side)
Total No of Manholes:07
1 All floor Drains steel cover to be cleaned and fixed
2 Back side 4 Shops floor Drains are blocked
Block:20,31,32
Total Shops :30
Total No of Manholes:05
1 All floor Drains steel cover to be cleaned and fixed
2 floor Drain in one shop not installed
3 one side GCO missing while other side is blocked
Block:21
Total Shops :84 (42 front+42 back side)
Total No of Manholes:14
1 All floor Drains steel cover to be cleaned and fixed
2 One GCO missing
3 MH-K-01 manhole is blocked (Near to Municipal Main Manhole)
Block:23,24,25
Total Shops :47+ Toilets Area+ offices area
Total No of Manholes:04
1 All floor Drains steel cover to be cleaned and fixed
2 Main Manhole between B23 toilets & B25 Toilets is not as per standard,all 4 inlets lines and one outlet line are at
the same level,also outlet line size is small i-e 4" dia pipe is used.
3 Back side of B23,one GCO missing
4 Manhole MH-L-02 is missing
5 2 Hands Sprays missing in Office Area Toilets
Block:26,27,28
Total Shops : 92
Total No of Manholes:10
1 All floor Drains steel cover to be cleaned and fixed
2 Manhole MH-L-04 need inside cleaning
3 Slope require among Manhole MH-L-03,MH-L-04 & MH-L-05, the already established slope is very less,Blockage
chances is very high.
4 2 GCO missing at B26,B27