14.PS-14-Welding Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

Federal Electricity & Water Authority

Water Directorate
Asset Management Department

STANDARD SPECIFICATIONS
FOR WATER WORKS

TECHNICAL TERMS

Chapter – 4
Engineering Specifications
E – Pipeline works Specifications

PS 14
WELDING WORKS

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: Document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 she 1 of: 27
et:
SPECIFICATIONS FOR PIPELINE WELDING WORKS

TABLE OF CONTENT
1. SCOPE
2. APPLICABLE STANDARDS AND CODES
3. DESIGN CONSIDERATION
4. WELDING REQUIREMENTS
4.1 Approved Welding Processes
4.2 Welding Procedure Qualification
4.2.1 Welding Procedure Specifications (WPS)
4.2.2 Procedure Qualification Records (PQR)
4.3 Welders Qualification
4.3.1 Welder’s Qualification Tests
4.4 Essential Variables
4.4.1 Base Material
4.4.2 Welding Process
4.4.3 Joint Design
4.4.4 Base Material Thickness
4.4.5 Welding Consumable
4.4.6 Welding Position
4.4.7 Welding Parameters
4.5 Qualification Tests
4.5.1 Non-Destructive Examination
4.5.2 Destructive Tests
4.6 Production Welding Requirements
4.6.1 Welding Equipment
4.6.2 Welding Processes
4.6.3 Weather Protection
4.6.4 Welding Consumables
4.6.5 Electrode Size
4.6.6 Shielding Gases
4.7 Cutting and Weld Joint Preparation
4.8 Cleaning Requirements
4.9 Edge Preparation and Joint Alignment
4.10 Tack Welds
4.11 Joint Backing Requirements
4.12 Heat Treatment of Welding Works
4.12.1 Preheat Requirements
4.12.2 Preheat Temperatures
4.12.3 Application of Preheat
4.13 Interpass Temperature
4.14 Interruption Of Welding
4.15 Weld Bead Sequence
4.16 Interpass Cleaning

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 2 of: 27
:
4.17 Peening
4.18 Seal and Socket Welding
4.19 Attachment Welds
4.20 Weld Spacing
4.21 Workmanship and Weld Finish
4.22 Welding Technique
4.23 Post Weld Heat Treatment
4.24 Weld Identification
5. INSPECTION AND TESTING
5.1 General
5.1.1 Reduced Percentage Examination
5.2 Visual Examination
5.3 Radiographic Examination
5.3.1 Reporting
5.4 Ultrasonic Examination
5.5 Magnetic Particle/Dye-Penetrant Examination
5.6 Ultrasonic Thickness Measurement
5.7 Extent of Non-Destructive Examination
5.8 NDE Personnel Qualifications
5.9 Repair of Defects
5.9.1 General
5.9.2 Minor Surface Repairs
5.9.3 Repairs Involving Welding
5.9.4 NDE of Repair Welds
5.9.5 Limitations on Repairs
5.9.6 Additional Acceptance Criteria
6. WELDING OF D.I. PIPES ON SITE
7. VENDOR DOCUMENTATION

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 3 of: 27
:
SPECIFICATIONS FOR PIPELINE WELDING WORKS
1. SCOPE

This specification prescribes the minimum requirements for welding, welding inspection and
Non-Destructive Examination of shop fabricated and field fabricated steel piping (carbon steel
and stainless steel and ductile Iron pipes). The requirements apply to pipework associated
with vendor supplied equipment packages, longitudinal seam welds of bulk purchased piping
components such as pipes, tees and elbows, pipework fabricated as part of a contractual
fabrication and field erected piping.

This specification shall apply to the main Contractor and to all his sub-contractors.

2. APPLICABLE STANDARDS AND CODES

All materials and work manship shall comply with the latest edition of applicable standards
and codes which shall include but not be limited to the following.

API 5L Specification for Line Pipe


API 1104 Welding Pipelines and related facilities.
BS 4504 Sect 3.1 Circular Flanges for Pipes, Valves and Fittings (PN
designated) Specification for steel flanges.
ASME B31.3 Process Piping
ASME Section II Part C Welding Rods, Electrodes and Filler Metals
ASME Section V non-destructive Examination
ASME Section VIII Div. 1 Pressure Vessels
ASME Section IX Welding and Brazing Qualifications
ASTM A 312 Seamless and welded austenitic stainless steel pipe
ASTM A 106 Seamless carbon steel pipe for high temperature service.
ASTM E110 Indentation Hardness of Metallic Materials by Portable
Hardness Testers
ASTM E92 Vickers Hardness of Metallic Materials
ASTM E94 Standard Recommended Practice for Radiographic Testing
ASTM A 370 Mechanical Testing of Steel Products

3. DESIGN CONSIDERATION

The welding type selection, welding preparation, welding procedure, welders qualification,
welding machine type and welding inspection and tests, all shall be in accordance with the
ASTM, ANSI, ASME IX or equivalent British Standards. Filler metal shall comply with the
requirements of the AWS or equivalent.
The design, fabrication and inspection of pipework shall comply with the requirements of
ASME B31.3 except as modified herein.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 4 of: 27
:
4. WELDING REQUIREMENTS

All welding and quality control of welding fabrication shall be done by the Contractor in
accordance with the requirements of this Specification. Weld metal composition shall
becompatible with the parent metal.The Contractor shall comply with FEWA/Engineer Safety
Regulations.All welding shall be as specified by the Contractor on the drawings and the
isometric drawings showing all welds, each marked with a unique identification number.

4.1 Approved Welding Processes


Welding of pipe work joints shall be by fusion welding or argon welding as required, using
manual or semi-automatic welding process. The process shall be such that the arc and the
deposited metal are protected from atmospheric conditions.

The following processes are approved for use on pipework :

a) Shielded Metal Arc Welding (SMAW)


b) Gas Tungsten Arc Welding (GTAW, or TIG)
c) Gas Metal Arc Welding (GMAW or MIG/MAG)
d) Submerged Arc Welding (SAW)
e) Electric Resistance Welding - high frequency process (for longitudinal seams only)

The selection of the welding process, electrodes, shielding gas etc. depend on the materials
properties of the pipes to be welded in accordance with the welding code's
requirement.Manual GTAW (TIG) welding must be done with the addition of filler metal and
high frequency starting unit. It is limited to a thickness range of 3 mm to 6 mm for carbon
steel.

Short circuiting arc (MIG, MAG or GMAW) welding, Gas Shielded Flux-Cored Arc or Plasma
Arc Welding may be used only upon specific approval by FEWA/Engineer.

Self shielded flux-cored arc welding shall not be permitted.


The root pass welding of pipework of all materials for pipes of nominal diameter less than or
equal to DN 50 mm (2" NB) shall be done by GTAW process.

Full welding of pipework of all materials for pipes of nominal diameter less than or equal to
DN 50 mm (2" NB) and wall thickness less than 6 mm shall be done by GTAW process.

4.2 Welding Procedure Qualification

4.2.1 Welding Procedure Specifications (WPS)


Fabrication welds executed at factory/works, which are liable to be highly stressed, such as
may be the case in pressure parts of those subjected to rotational stresses or reversal of
stresses in operation, the Contractor shall provide, if requested, with details of welding,
fabrication procedure adopted and relevant test certificates

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 5 of: 27
:
Copies of all welding records including welding procedure, protecting and post heating, stress
relieving, analysis report, physical preparation of material and copies of the tests of welds
shall be submitted to FEWA/Engineer.Certified copies of the essential welds shall be included
in the operational and maintenance manuals. Where required by FEWA/Engineer the
selected welds shall be subjected to penetrate tests as per relevant standards

Unless otherwise agreed a qualified third party inspection agency shall be appointed by the
Contractor for the qualification welders and evaluation of welding works at the fabrication
shop and at site.Welding procedure specifications and repair weld procedures are required to
cover all circumferential butt welds, any longitudinal butt welds and attachment welds
including branch, weldolet, sockolet and pipe support welds.

All welding procedures should be submitted for approval on Form QW-482 of ASME Sec. IX.
The proposed WPS shall include but not be limited to the following :

a) Contractor's name
b) WPS number, revision and date
c) Welding process and type (manual, automatic, etc)
d) Joint design and sketch and sequence of passes
e) Base material P number and group number
f) Material type and grade
g) Pipe diameter and thickness range
h) Welding consumables - AWS classification, manufacturer, brand name, F number, A
number, size, etc.
i) Welding positions
j) Welding progression
k) Preheat temperature, minimum
l) Interpass temperature, minimum and maximum
m) Method of preheat application and measurement
n) Post weld heat treatment, holding temperature and time, heating rate, cooling rate and
method of application.
o) Type of current and polarity
p) Method of edge preparation
g) Method of back grinding
r) Gas shielding - flow rate and composition
s) Gas backing - initial duration of purging, flow rate, composition and duration
t) Current, voltage and welding speed for each layer.

Written approval by FEWA/Engineer is required prior to the use of any pre-qualified WPS.

4.2.2 Procedure Qualification Records (PQR)


Welding procedure qualification tests shall be conducted in accordance with ASME Section
IX and shall be carried out under the surveillance of FEWA/Engineer.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 6 of: 27
:
The results of the qualification tests along with the test reports shall be submitted in the
approved format, as recommended by ASME Sect. IX Code by the Contractor.
The procedure Qualification Record (PQR) shall include the following:

a) Contractor's name
b) PQR number and date
c) WPS number, revision and date
d) Welding process
e) Type (manual, automatic, semi-automatic)
f) Joint design and sequence of passes
g) Base material specification, grade, carbon equivalent, thickness and pipe diameter.
h) Filler metal AWS classification, size, manufacturer, brand name, A. No. and F. No.
i) Welding position and progression
j) Preheat temperature, method of application and measurement.
k) Interpass temperature
l) Post weld heat treatment, holding temperature, holding time, heating and cooling rates
m) Shielding gas, composition and flow rate
n) Backing gas composition and flow rate
o) Current type and polarity
p) Tungsten electrode type and size (for GTAW )
q) Orifice or gas cup size (for GTAW & GMAW)
r) Method of cleaning
s) Method of back grinding
t) Welding current, arc voltage, welding speed and heat input as per sect 6.3.7 for each
pass.
The Contractor shall submit the following back up certificates/reports for approval prior to the
commencement of production welding :

a) Welding procedure specifications (WPS), and Procedure Qualification Records (PQR)


revised if necessary.
b) Mill certificates of the test piece sample metal used.
c) Batch test certificates of the welding consumables.
d) Heat treatment charts, where applicable.
e) Non-destructive examination reports.
f) Mechanical test reports including photo micrographs.
g) Welding consumable control/electrode redrying procedure.

The sample welds shall be carried out on specimens of similar shape, thickness and chemical
analysis as of the material to be welded, and in a position, which shall represent as far as
possible the worst conditions under which actual welding would take place.NDE and
mechanical testing shall be conducted after post weld heat treatment where applicable. NDE
shall be conducted by American Society of Non Destructive Testing (ASNT) Level II or
equivalent certified personnel.Mechanical testing shall be carried out in accordance with
ASME Sec. IX in an approved testing laboratory using calibrated instruments.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 7 of: 27
:
4.3 Welders Qualification
Only approved qualified welders shall do all welding works at manufacturer/ fabricator works
or at site. Such welders shall be certified by a qualified independent testing authority. If not
otherwise agreed upon, the tests and certificates shall not be older than six months prior to
the time of execution of the welding works. The certificates shall be first submitted to FEWA/
Engineer for approval then be filed with the Contractor on site.

Welders engaged on welding at Site shall be under the supervision of a competent welding
engineer. The welding engineer shall exclusively employed for this work with due approval of
FEWA/Engineer.

4.3.1 Welder’s Qualification Tests


Welders and welding operators shall be qualified in accordance with ASME Section IX. And
the requirements stated hereunder.Automatic MIG/MAG/GMAW welding operators shall be
qualified by radiography and guided bend tests.

All welders and welding operators shall be qualified for all welding positions in which they will
carry out production welding. All welds executed by unqualified welders shall be rejected.No
welder shall be qualified on production welds.

A welder or welding operator who fails the performance qualification test of this
specification,may be granted an immediate retest in accordance with ASME Sec. IX (QW-321
solely at FEWA/Engineer discretion. If the welder or welding operator fails in the retest, he
may be given only one further test in accordance with QW-321.3 but only after he has
received adequate training to the satisfaction of FEWA/Engineer.

Welder’s valid qualificatrion shows that the welder or welding operator has been continuously
engaged on work of a similar nature with the specific welding process since successful
qualification. A break in continuity of more than 3 months (90 days) shall require
requalification.

All qualified welders for production welding shall be assigned a unique identification number
with welder's photograph on identification badges singed by FEWA/Engineer and to be worn
by the welders during welding.

4.4 Essential Variables


Where notch toughness is required as part of the mechanical tests for procedure qualification,
a change in any supplementary essential variable shall call for requalification of the welding
procedure. The following variables shall be treated as essential variables in addition to those
listed in ASME Sec. IX.

4.4.1 Base Material


Each base metal within a given P number or Group number having nominally different
chemical or mechanical properties (as Table QW-422 of ASME Sec. IX) require:

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 8 of: 27
:
a) Separate welding procedure specification (WPS)
b) Separate procedure qualification whenever a welding operation satisfactory for one base
material is, in the opinion of FEWA/Engineer, unsatisfactory for another base material
within the same P or Group number.

4.4.2 Welding Process


Any change in welding process, addition, deletion or combination of welding processes.

4.4.3 Joint Design


a) A change from double sided weld to a single sided weld but not vice versa.
b) An increase of more than 20° or a decrease of more than 10° in the included angle.

4.4.4 Base Material Thickness


The maximum thickness qualified shall be limited to twice the thickness of the test pipe.

4.4.5 Welding Consumable


The following will require procedure requalification :

a) Change in wire chemistry.


b) A change in filler metal.
c) A change in submerged arc welding flux. manufacturer's grade.
d) Changes in the chemical composition of the weld deposit A number.

4.4.6 Welding Position


Any change in welding position except that qualification in the 6G position or 2G plus 5G
positions will qualify for all positions.

4.4.7 Welding Parameters


Any change in the parameters affecting heat input (current, voltage and welding speed)
outside ± 15% of those qualified for root, fill and capping passes.
Heat Input = (current in amps x volts x 60)
(KJ/cm) (welding speed (cm/min) x 1000)

4.5 Qualification Tests


4.5.1 Non-Destructive Examination
The test weld shall be 100% visually examined.
After satisfactory visual examination, butt welds shall be subjected to 100% radiographic
examination.
Fillet welds shall be examined by magnetic particle inspection (MPI) for magnetic materials
and dye penetrant (DP) examination for non-magnetic materials.
The acceptance criteria shall be ASME B31.3, Table 341.3.2 except as modified by this
specification.

The Contractor shall supply a welding schedule indicating also the extent and kind of non-
destructive tests of the welds which are subject to approval by FEWA/ Engineer.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 9 of: 27
:
Unless otherwise agreed or specified 10% of normal weld works and 100% of all critical
welds are subjected to weld tests such as Ultrasonic tests (BS 3923) BS EN ISO 17640:2010
Non-destructive testing of welds. Ultrasonic testing. Techniques, testing levels, and
assessment or radiographic tests (BS 2600) BS EN ISO 17636-2:2013 Non-destructive
testing of welds. Radiographic testing. X- and gamma-ray techniques with digital detectors or
magnetic particle test (BS 4397) BS ISO 4397:2011.

If any defect is noticed in the welds the Contractor shall rectify the defect by cutting, replacing
and re-welding as if the process is being carried out freshly

4.5.2 Destructive Tests


The type, number and location of specimens to be removed from the test weld, test specimen
dimensions, testing procedure and evaluation of tests shall be in accordance with ASME Sec.
IX.All mechanical tests shall be conducted after post weld treatment wherever applicable.

4.6 Production Welding Requirements

4.6.1 Welding Equipment


All welding equipment shall be of sufficient capacity for the work to be performed and shall be
capable of producing welds of acceptable quality.
All equipment shall be maintained in good working condition by the Contractor.

Any equipment which does not meet these requirements shall be replaced.

All welding equipment and accessories shall meet the safety regulations of the relevant
international specifications (such as NEMA) and shall be safe to operate.

When using the GTAW process, a high frequency (HF) arc initiation unit, a controlled current
delay device (to eliminate crater) and suitable pre-end post-gas flow device (to eliminate
porosity and air entrapment) shall be used.

4.6.2 Welding Processes


Only approved welding processes shall be used for production welding.

4.6.3 Weather Protection

The Contractor shall provide approved adequate shelter to protect the welding environment
from inclement weather and drafts.No welding shall be carried out when the weld surfaces
are wet or dirty and if inadequate provision has been made for weather protection .

All surfaces to be welded and the adjoining area of the material shall be warm and dry.Where
the surfaces to be welded are covered by moisture and where there is no requirement of
preheat by the applicable WPS, the surfaces should be completely dried and warmed up by a

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 10 of: 27
:
hydrocarbon torch using a soft flame before starting to weld. The use of oxy-acetylene
torches shall not be permitted.

4.6.4 Welding Consumables


Electrodes, filler wires and fluxes shall conform to the requirements of ASME Boiler and
Pressure Vessel Code Section II Part C. Gases, both combustible and inert, shall meet the
requirements of American Welding Society or any other standard acceptable to
FEWA/Engineer.

The Contractor shall prepare and submit to FEWA/Engineer a list of welding consumables to
be used on the project showing type, manufacturer, brand and the manufacturer's
recommended storage and drying procedure for each.

Storage and control of welding consumables shall be in accordance with the following :

- All electrodes shall be stored in fully sealed packages and stored in dry storage rooms.
- All electrodes which are damaged, wet, rusty or contaminated with oil, grease, dirt etc.
shall be scrapped. Electrodes partly used shall not be used.
- The Contractor shall provide separate ovens for baking and storing of low hydrogen
welding consumables.
- SMAW electrodes of different weld metal compositions or having different flux type
covering shall not be stored or baked together in the same oven.
- Low hydrogen electrodes shall be baked at 300°C for at least one hour or as per
manufacturer's recommendations.
- Cellulose coated SMAW electrodes shall be kept in a dry and dust free enclosure after
opening of the factory container.
Filler wires, Fluxes and bare electrodes shall be stored in sealed, dirt and moisture proof
containers within a dry, dust-free enclosure.

Only fused type fluxes shall be used and they should be dried according to manufacturer's
recommendation. If agglomerated fluxes are used, they shall be baked at a temperature of
250°C - 300°C for a minimum of two hours and kept in drying ovens at all times.For carbon
steel materials, the SAW process shall not utilise an active (Mn-Si) flux nor EHXX (high
manganese) wires.

Only low hydrogen electrodes shall be used for the following cases with SMAW :

(a) Welding and/or installing hot-tap connections on pipes containing flammable liquids, gas
or combustible materials.
(b) For the repair of all welds in carbon steel plates.
(c) Full penetration double-groove joints.
(d) Fill and cap passes of all other applications for all carbon steels for all thicknesses.
With the exception of low hydrogen electrodes, (a) through (c), cellulose coated electrodes
may be used only for the root passes of carbon steels with prior written permission of
FEWA/Engineer.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 11 of: 27
:
Welding electrodes kept in the drying oven shall be consumed on "first in - first out" basis.

4.6.5 Electrode Size

(a) The maximum electrode diameter for all single sided welding using the SMAW process
shall be 3.2mm for the root pass and 5mm for the fill and cap passes.
b) The maximum electrode diameter for double sided welds using SMAW shall be 4mm for
the root pass and 5mm for the fill and cap passes.

4.6.6 Shielding Gases


The shielding gases are used for the protection of the electrode and the weld pool from the
surrounding air. Depending on the welding process adopted, parent material, weld
configuration and shielding gas shall be selected.

4.7 Cutting and Weld Joint Preparation


Preparation and cutting of carbon steels may be done by machining, grinding, machine
guided gas torch or plasma arc cuttings. Gas torch and plasma arc cutting shall only be used
where it is not practicable to use mechanical methods.

Thermal cutting is acceptable for carbon and low alloy steels. For plates less than 25 mm
thick, cold shearing may be used. For plates between 11 mm to 25 mm thick the cut edges
shall be dressed back atleast 2 mm by machining or grinding. The edges shall be inspected
by MP or DP method. For stainless steel material, flame cutting is not allowed but plasma
cutting may be applied.
End profiles of pipes and fittings which are to be butt welded shall be in accordance with
ASME B 16.25. Pipes for socket weld joints shall be cut square. All cut surfaces shall be
finally prepared by grinding or machining to clean, bright metal. After the edges have been
prepared for welding, they shall be visually examined to confirm that the preparations are
smooth and uniform and free from tears, cracks, gouges and other discontinuities which
might affect the weld quality.

Further the prepared welding ends shall be examined by ultrasonics for a distance of 50mm
back from the bevelled edge to ensure freedom from laminations, and magnetic particle
inspection on bevels. The use of arc air gouging shall not be permitted.Branch connection cut
outs shall be carefully bevelled and accurately matched to form a suitable groove for welding
and to permit complete penetration of the welds at all points.

4.8 Cleaning Requirements


All surfaces to be welded and the surrounding areas shall be clean and free of paint, oil
dirt,rust , oxides or any other foreign matter which could interfere with welding, prior to the
application of preheat or welding. The deemed surface shall extend at least 25 mm beyond
the substrate actually touched by the arc.

4.9 Edge Preparation and Joint Alignment


The edge preparation for butt joints shall be as indicated below:

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 12 of: 27
:
a) For piping with thickness upto 26 mm the preparation shall be 'V' type, with 370 30' + 20
30' bevelling.
b) For piping with thickness over 26 mm, the preparation shall conform to ASME B31-3, or
shall be of another type approved by FEWA/Engineer.
For butt welding of all piping components, pipe ends, fittings and welding neck flanges, a
uniform root opening its required as shown:

<DN 50 mm 1.5 mm
DN 50 to DN 250 mm 1.5 to 2.5 mm
>DN 250 mm 2.5 to 3.5 mm

Butt weld alignment shall satisfy the requirement of ASME B31.3 and the conditions stated
below.Internal misalignment of pipework shall not exceed 1.0mm in order to facilitate welding
of the root pass. When a GTAW root pass is to be used the maximum misalignment shall not
exceed 0.8mm Misalignment may be reduced by the use of hydraulic or screw type of
clamps.

Hammering heating and buttering of weld shall not be permitted.In case of pipes/components
with different thickness misalignment upto 3.2 mm may be improved by internal machining
provided the taper does not exceed 1 in 4 max. However the minimum required wall
thickness shall be maintained. Grinding shall not be used.Correction of misalignment by use
of cold working shall not be permitted.

Where internal pipe aligners are used, they shall not be removed until the root pass has been
completed. Where external lineup clamps are used, the clamp may be removed when the
root bead is at least 50% completed. The root bead should be spaced evenly around the
circumference.The longitudinal welds of adjacent pipes shall be staggered by at least
100mm.

4.10 Tack Welds


All tack welds shall be made by qualified welders using approved electrodes and pre-heat, as
specified by the approved welding procedures.Tack welds to assist alignment shall have a
minimum length of 25mm and shall be of sufficient size to maintain joint alignment until
production welding begins.All tacks welds which will be part of the main welds shall be
cleaned, ground to a feather edge at both ends and visually inspected prior to welding of the
root pass.

Any defective tack shall be completely removed by grinding prior to welding of the root pass.
When tack welds are removed, the Contractor shall ensure that the root preparation is
correctly maintained for the subsequent pass.Tack welds not incorporated in the final weld
shall be removed by grinding or other mechanical means to achieve smooth surface without
reduction in wall thickness, followed by Non destructive test inspection.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 13 of: 27
:
4.11 Joint Backing Requirements
Permanent backing rings or backing plates shall not be used.The use of consumable inserts
for root passes shall not be permitted.

4.12 Heat Treatment of Welding Works


Heat treatment prior to and after welding in order to achieve stress relieving shall be applied
as specified in the following table:
Welding after stress relieving is basically prohibited. Should welding on a piece of equipment
which has previously undergone a stress relieving heat treatment become necessary, the
relevant piece shall undergo a new stress relieving process.

Welding Heat treatment

Material Pre-heating After-heating

Temperature Wall thickness Temperature Wall thickness

St 35 - - 650-700C Above 20 mm

St 35.8 - - 650-700C Above 20 mm

St 45.8 - - 650-700C Above 10 mm

15 Mo3 150C Above 10 mm 660-700C Above 15 mm

13CrMo44 200-300C Above 10 mm 680-720C Usual (*)

10CrMo910 200-300C Above 6 mm 730-780C Usual (*)

X20CrMoV121 400-450C All 720-780C All

(*) Not necessary for fusion butt-welded pipes with DN <51mm and Wall thickness 
8 mm

Above table of heat treatment shall be completed by a supplementary table including all heat
treatment recommended for any other material included in the Contract subject to welding
either at workshop or at Site. This supplementary table shall be supplied to FEWA/ Engineer
for approval not more than 3 months after Award of Contract.

4.12.1 Preheat Requirements


Preheating of the parent metal prior to any welding, tack welding and thermal cutting can be
necessary to minimise the detrimental effects of high temperature and severe thermal
gradients inherent in welding.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 14 of: 27
:
4.12.2 Preheat Temperatures
The minimum pre-heat temperature for welding, flame cutting and arc cutting shall be as
specified below. Where welding procedure specification (WPS) indicates that a higher
preheat temperature is necessary, this shall be used for production welding.

Materials Minimum Temperature


Carbon steels upto 25mm thick 10 Deg C (50 Deg F)
Carbon steels above 25mm thick 79 Deg C (175 Deg F)
Austenitic stainless steel (all thickness) 10 Deg C (50Deg F)

The determination of pre-heat temperature for carbon steel production welds should be based
upon ASME Section 1X Code after consideration of specific heat input, joint thickness metal
composition, welding process and welding consumables.

Unless notified otherwise by FEWA/Engineer the following criteria should be used to


determine preheat levels :

(1) The relevant carbon equivalent (CE) should be calculated from the maximum CE allowed
by the material specification.
(2) Consideration should be given to joint restraint as in case of branch connections
(weldolets, sockolets and nippolets).

When the base metal temperature is below 21 deg.C for carbon steels, the material shall
bepreheated to 50 deg.C prior to welding.Whenever material is wet or contains surface
moisture or condensate, it shall be dried by heating. The fusion faces and 100 mm on each
side of the welds shall be preheated up to 50 deg.C.

4.12.3 Application of Preheat


Preheat shall be applied by electrical resistance methods. Preheating methods with
hydrocarbon gases shall only be used with prior written approval of FEWA/Engineer.The use
of oxy-acetylene torch for preheating is prohibited.Preheat shall be applied in a gradual and
uniform manner and shall be maintained throughout the welding operation.

The minimum preheat temperature shall be established on both sides of the joint
preparationfor a minimum distance of 75 mm or 3 times the material thickness whichever is
greater. If possible, the preheat temperature shall be measured on the opposite face to that
being heated. Where access to only one face is possible, the heat source shall be turned off
to allow for temperature equalization (one minute for each 25mm of wall thickness) before
measuring the preheat temperature.

The preheat temperature shall be held for at least 5 minutes before welding is
commencedand shall be checked before and during welding by thermo-couples, contact
pyrometer or bytemperature indicating crayons. (colour charging crayons shall not be used)

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 15 of: 27
:
4.13 Interpass Temperature
Interposes temperature is the temperature at which the weld area must be before the
nextpass is started.The maximum interpass temperature shall not exceed the following limits
unless stated in the approved welding procedure specifications (WPS):

(a) Carbon Steels : 250 0C


(b) Austenitic Stainless Steel : 175 0C

The interpass temperature shall be measured at a distance of about 12.5mm from the bevel
ends and shall be measured by contact pryrometer, thermo-couples or temperature indicating
crayons. (colour changing crayons shall not be used)

4.14 Interruption of Welding


Welding of each joint should be a continuous operation. No weld shall be allowed to cool
unless at least 3 runs have been deposited and 50% of wall thickness is deposited. If for any
reason welding is discontinued, the following criteria shall apply:

a) If 3 runs, and 50% wall thickness has not been deposited, then the weld should be cut
out and recommenced from a new preparation.
b) If 3 runs, and 50% wall thickness have been deposited then the welding operation may
commence provided the following conditions (c) and (d) are met:
c) The weld on interruption shall be allowed to cool slowly from welding temperature to
room temperature (this may be done by wrapping the weld with insulation and allowing
the joint to cool in still air.)
d) Before welding is resumed the weld shall be preheated to the specified temp, after a
close visual or MPI as required by FEWA/Engineer.

Root runs and second passes (hot passes) shall be made without interruption other than
forchanging electrodes or filler wires or to allow welders to reposition themselves.The second
pass (hot pass) of carbon steel pipe welds shall be deposited immediately after the root pass
in order to prevent "cold cracking' in the root area due to shrinkage stresses and joint
restraint.

4.15 Weld Bead Sequence


Weld bead deposition shall be established during welding procedure qualification and shall be
indicated on the joint design of the Procedure Qualification Record (PQR). The specified
welding sequence shall be adhered to during production welding.Adjacent weld beads shall
be staggered and not started from the same location.Welding shall be carried out in a
sequence which will minimize distortion.All welds shall be full penetration welds apart from
the following:

a) Socket welds which may be used on pipe of nominal size DN 40 mm and less, as defined
in the contract drawings.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 16 of: 27
:
b) Pipe support attachment welds.
c) Fillet welds, as specified, which shall be continuous.

Where access permits, pipework with nominal size over DN 600 mm shall be welded from
both sides. Double sided welds shall be back-gouged to sound metal and ground smooth
prior to welding from the second side. However the Contractor shall ensure safe working
atmosphere like ventilation/fume extraction/respirators etc. is provided in order for the welder
to perform the welding.

All pressure containing welds shall have a minimum of three passes with overlaps of starts
and stops. This shall include seal welds of threaded connections and socket
welds.Longitudinal butt-welded pipe fittings are not allowed without written approval of
FEWA/Engineer.

4.16 Interpass Cleaning


After each welding pass, the weld shall be cleaned of all flux, slag and spatter by power
wirebrush, grinding or hand chipping tools. In case of root pass the weld shall be
ground.Every welding pass shall be visually examined by the welder to ensure that the weld
is free from slag, porosity and uneven contour before the start of the next pass.Any defects
found shall be removed or repaired prior to the start of the next pass.Any cracks found shall
be brought to FEWA/Engineer's notice before removal and restart of work.Upon completion of
the weld, the adjacent surfaces shall be cleaned of all spatter, slag, flux,soot and other
foreign materials.

4.17 Peening
No weld peening of any sort shall be permitted.

4.18 Seal and Socket Welding


Sealing compound or Teflon tape shall not be used on joints which are to be seal
welded.Seal welding of threaded connections shall cover all exposed threads. Seal welds
shall contain a minimum of two passes and shall extend from the outer diameter of the fitting
smoothly to the nipple surface without any undercut.Seal welding shall be carried out using a
low heat-input welding process such as GTAW or SMAW. When SMAW process is used, the
electrode size shall not exceed 3.2 mm in diameter.

During socket welding, the inserted end of the pipe nipple shall not come in contact with the
bottom of the socket. A minimum clearance of 1.6mm shall be given prior to welding. Use of
contraction rings to achieve minimum clearance are not allowed without written approval of
FEWA/Engineer.

4.19 Attachment Welds


Fillet welds used for attachments shall be carried out by qualified welders using approved
electrodes and preheat as specified by FEWA/Engineer approved welding procedure.Fillet
welds shall have proper fusion and penetration at the root of the joint. Fillet welds shall fuse
gradually into the pipe and be free from marked irregularities, convexity/concavity and

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 17 of: 27
:
undercut.Temporary attachments welded to pipework to facilitate fabrication shall be
permitted with the prior approval of FEWA/Engineer.All temporary attachments shall be
completely and carefully removed checked by DP/MPI test prior to any post weld heat
treatment. Removal of temporary attachments by hammering or bending is not permitted.

4.20 Weld Spacing


Distances between welds shall be measured between the adjacent edges of the cap
passes.Weld joints shall not be arranged so close to each other. Sufficient weld clearance
shall be maintained to prevent thermal stresses near the joint. Circumferential butt welds on
the pipeline shall be separated by maximum possible distance. Longitudinal butt welds of
adjacent pipes shall be separated by at least 100 mm or 5 times the thickness of the thicker
pipes whichever is greater.
Should the site conditions warrant, short pipe lengths between fittings can be used and its
butt welds shall not be closer than 75 mm or 5 times the thickness of the thicker pipes
whichever is greater.Branch/nozzle and other pressure attachment welds shall not be closer
than 75mm to adjacent pressure welds.

Cases which fail to meet this criteria shall be referred to FEWA/Engineer for approval prior to
the commencement of fabrication.Non-pressure containing attachment welds, such as pipe
support welds shall be at a minimum distance of 50mm from any pressure containing
welds.Where pup sections are to be inserted, the length of such insert pup sections for both
new and existing fabrication shall not be less than three pipe diameters, or 150mm whichever
is greater.

4.21 Workmanship and Weld Finish


The welding arc shall be struck inside the joint groove or where the weld is to be made. Arc
strikes, gouges and other indications of careless workmanship outside the weld arc shall be
carefully removed by grinding and the ground area shall be examined by MPI or Dye
penetrant test, and ultrasonics to ensure min. wall thickness is maintained.

Arc strikes, gouges etc. outside the fusion face shall be limited to one per pipe and one per
joint.Repair of Arc strikes shall be at the discretion of FEWA/Engineer.If resultant wall
thickness after grinding is less than the minimum design thickness, the position of pipe
containing arc burn shall be removed as a cylinder.Insert patching and rewelding to increase
the wall thickness shall not be permitted.

Coated surfaces shall be protected from the welding arc and the associated weld
spatter.Weld reinforcement and internal weld protrusion shall be as required by ASME B31.3
but in no case shall the height exceed the weld crown.Excessive internal weld protrusions on
accessible joints shall be removed by grinding. Welds having excessive protrusions on
inaccessible joints shall be cut and re-welded.

Welds which are to be examined by non-destructive testing shall be appropriately surface


finished to facilitate easy interpretation of results.External weld undercutting shall not be
permitted.The acceptability of fillet welds shall be established by suitable gauges or

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 18 of: 27
:
templates. The minimum required size of each fillet weld shall be as specified in the
applicable drawing.

Where leg length is specified, the throat thickness for a 1 x 1 fillet weld shall be from 0.7 to 1
times the required leg length. The throat thickness for a 1 x 2 fillet weld shall be 0.7 to 1.2
times the size of the shorter leg.

4.22 Welding Technique


Wherever possible, welding should be carried out with minimum weaving.The width of weave
during production welding shall be within acceptable limits of FEWA/Engineer approved and
qualified welding procedure. In no case shall the width of weaving exceed three times the
core wire diameter or 12 mm whichever is less for SMAW.

For SAW process, welding shall be done without any weaving (oscillation.)All pressure
containing welds shall have at least two passes with overlapping starts and stops.Only single
electrode processes shall be used. Use of multiple electrodes shall require prior
FEWA/Engineer approval.Welding of all pressure containing welds shall be done with direct
current unless otherwise previously approved by FEWA/Engineer.All vertical welding shall be
done uphill. Downhill ('stove-pipe') welding of pressure containing welds shall not be
permitted.

4.23 Post Weld Heat Treatment


Post Weld Heat Treatment shall be required under the following conditions:

a) All carbon steel pipework when the material thickness through a butt weld joint exceeds
19mm.
b) Carbon steel pipework subject to vibration, such as compressor piping, when the
material thickness through the butt weld joint exceeds 12.7mm.
c) Carbon Steel branch connections when the thickness in any plane through the branch
weld exceeds thickness requirements as indicated in ASME B31.3 para 331.1.3.
d) Wherever required for the fabrication of fittings as applicable.

Post weld heat treatment shall be carried out as soon as possible after completion of welding
and shall be conducted in accordance with ASME B31.3 except as modified by this
specification.The temperature controls during heating and cooling shall meet the
requirements of ASME Sec. VIII Division 1.
A post weld heat treatment (PWHT) procedure shall be submitted for FEWA/Engineer
approval prior to any PWHT being conducted.Wherever possible PWHT shall be conducted in
an enclosed furnace. For site or field welds,local PWHT by electrical resistance method shall
be conducted.

The use of manually operated gas torches or gas rings or proprietary exothermic kits shall not
be permitted.Where Local PWHT is done, the weld being post-weld heat treated shall be in
the centre of the heated band. The heated band shall be sufficiently wide such that a band at

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 19 of: 27
:
least 25mm on each side of the weld edges reaches the specified temperature range. There
shall be sufficient insulation to avoid an undesirable temperature gradient.

During furnace or local post-weld heat treatment, there shall be a minimum of 4


thermocouples (or as otherwise approved by FEWA/Engineer) used to ensure that thermal
gradients outside the requirements of this specification do not occur during the heat treatment
cycle. Thermocouples shall be positioned at a distance of 25mm from the weld edges on
each side of the weld. The minimum number of thermocouples required may be decreased
only with prior FEWA/Engineer approval.

A time temperature chart recording the thermal history of the part heat treated shall be
provided by the Contractor. The chart shall be clearly identified with the drawing/ISO number,
part and weld number an signed by the CONTRACTOR and certifying authority where
applicable. The chart shall be included in the project record work/"As-built"
documentation.Thermocouples shall, if possible, be placed on the inside for objects being
heated from the outside, and vice-versa, if internally heated.

Thermocouples and temperature recording equipment shall be calibrated prior to use and
shall have a valid certification by a reputed certifying authority.Welding shall be avoided on
any post-weld heat treated material. If any welding is to be carried out on any post weld heat
treated material, this shall be referred to FEWA/Engineer.

Failure to do so will call for repeating heat treatment.All machined surfaces such as pipe
ends, flange faces and threads shall be suitably protected during the PWHT cycle.NDT of
welds, where applicable, shall be conducted after PWHT for final acceptance.

4.24 Weld Identification


Each weld shall be uniquely identified with a weld number and ISO/drawing number and the
same must be represented on the weld identification/NDT drawings. After the completion of
each weld and prior to its visual examination, the weld and welder identifications shall be
marked adjacent to the weld at a distance of about 50mm from the weld using paint or
indelible crayons. This identification shall remain on the pipe till the completion of all NDT for
any verification by FEWA/Engineer.

5. INSPECTION AND TESTING


5.1 General
Contractor to include the provision of service by FEWA/Engineer approved third party
inspection (TPI) subcontractor to cover inspection activities in addition to Contractor ‘s own
inspection.Contractor shall submit to FEWA/Engineer his proposed QA/QC/Inspection
organisation.The Contractor shall submit detailed non-destructive examination (NDE)
procedures for FEWA/Engineer approval.

All NDE shall be carried out in accordance with the procedures approved by
FEWA/Engineer.The radiographic inspection procedures shall include film-processing
procedures to be usedfor non-destructive examination (NDE).The Contractor shall

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 20 of: 27
:
demonstrate, to the satisfaction of FEWA/Engineer nondestructive testing production
technique of exposure, film screen combination, use of lead screens, and film processing and
handling are satisfactory and meet this specification.

The Standard Test Radiograph shall be repeated at the option of FEWA/Engineer whenever
any change has been made in the operation procedure or whenever production films vary
appreciably in details, contract or density, from the Standard Test Radiograph.Radiographic
inspection shall be conducted by the use X-rays. Gamma ray examination may only be used
with the approval of FEWA/Engineer.

The Contractor shall submit detailed radiation safety procedures which comply with FEWA
safety regulations.Radiographic inspection shall comply with the relevant safety codes and
radiation control procedures. Special attention is drawn to the necessity for audible and visual
warning devices and for regular monitoring of radiation levels.Radiographic procedures shall
be qualified using both source and film side penetrameter.

Each radiographic film shall contain the following identification information:


 Project identification
 Weld number
 Welder number
 Pipe diameter and wall thickness
 Date
 Film location markers related to the area of weld that the radiographic covers
 NDE Contractor's symbol
 Weld thickness
 Image Quality Indicator

The zero datum shall be top dead centre of the pipe. Defect location shall be in metric units
system. Each radiograph shall have reference markers at 10 cm intervals.The letter "R" shall
appear on all radiographs of weld repairs in addition to the above information.The RT films
shall be stored and kept by the Contractor until final handing over, and shall be available at
anytime for FEWA/Engineer review.

Prior to the commencement of work, the Contractor shall establish an identification system
such that each assembly, each component and each weld can be uniquely and fully identified
with welder/welding operator, welding procedure specification (WPS), NDE
procedure/technique, extent of NDE and NDE results.Procedures for radiography, ultrasonic,
magnetic particle and dye-penetrant examination shall all be conducted in accordance with
ASME Section V.

All personnel performing NDE shall have ASNT Level II or equivalent certification as
approved by FEWA/Engineer prior to the commencement of work.The Contractor must
submit weld map showing NDE system for written FEWA/Engineer approval prior to the
commencement of fabrication.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 21 of: 27
:
5.1.1 Reduced Percentage Examination
For any examination frequency less than 100%, say 'X' percent examination (X may be 5, 10
or 25%), the following rules shall apply:

(a) At least 'X' percent of the total number of welds within the specified line class shall be
examined for 100% of their length (circumference).
(b) At least 'X' percent of the total number of welds on each isometric shall be examined and
shall not be less then one weld per isometric.
(c) At least 'X' percent of the total number of welds made by each welder shall be examined
for 100% of their length. At least one complete weld shall be examined for each welder.
(d) Examinations shall be representative of the entire range of pipe sizes and joints that
have been welded.
(e) Where reduced percentage examination is required and the resulting test shows defects,
then additional examinations as required by ASME B 31.3 para 341.3.4 shall apply
regardless of the examination process used.
(f) Defect acceptance criteria for all reduced percentage examinations shall be the same as
for 100% examination.
(g) 'X' percent shall be determined by FEWA/Engineer and shall be specified for each piping
class.

5.2 Visual Examination


Prior to visual examination, welds and the adjoining areas shall be thoroughly cleaned free of
all slag, mill scale, dirt, weld spatter, paint, oil, flux, stub ends and other foreign matter.The
Contractor shall provide easy access to the pipework for inspection. This will include the
provisions of ladders and scaffolding when required.

The workmanship and weld finish shall be as per this specification.Weld acceptance criteria
for visual examination shall be as per ASME B31.3, Table 341.3.2 except as modified by this
specification.

5.3 Radiographic Examination


Radiographic procedures shall be in accordance with the methods described in ASME
Section V Article 2 except as modified by this section.Radiographs should be evaluated in
accordance with ASME B31.3, Table 341.3.2, except as modified by this specification.Only
fine grain, high contrast film or ultra fine grain high contrast film shall be used. Type 1film
(AGFA, structurix D4 or equivalent) of ASTM E94 shall be used for gamma ray radiography of
pipes with wall thicknesses below 10mm.

Gamma radiography shall only be used if it can be proven that the required sensitivity can be
achieved.Wherever possible, DIN penetrameters (wire type Image Quality Indicators) shall be
used.Radiographic sensitivity shall be 1.8% or better.Where film side IQI's are used,
correlation of sensitivity with source side IQI'S shall be established before proceeding with
inspection.Only lead intensifying screens shall be used.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 22 of: 27
:
The radiographic density in the diagnostic area shall be between 2.0 and 3.5All burn-through
shall not be permitted.Radiography shall be conducted after any required PWHT for final
acceptance.

5.3.1 Reporting
The radiography report shall include the following information:
- Contract number
- Project title
- Name of the component
- Source type (X-ray/Ir-192)
- Source strength (mA/curies)
- Focal spot size
- Technique (SWSI/DWDI/DWSI/PANAROMIC)
- Film type and size
- Penetrameter type and number
- Exposure time
- Developing time and temperature
- Density
- Sensitivity
- Lead screens (front and back)
- Specification (ASME B31.3)
- Weld identifications
- Pipe diameter and wall thickness
- Welder identification
- Interpretation
- Remarks (Accept/Reject)
- Radiographer's name and signature
- Date of exposure

5.4 Ultrasonic Examination


The Contractor shall submit an ultrasonic examination procedure for all full penetration butt
and branch welds for FEWA/Engineer approval prior to the commencement of examination of
production welds.Ultrasonic examination shall be carried out in accordance with ASME
Section V Article 5, except as modified by this section and the results shall be evaluated in
accordance with ASME B31.3 Table 341.3.2.

The ultrasonic equipment shall be checked for linearity, db attenuation etc. and a valid
calibration certificate shall be submitted for FEWA/Engineer review, prior to use.As a
minimum requirement, ultrasonic examination shall be conducted using a minimum of three
transducers, one 0° compression and two angle beam transducers with a frequency of 1 to 5
MHZ. Where access permits, ultrasonic examination shall be conducted from both sides of
the joint.

Prior to conducting ultrasonic examination, the Contractor shall ensure that the weld and the
surrounding area are sufficiently smooth to avoid false or misleading indications. Transfer

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 23 of: 27
:
correction should be applied to accommodate surface curvature and roughness.Branch
connections that include a reinforcing pad plate shall be examined after welding the branch to
the header and again after welding on the reinforcing plate.

The test report should outline the technique employed, type and size and frequency of probes
used, and defects discovered and shall contain the following information as a minimum:
(a) Weld identification and welder number
(b) Weld procedure used
(c) Size of reportable defect
(d) Depth of reportable defect
(e) Location and orientation of reportable defect (with a sketch)
(f) Weld acceptable/not acceptable.
(g) Specification
(h) Inspector's name and signature
(i) Date of Examination
(j) Scanning Diagram.
Ultrasonic examination of welds shall be conducted after PWHT that may be required for final
acceptance.

5.5 Magnetic Particle/Dye-Penetrant Examination


Magnetic particle examination shall be carried out on magnetic materials.Dye-penetrant
examination shall be carried out on non-magnetic materials (stainless steels and non-ferrous
materials).Weld areas to be examined by magnetic particle/dye-penetrant examination shall
be sufficiently smooth to avoid spurious indications that may result from irregular weld
surfaces.All magnetic particle examination shall be carried out by alternating current yoke
method with a white background and black magnetic ink.

Magnetic particle examination shall be carried out in accordance with ASME Section V Article
7. Dye-penetrant examination shall be carried out in accordance with ASME Section V
Article6. The acceptance criteria shall be as per ASME B31.3 and Table 341.3.2.Where
PWHT is required, magnetic particle/dye-penetrant examination shall be conductedafter
PWHT for final acceptance. Examination shall be conducted before PWHT for any
repair/rectification that may be required before PWHT.

5.6 Ultrasonic Thickness Measurement


Ultrasonic thickness measurements, where required by the ASME B31.3 code, and/or by
FEWA/Engineer, it shall be done with Ultrasonic Flaw Detectors. The use of D-Meters is not
permitted for thickness measurements.Where specified by FEWA/Engineer, ultrasonic
thickness measurements shall be made on both sides of welds at a distance of 25mm from
the weld edges.
The thickness readings shall be recorded on NDE spool drawings.

5.7 Extent of Non-Destructive Examination

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 24 of: 27
:
The minimum requirements of non-destructive examination of welds shall be as per
ASMEB31.3 code. More stringent NDE may be specified based upon materials of
construction,service severity and/or testing limitations.

5.8 NDE Personnel Qualifications


Welding inspectors shall be certified to AWS or equivalent.All personnel carrying out non-
destructive examination (radiography, ultrasonic, magnetic particle and dye-penetrant
examination) shall be ASNT Level II certified or equivalent.

Where the NDE technician is certified by the Contractor himself, the qualification shall be in
accordance with Contractor's written procedures which shall use ASNT'S recommended
practice No. SNT-TC-1A, as a guide. This written procedure shall be subject to
FEWA/Engineer approval.

New qualification tests may be required if a technician's performance indicates


deficiencies.The Contractor shall bear all costs for qualifying technicians and FEWA/Engineer
Inspector will have the option to witness any qualification tests.The Contractor shall have
records of qualifications and certificates for each technician available for review by
FEWA/Engineer prior to the commencement of work by the technician.Any technician may be
disqualified by FEWA/Engineer upon proof of unethical practices, negligence, non-
compliance with procedures or poor performance.

5.9 Repair of Defects


5.9.1 General
Prior to carrying out any repairs involving welding, the Contractor shall submit a written repair
welding procedure to FEWA/Engineer for approval.This shall include details of the type and
extent of defects, method of removal, preparation of area to be welded, method of application
of preheat, reference welding procedure specification and NDE procedures.Acceptance of all
repair work shall be subject to FEWA/Engineer approval.

5.9.2 Minor Surface Repairs


Minor surface imperfections may be removed by grinding provided that the wall thickness
isnot reduced locally by more than 12.5% of the nominal value specified or the minimum
design thickness whichever is greater and the minimum wall thickness is maintained, which
will be verified by ultrasonic thickness survey.The ground area shall be dressed to a uniform
and smooth profile with no sharp corners ornotches.The ground area shall be examined by
MPI or dye-penetrant examination to ensure that the defects have been completely removed.

5.9.3 Repairs Involving Welding


Any defect that cannot be removed by surface grinding shall be repaired by welding.Any
defect exceeding acceptance criteria of this specification shall be carefully removed by
grinding.The excavation shall extend at least 25mm beyond both extremities of the defect
without substantial removal of the base metal and shall be done in such a manner that the
remaining weld or base metal is not nicked or undercut.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 25 of: 27
:
The grooves shall be free from scale, have a smooth contour to facilitate welding. Surface
should be ground to a smooth, bright metal surface.The ground area shall be carefully
examined visually and then by MPI or dye-penetrant examination prior to commencement of
re-welding to ensure that the defect has been completely removed.

The area to be repaired shall be pre-heated to at least 50 deg.C above the temperature
specified in the corresponding initial welding procedure but shall not exceed the maximum
interpass temperature. Repair welding shall be carried out using the approved repair welding
procedure. The Contractor shall take appropriate care such as proper weld sequencing,
control of interpass temperature etc. to minimize residual stresses.

All repair welding shall be carried out by qualified welders.If any repairs are carried out after
PWHT or hydrostatic test, the PWHT and hydrostatic test shall be repeated.Planar defects
such as cracks etc. shall not be permitted. Such joints containing cracks shall be cut out.

5.9.4 NDE of Repair Welds


All areas repaired by welding shall be thoroughly cleaned free of slag, spatter etc. and ground
to a smooth contour with the parent material and existing weld taking care that over-grinding
does not occur.The repaired weld shall be subject to 100% visual examination and then NDE
by the same techniques used for the original examination. The acceptance criteria shall be
the same as for the original welds.A weld with defects may be only repaired twice.
If the repair is not acceptable after the second repair, the complete weld shall be removed,
rebevelled, re-welded and re-examined.

5.9.5 Limitations on Repairs


Repairs shall be limited to 30% of the weld length. For internal repairs or external repairs
which open the root, only 20% of the weld length shall be repaired. Repairs opening the root
shall only be carried out in the presence of FEWA/Engineer. The minimum length of a repair
area shall be 25 mm.If the repairs cannot be carried out without exceeding these limitations,
or not carried out successfully, the weld shall be cut out.

5.9.6 Additional Acceptance Criteria


Defect Acceptance levels shall be as per ASME B31.3. Hollow bead porosity and concave
root shall not be permitted.Visual Acceptance standard for undercutting length shall be as per
API 1104, Section 6.7.

The Contractor shall have the various inspection stages witnessed and reports reviewed by
FEWA/Engineer."Acceptance" by FEWA/Engineer does not relieve the Contractor of his
responsibility to fulfill his contractual obligations.

6. WELDING OF D.I. PIPES ON SITE

On-site welding of D.I. pipes, fittings, flanges and the like shall be by electric arc in
accordance with approved international standards and procedures. Welding shall only be

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 26 of: 27
:
carried out by welders well qualified and experienced in this work. The welders shall be
subject to FEWA approval.

Prior to any welding, the parts to be joined must be thoroughly cleaned by grinding or filing in
order to obtain a bright metallic surface. Any coatings which might stick to the tools shall be
scraped off or must be removed by chemical means (e.g. turpentine). All surfaces shall be
free of zinc.All parts to be welded shall be kept dry and shelters shall be erected over the
working area in the event of inclement weather.

Welding shall be carried out using sheathed nickel-iron electrodes containing approximately
50% nickel. Welding shall be either by alternating current or direct current on the negative
pole. The current shall be 110 - 120 amps. Preheating or post -heating shall be applied as
and when required. All parts to be welded shall be held firmly in jigs or clamps. Restraining
beads on spigot ends shall follow a copper gauge held tightly around the pipe in accordance
with pipe manufacturer recommendations. No undercutting shall be permitted.

All welds shall be allowed to cool naturally without forced ventilation. They shall be cleaned of
slag and as a minimum requirement painted with one coat of Zinc rich paint and one coat of
bituminous paint giving a minimum dry film thickness of 150 microns. Where specific coatings
are required then the same coating specification shall be applied to the welded item.

All internal cement mortar linings shall be made good in accordance with the specifications.
Any damaged or rejected pipe work shall be replaced by the CONTRACTOR at his own
expense. No on-site welding of D.I. pipes shall be allowed prior to having written approval
from FEWA.

7. VENDOR DOCUMENTATION
The as-built QC dossier shall include the following:

(a) Material identification/traceability reports for each item in the contract drawings.
(b) Mill certificates of all materials giving the chemical composition and mechanical
properties.
(c) FEWA/Engineer approved procedure specifications (WPS)
(d) FEWA/Engineer approved Procedure Qualification Records (PQR) along with backup
NDE and mechanical test reports.
(e) List of Qualified Welders and Welder Performance of Notification Certificates.
(f) NDT reports.
(g) As-built drawings.
(h) Weld identification drawings.
(i) NDT summary control sheets, which show weld numbers, type and extent of NDT for
each weld, report numbers for each weld identification drawing and welding date.
(j) Heat treatment reports and charts.
(k) Dimensional inspection reports.
(l) Hydrotest reports.
(m) Blasting and painting reports.

client: FEDERAL ELECTRICITY AND WATER AUTHORITY (FEWA)


project: STANDARD SPECIFICATIONS FOR WATER WORKS

Engineer WATER DIRECTORATE - ASSET MANAGEMENT DEPARTMENT

title: Technical Terms / Chapter 4/ Engineering Specifications / Pipeline Works Specifications.

WAM PS14- WELDING WORKS


office: DUBAI order: document: MWA_PRO_07/WAM-04-PS14 rev: DEC/2014 sheet 27 of: 27
:

You might also like