14.PS-14-Welding Works
14.PS-14-Welding Works
14.PS-14-Welding Works
Water Directorate
Asset Management Department
STANDARD SPECIFICATIONS
FOR WATER WORKS
TECHNICAL TERMS
Chapter – 4
Engineering Specifications
E – Pipeline works Specifications
PS 14
WELDING WORKS
TABLE OF CONTENT
1. SCOPE
2. APPLICABLE STANDARDS AND CODES
3. DESIGN CONSIDERATION
4. WELDING REQUIREMENTS
4.1 Approved Welding Processes
4.2 Welding Procedure Qualification
4.2.1 Welding Procedure Specifications (WPS)
4.2.2 Procedure Qualification Records (PQR)
4.3 Welders Qualification
4.3.1 Welder’s Qualification Tests
4.4 Essential Variables
4.4.1 Base Material
4.4.2 Welding Process
4.4.3 Joint Design
4.4.4 Base Material Thickness
4.4.5 Welding Consumable
4.4.6 Welding Position
4.4.7 Welding Parameters
4.5 Qualification Tests
4.5.1 Non-Destructive Examination
4.5.2 Destructive Tests
4.6 Production Welding Requirements
4.6.1 Welding Equipment
4.6.2 Welding Processes
4.6.3 Weather Protection
4.6.4 Welding Consumables
4.6.5 Electrode Size
4.6.6 Shielding Gases
4.7 Cutting and Weld Joint Preparation
4.8 Cleaning Requirements
4.9 Edge Preparation and Joint Alignment
4.10 Tack Welds
4.11 Joint Backing Requirements
4.12 Heat Treatment of Welding Works
4.12.1 Preheat Requirements
4.12.2 Preheat Temperatures
4.12.3 Application of Preheat
4.13 Interpass Temperature
4.14 Interruption Of Welding
4.15 Weld Bead Sequence
4.16 Interpass Cleaning
This specification prescribes the minimum requirements for welding, welding inspection and
Non-Destructive Examination of shop fabricated and field fabricated steel piping (carbon steel
and stainless steel and ductile Iron pipes). The requirements apply to pipework associated
with vendor supplied equipment packages, longitudinal seam welds of bulk purchased piping
components such as pipes, tees and elbows, pipework fabricated as part of a contractual
fabrication and field erected piping.
This specification shall apply to the main Contractor and to all his sub-contractors.
All materials and work manship shall comply with the latest edition of applicable standards
and codes which shall include but not be limited to the following.
3. DESIGN CONSIDERATION
The welding type selection, welding preparation, welding procedure, welders qualification,
welding machine type and welding inspection and tests, all shall be in accordance with the
ASTM, ANSI, ASME IX or equivalent British Standards. Filler metal shall comply with the
requirements of the AWS or equivalent.
The design, fabrication and inspection of pipework shall comply with the requirements of
ASME B31.3 except as modified herein.
All welding and quality control of welding fabrication shall be done by the Contractor in
accordance with the requirements of this Specification. Weld metal composition shall
becompatible with the parent metal.The Contractor shall comply with FEWA/Engineer Safety
Regulations.All welding shall be as specified by the Contractor on the drawings and the
isometric drawings showing all welds, each marked with a unique identification number.
The selection of the welding process, electrodes, shielding gas etc. depend on the materials
properties of the pipes to be welded in accordance with the welding code's
requirement.Manual GTAW (TIG) welding must be done with the addition of filler metal and
high frequency starting unit. It is limited to a thickness range of 3 mm to 6 mm for carbon
steel.
Short circuiting arc (MIG, MAG or GMAW) welding, Gas Shielded Flux-Cored Arc or Plasma
Arc Welding may be used only upon specific approval by FEWA/Engineer.
Full welding of pipework of all materials for pipes of nominal diameter less than or equal to
DN 50 mm (2" NB) and wall thickness less than 6 mm shall be done by GTAW process.
Unless otherwise agreed a qualified third party inspection agency shall be appointed by the
Contractor for the qualification welders and evaluation of welding works at the fabrication
shop and at site.Welding procedure specifications and repair weld procedures are required to
cover all circumferential butt welds, any longitudinal butt welds and attachment welds
including branch, weldolet, sockolet and pipe support welds.
All welding procedures should be submitted for approval on Form QW-482 of ASME Sec. IX.
The proposed WPS shall include but not be limited to the following :
a) Contractor's name
b) WPS number, revision and date
c) Welding process and type (manual, automatic, etc)
d) Joint design and sketch and sequence of passes
e) Base material P number and group number
f) Material type and grade
g) Pipe diameter and thickness range
h) Welding consumables - AWS classification, manufacturer, brand name, F number, A
number, size, etc.
i) Welding positions
j) Welding progression
k) Preheat temperature, minimum
l) Interpass temperature, minimum and maximum
m) Method of preheat application and measurement
n) Post weld heat treatment, holding temperature and time, heating rate, cooling rate and
method of application.
o) Type of current and polarity
p) Method of edge preparation
g) Method of back grinding
r) Gas shielding - flow rate and composition
s) Gas backing - initial duration of purging, flow rate, composition and duration
t) Current, voltage and welding speed for each layer.
Written approval by FEWA/Engineer is required prior to the use of any pre-qualified WPS.
a) Contractor's name
b) PQR number and date
c) WPS number, revision and date
d) Welding process
e) Type (manual, automatic, semi-automatic)
f) Joint design and sequence of passes
g) Base material specification, grade, carbon equivalent, thickness and pipe diameter.
h) Filler metal AWS classification, size, manufacturer, brand name, A. No. and F. No.
i) Welding position and progression
j) Preheat temperature, method of application and measurement.
k) Interpass temperature
l) Post weld heat treatment, holding temperature, holding time, heating and cooling rates
m) Shielding gas, composition and flow rate
n) Backing gas composition and flow rate
o) Current type and polarity
p) Tungsten electrode type and size (for GTAW )
q) Orifice or gas cup size (for GTAW & GMAW)
r) Method of cleaning
s) Method of back grinding
t) Welding current, arc voltage, welding speed and heat input as per sect 6.3.7 for each
pass.
The Contractor shall submit the following back up certificates/reports for approval prior to the
commencement of production welding :
The sample welds shall be carried out on specimens of similar shape, thickness and chemical
analysis as of the material to be welded, and in a position, which shall represent as far as
possible the worst conditions under which actual welding would take place.NDE and
mechanical testing shall be conducted after post weld heat treatment where applicable. NDE
shall be conducted by American Society of Non Destructive Testing (ASNT) Level II or
equivalent certified personnel.Mechanical testing shall be carried out in accordance with
ASME Sec. IX in an approved testing laboratory using calibrated instruments.
Welders engaged on welding at Site shall be under the supervision of a competent welding
engineer. The welding engineer shall exclusively employed for this work with due approval of
FEWA/Engineer.
All welders and welding operators shall be qualified for all welding positions in which they will
carry out production welding. All welds executed by unqualified welders shall be rejected.No
welder shall be qualified on production welds.
A welder or welding operator who fails the performance qualification test of this
specification,may be granted an immediate retest in accordance with ASME Sec. IX (QW-321
solely at FEWA/Engineer discretion. If the welder or welding operator fails in the retest, he
may be given only one further test in accordance with QW-321.3 but only after he has
received adequate training to the satisfaction of FEWA/Engineer.
Welder’s valid qualificatrion shows that the welder or welding operator has been continuously
engaged on work of a similar nature with the specific welding process since successful
qualification. A break in continuity of more than 3 months (90 days) shall require
requalification.
All qualified welders for production welding shall be assigned a unique identification number
with welder's photograph on identification badges singed by FEWA/Engineer and to be worn
by the welders during welding.
The Contractor shall supply a welding schedule indicating also the extent and kind of non-
destructive tests of the welds which are subject to approval by FEWA/ Engineer.
If any defect is noticed in the welds the Contractor shall rectify the defect by cutting, replacing
and re-welding as if the process is being carried out freshly
Any equipment which does not meet these requirements shall be replaced.
All welding equipment and accessories shall meet the safety regulations of the relevant
international specifications (such as NEMA) and shall be safe to operate.
When using the GTAW process, a high frequency (HF) arc initiation unit, a controlled current
delay device (to eliminate crater) and suitable pre-end post-gas flow device (to eliminate
porosity and air entrapment) shall be used.
The Contractor shall provide approved adequate shelter to protect the welding environment
from inclement weather and drafts.No welding shall be carried out when the weld surfaces
are wet or dirty and if inadequate provision has been made for weather protection .
All surfaces to be welded and the adjoining area of the material shall be warm and dry.Where
the surfaces to be welded are covered by moisture and where there is no requirement of
preheat by the applicable WPS, the surfaces should be completely dried and warmed up by a
The Contractor shall prepare and submit to FEWA/Engineer a list of welding consumables to
be used on the project showing type, manufacturer, brand and the manufacturer's
recommended storage and drying procedure for each.
Storage and control of welding consumables shall be in accordance with the following :
- All electrodes shall be stored in fully sealed packages and stored in dry storage rooms.
- All electrodes which are damaged, wet, rusty or contaminated with oil, grease, dirt etc.
shall be scrapped. Electrodes partly used shall not be used.
- The Contractor shall provide separate ovens for baking and storing of low hydrogen
welding consumables.
- SMAW electrodes of different weld metal compositions or having different flux type
covering shall not be stored or baked together in the same oven.
- Low hydrogen electrodes shall be baked at 300°C for at least one hour or as per
manufacturer's recommendations.
- Cellulose coated SMAW electrodes shall be kept in a dry and dust free enclosure after
opening of the factory container.
Filler wires, Fluxes and bare electrodes shall be stored in sealed, dirt and moisture proof
containers within a dry, dust-free enclosure.
Only fused type fluxes shall be used and they should be dried according to manufacturer's
recommendation. If agglomerated fluxes are used, they shall be baked at a temperature of
250°C - 300°C for a minimum of two hours and kept in drying ovens at all times.For carbon
steel materials, the SAW process shall not utilise an active (Mn-Si) flux nor EHXX (high
manganese) wires.
Only low hydrogen electrodes shall be used for the following cases with SMAW :
(a) Welding and/or installing hot-tap connections on pipes containing flammable liquids, gas
or combustible materials.
(b) For the repair of all welds in carbon steel plates.
(c) Full penetration double-groove joints.
(d) Fill and cap passes of all other applications for all carbon steels for all thicknesses.
With the exception of low hydrogen electrodes, (a) through (c), cellulose coated electrodes
may be used only for the root passes of carbon steels with prior written permission of
FEWA/Engineer.
(a) The maximum electrode diameter for all single sided welding using the SMAW process
shall be 3.2mm for the root pass and 5mm for the fill and cap passes.
b) The maximum electrode diameter for double sided welds using SMAW shall be 4mm for
the root pass and 5mm for the fill and cap passes.
Thermal cutting is acceptable for carbon and low alloy steels. For plates less than 25 mm
thick, cold shearing may be used. For plates between 11 mm to 25 mm thick the cut edges
shall be dressed back atleast 2 mm by machining or grinding. The edges shall be inspected
by MP or DP method. For stainless steel material, flame cutting is not allowed but plasma
cutting may be applied.
End profiles of pipes and fittings which are to be butt welded shall be in accordance with
ASME B 16.25. Pipes for socket weld joints shall be cut square. All cut surfaces shall be
finally prepared by grinding or machining to clean, bright metal. After the edges have been
prepared for welding, they shall be visually examined to confirm that the preparations are
smooth and uniform and free from tears, cracks, gouges and other discontinuities which
might affect the weld quality.
Further the prepared welding ends shall be examined by ultrasonics for a distance of 50mm
back from the bevelled edge to ensure freedom from laminations, and magnetic particle
inspection on bevels. The use of arc air gouging shall not be permitted.Branch connection cut
outs shall be carefully bevelled and accurately matched to form a suitable groove for welding
and to permit complete penetration of the welds at all points.
<DN 50 mm 1.5 mm
DN 50 to DN 250 mm 1.5 to 2.5 mm
>DN 250 mm 2.5 to 3.5 mm
Butt weld alignment shall satisfy the requirement of ASME B31.3 and the conditions stated
below.Internal misalignment of pipework shall not exceed 1.0mm in order to facilitate welding
of the root pass. When a GTAW root pass is to be used the maximum misalignment shall not
exceed 0.8mm Misalignment may be reduced by the use of hydraulic or screw type of
clamps.
Hammering heating and buttering of weld shall not be permitted.In case of pipes/components
with different thickness misalignment upto 3.2 mm may be improved by internal machining
provided the taper does not exceed 1 in 4 max. However the minimum required wall
thickness shall be maintained. Grinding shall not be used.Correction of misalignment by use
of cold working shall not be permitted.
Where internal pipe aligners are used, they shall not be removed until the root pass has been
completed. Where external lineup clamps are used, the clamp may be removed when the
root bead is at least 50% completed. The root bead should be spaced evenly around the
circumference.The longitudinal welds of adjacent pipes shall be staggered by at least
100mm.
Any defective tack shall be completely removed by grinding prior to welding of the root pass.
When tack welds are removed, the Contractor shall ensure that the root preparation is
correctly maintained for the subsequent pass.Tack welds not incorporated in the final weld
shall be removed by grinding or other mechanical means to achieve smooth surface without
reduction in wall thickness, followed by Non destructive test inspection.
St 35 - - 650-700C Above 20 mm
(*) Not necessary for fusion butt-welded pipes with DN <51mm and Wall thickness
8 mm
Above table of heat treatment shall be completed by a supplementary table including all heat
treatment recommended for any other material included in the Contract subject to welding
either at workshop or at Site. This supplementary table shall be supplied to FEWA/ Engineer
for approval not more than 3 months after Award of Contract.
The determination of pre-heat temperature for carbon steel production welds should be based
upon ASME Section 1X Code after consideration of specific heat input, joint thickness metal
composition, welding process and welding consumables.
(1) The relevant carbon equivalent (CE) should be calculated from the maximum CE allowed
by the material specification.
(2) Consideration should be given to joint restraint as in case of branch connections
(weldolets, sockolets and nippolets).
When the base metal temperature is below 21 deg.C for carbon steels, the material shall
bepreheated to 50 deg.C prior to welding.Whenever material is wet or contains surface
moisture or condensate, it shall be dried by heating. The fusion faces and 100 mm on each
side of the welds shall be preheated up to 50 deg.C.
The minimum preheat temperature shall be established on both sides of the joint
preparationfor a minimum distance of 75 mm or 3 times the material thickness whichever is
greater. If possible, the preheat temperature shall be measured on the opposite face to that
being heated. Where access to only one face is possible, the heat source shall be turned off
to allow for temperature equalization (one minute for each 25mm of wall thickness) before
measuring the preheat temperature.
The preheat temperature shall be held for at least 5 minutes before welding is
commencedand shall be checked before and during welding by thermo-couples, contact
pyrometer or bytemperature indicating crayons. (colour charging crayons shall not be used)
The interpass temperature shall be measured at a distance of about 12.5mm from the bevel
ends and shall be measured by contact pryrometer, thermo-couples or temperature indicating
crayons. (colour changing crayons shall not be used)
a) If 3 runs, and 50% wall thickness has not been deposited, then the weld should be cut
out and recommenced from a new preparation.
b) If 3 runs, and 50% wall thickness have been deposited then the welding operation may
commence provided the following conditions (c) and (d) are met:
c) The weld on interruption shall be allowed to cool slowly from welding temperature to
room temperature (this may be done by wrapping the weld with insulation and allowing
the joint to cool in still air.)
d) Before welding is resumed the weld shall be preheated to the specified temp, after a
close visual or MPI as required by FEWA/Engineer.
Root runs and second passes (hot passes) shall be made without interruption other than
forchanging electrodes or filler wires or to allow welders to reposition themselves.The second
pass (hot pass) of carbon steel pipe welds shall be deposited immediately after the root pass
in order to prevent "cold cracking' in the root area due to shrinkage stresses and joint
restraint.
a) Socket welds which may be used on pipe of nominal size DN 40 mm and less, as defined
in the contract drawings.
Where access permits, pipework with nominal size over DN 600 mm shall be welded from
both sides. Double sided welds shall be back-gouged to sound metal and ground smooth
prior to welding from the second side. However the Contractor shall ensure safe working
atmosphere like ventilation/fume extraction/respirators etc. is provided in order for the welder
to perform the welding.
All pressure containing welds shall have a minimum of three passes with overlaps of starts
and stops. This shall include seal welds of threaded connections and socket
welds.Longitudinal butt-welded pipe fittings are not allowed without written approval of
FEWA/Engineer.
4.17 Peening
No weld peening of any sort shall be permitted.
During socket welding, the inserted end of the pipe nipple shall not come in contact with the
bottom of the socket. A minimum clearance of 1.6mm shall be given prior to welding. Use of
contraction rings to achieve minimum clearance are not allowed without written approval of
FEWA/Engineer.
Cases which fail to meet this criteria shall be referred to FEWA/Engineer for approval prior to
the commencement of fabrication.Non-pressure containing attachment welds, such as pipe
support welds shall be at a minimum distance of 50mm from any pressure containing
welds.Where pup sections are to be inserted, the length of such insert pup sections for both
new and existing fabrication shall not be less than three pipe diameters, or 150mm whichever
is greater.
Arc strikes, gouges etc. outside the fusion face shall be limited to one per pipe and one per
joint.Repair of Arc strikes shall be at the discretion of FEWA/Engineer.If resultant wall
thickness after grinding is less than the minimum design thickness, the position of pipe
containing arc burn shall be removed as a cylinder.Insert patching and rewelding to increase
the wall thickness shall not be permitted.
Coated surfaces shall be protected from the welding arc and the associated weld
spatter.Weld reinforcement and internal weld protrusion shall be as required by ASME B31.3
but in no case shall the height exceed the weld crown.Excessive internal weld protrusions on
accessible joints shall be removed by grinding. Welds having excessive protrusions on
inaccessible joints shall be cut and re-welded.
Where leg length is specified, the throat thickness for a 1 x 1 fillet weld shall be from 0.7 to 1
times the required leg length. The throat thickness for a 1 x 2 fillet weld shall be 0.7 to 1.2
times the size of the shorter leg.
For SAW process, welding shall be done without any weaving (oscillation.)All pressure
containing welds shall have at least two passes with overlapping starts and stops.Only single
electrode processes shall be used. Use of multiple electrodes shall require prior
FEWA/Engineer approval.Welding of all pressure containing welds shall be done with direct
current unless otherwise previously approved by FEWA/Engineer.All vertical welding shall be
done uphill. Downhill ('stove-pipe') welding of pressure containing welds shall not be
permitted.
a) All carbon steel pipework when the material thickness through a butt weld joint exceeds
19mm.
b) Carbon steel pipework subject to vibration, such as compressor piping, when the
material thickness through the butt weld joint exceeds 12.7mm.
c) Carbon Steel branch connections when the thickness in any plane through the branch
weld exceeds thickness requirements as indicated in ASME B31.3 para 331.1.3.
d) Wherever required for the fabrication of fittings as applicable.
Post weld heat treatment shall be carried out as soon as possible after completion of welding
and shall be conducted in accordance with ASME B31.3 except as modified by this
specification.The temperature controls during heating and cooling shall meet the
requirements of ASME Sec. VIII Division 1.
A post weld heat treatment (PWHT) procedure shall be submitted for FEWA/Engineer
approval prior to any PWHT being conducted.Wherever possible PWHT shall be conducted in
an enclosed furnace. For site or field welds,local PWHT by electrical resistance method shall
be conducted.
The use of manually operated gas torches or gas rings or proprietary exothermic kits shall not
be permitted.Where Local PWHT is done, the weld being post-weld heat treated shall be in
the centre of the heated band. The heated band shall be sufficiently wide such that a band at
A time temperature chart recording the thermal history of the part heat treated shall be
provided by the Contractor. The chart shall be clearly identified with the drawing/ISO number,
part and weld number an signed by the CONTRACTOR and certifying authority where
applicable. The chart shall be included in the project record work/"As-built"
documentation.Thermocouples shall, if possible, be placed on the inside for objects being
heated from the outside, and vice-versa, if internally heated.
Thermocouples and temperature recording equipment shall be calibrated prior to use and
shall have a valid certification by a reputed certifying authority.Welding shall be avoided on
any post-weld heat treated material. If any welding is to be carried out on any post weld heat
treated material, this shall be referred to FEWA/Engineer.
Failure to do so will call for repeating heat treatment.All machined surfaces such as pipe
ends, flange faces and threads shall be suitably protected during the PWHT cycle.NDT of
welds, where applicable, shall be conducted after PWHT for final acceptance.
All NDE shall be carried out in accordance with the procedures approved by
FEWA/Engineer.The radiographic inspection procedures shall include film-processing
procedures to be usedfor non-destructive examination (NDE).The Contractor shall
The Standard Test Radiograph shall be repeated at the option of FEWA/Engineer whenever
any change has been made in the operation procedure or whenever production films vary
appreciably in details, contract or density, from the Standard Test Radiograph.Radiographic
inspection shall be conducted by the use X-rays. Gamma ray examination may only be used
with the approval of FEWA/Engineer.
The Contractor shall submit detailed radiation safety procedures which comply with FEWA
safety regulations.Radiographic inspection shall comply with the relevant safety codes and
radiation control procedures. Special attention is drawn to the necessity for audible and visual
warning devices and for regular monitoring of radiation levels.Radiographic procedures shall
be qualified using both source and film side penetrameter.
The zero datum shall be top dead centre of the pipe. Defect location shall be in metric units
system. Each radiograph shall have reference markers at 10 cm intervals.The letter "R" shall
appear on all radiographs of weld repairs in addition to the above information.The RT films
shall be stored and kept by the Contractor until final handing over, and shall be available at
anytime for FEWA/Engineer review.
Prior to the commencement of work, the Contractor shall establish an identification system
such that each assembly, each component and each weld can be uniquely and fully identified
with welder/welding operator, welding procedure specification (WPS), NDE
procedure/technique, extent of NDE and NDE results.Procedures for radiography, ultrasonic,
magnetic particle and dye-penetrant examination shall all be conducted in accordance with
ASME Section V.
All personnel performing NDE shall have ASNT Level II or equivalent certification as
approved by FEWA/Engineer prior to the commencement of work.The Contractor must
submit weld map showing NDE system for written FEWA/Engineer approval prior to the
commencement of fabrication.
(a) At least 'X' percent of the total number of welds within the specified line class shall be
examined for 100% of their length (circumference).
(b) At least 'X' percent of the total number of welds on each isometric shall be examined and
shall not be less then one weld per isometric.
(c) At least 'X' percent of the total number of welds made by each welder shall be examined
for 100% of their length. At least one complete weld shall be examined for each welder.
(d) Examinations shall be representative of the entire range of pipe sizes and joints that
have been welded.
(e) Where reduced percentage examination is required and the resulting test shows defects,
then additional examinations as required by ASME B 31.3 para 341.3.4 shall apply
regardless of the examination process used.
(f) Defect acceptance criteria for all reduced percentage examinations shall be the same as
for 100% examination.
(g) 'X' percent shall be determined by FEWA/Engineer and shall be specified for each piping
class.
The workmanship and weld finish shall be as per this specification.Weld acceptance criteria
for visual examination shall be as per ASME B31.3, Table 341.3.2 except as modified by this
specification.
Gamma radiography shall only be used if it can be proven that the required sensitivity can be
achieved.Wherever possible, DIN penetrameters (wire type Image Quality Indicators) shall be
used.Radiographic sensitivity shall be 1.8% or better.Where film side IQI's are used,
correlation of sensitivity with source side IQI'S shall be established before proceeding with
inspection.Only lead intensifying screens shall be used.
5.3.1 Reporting
The radiography report shall include the following information:
- Contract number
- Project title
- Name of the component
- Source type (X-ray/Ir-192)
- Source strength (mA/curies)
- Focal spot size
- Technique (SWSI/DWDI/DWSI/PANAROMIC)
- Film type and size
- Penetrameter type and number
- Exposure time
- Developing time and temperature
- Density
- Sensitivity
- Lead screens (front and back)
- Specification (ASME B31.3)
- Weld identifications
- Pipe diameter and wall thickness
- Welder identification
- Interpretation
- Remarks (Accept/Reject)
- Radiographer's name and signature
- Date of exposure
The ultrasonic equipment shall be checked for linearity, db attenuation etc. and a valid
calibration certificate shall be submitted for FEWA/Engineer review, prior to use.As a
minimum requirement, ultrasonic examination shall be conducted using a minimum of three
transducers, one 0° compression and two angle beam transducers with a frequency of 1 to 5
MHZ. Where access permits, ultrasonic examination shall be conducted from both sides of
the joint.
Prior to conducting ultrasonic examination, the Contractor shall ensure that the weld and the
surrounding area are sufficiently smooth to avoid false or misleading indications. Transfer
The test report should outline the technique employed, type and size and frequency of probes
used, and defects discovered and shall contain the following information as a minimum:
(a) Weld identification and welder number
(b) Weld procedure used
(c) Size of reportable defect
(d) Depth of reportable defect
(e) Location and orientation of reportable defect (with a sketch)
(f) Weld acceptable/not acceptable.
(g) Specification
(h) Inspector's name and signature
(i) Date of Examination
(j) Scanning Diagram.
Ultrasonic examination of welds shall be conducted after PWHT that may be required for final
acceptance.
Magnetic particle examination shall be carried out in accordance with ASME Section V Article
7. Dye-penetrant examination shall be carried out in accordance with ASME Section V
Article6. The acceptance criteria shall be as per ASME B31.3 and Table 341.3.2.Where
PWHT is required, magnetic particle/dye-penetrant examination shall be conductedafter
PWHT for final acceptance. Examination shall be conducted before PWHT for any
repair/rectification that may be required before PWHT.
Where the NDE technician is certified by the Contractor himself, the qualification shall be in
accordance with Contractor's written procedures which shall use ASNT'S recommended
practice No. SNT-TC-1A, as a guide. This written procedure shall be subject to
FEWA/Engineer approval.
The area to be repaired shall be pre-heated to at least 50 deg.C above the temperature
specified in the corresponding initial welding procedure but shall not exceed the maximum
interpass temperature. Repair welding shall be carried out using the approved repair welding
procedure. The Contractor shall take appropriate care such as proper weld sequencing,
control of interpass temperature etc. to minimize residual stresses.
All repair welding shall be carried out by qualified welders.If any repairs are carried out after
PWHT or hydrostatic test, the PWHT and hydrostatic test shall be repeated.Planar defects
such as cracks etc. shall not be permitted. Such joints containing cracks shall be cut out.
The Contractor shall have the various inspection stages witnessed and reports reviewed by
FEWA/Engineer."Acceptance" by FEWA/Engineer does not relieve the Contractor of his
responsibility to fulfill his contractual obligations.
On-site welding of D.I. pipes, fittings, flanges and the like shall be by electric arc in
accordance with approved international standards and procedures. Welding shall only be
Prior to any welding, the parts to be joined must be thoroughly cleaned by grinding or filing in
order to obtain a bright metallic surface. Any coatings which might stick to the tools shall be
scraped off or must be removed by chemical means (e.g. turpentine). All surfaces shall be
free of zinc.All parts to be welded shall be kept dry and shelters shall be erected over the
working area in the event of inclement weather.
Welding shall be carried out using sheathed nickel-iron electrodes containing approximately
50% nickel. Welding shall be either by alternating current or direct current on the negative
pole. The current shall be 110 - 120 amps. Preheating or post -heating shall be applied as
and when required. All parts to be welded shall be held firmly in jigs or clamps. Restraining
beads on spigot ends shall follow a copper gauge held tightly around the pipe in accordance
with pipe manufacturer recommendations. No undercutting shall be permitted.
All welds shall be allowed to cool naturally without forced ventilation. They shall be cleaned of
slag and as a minimum requirement painted with one coat of Zinc rich paint and one coat of
bituminous paint giving a minimum dry film thickness of 150 microns. Where specific coatings
are required then the same coating specification shall be applied to the welded item.
All internal cement mortar linings shall be made good in accordance with the specifications.
Any damaged or rejected pipe work shall be replaced by the CONTRACTOR at his own
expense. No on-site welding of D.I. pipes shall be allowed prior to having written approval
from FEWA.
7. VENDOR DOCUMENTATION
The as-built QC dossier shall include the following:
(a) Material identification/traceability reports for each item in the contract drawings.
(b) Mill certificates of all materials giving the chemical composition and mechanical
properties.
(c) FEWA/Engineer approved procedure specifications (WPS)
(d) FEWA/Engineer approved Procedure Qualification Records (PQR) along with backup
NDE and mechanical test reports.
(e) List of Qualified Welders and Welder Performance of Notification Certificates.
(f) NDT reports.
(g) As-built drawings.
(h) Weld identification drawings.
(i) NDT summary control sheets, which show weld numbers, type and extent of NDT for
each weld, report numbers for each weld identification drawing and welding date.
(j) Heat treatment reports and charts.
(k) Dimensional inspection reports.
(l) Hydrotest reports.
(m) Blasting and painting reports.