2 Stories Building
2 Stories Building
2 Stories Building
Summary
Excavation $ 14,669.20
Carpentry $ 93,479.73
Roofing $ 21,249.90
Painting $ 22,018.39
Subtotal $ 303,322.87
Subtotal $ 479,250.14
Subtotal $ 527,175.15
Site works
Supervision
Allowance for full-time supervision of the works by a
8 suitable qualified and experienced individual as named and
detailed within the tender document
Additional Items
9 The contractor should read and familiarise himself with the 1
preliminaries section of the tender document item
Site Clearance
10 Allowance for site Clearance 1 item $ 1,500.00
Landscaping
11 Allow a provisional sum for landscaping to site 1 item $ 500.00
Sewerage Work
12 Allow the provisional sum of SBD$1000 for sewage 1
connection inclusive of all excavation,backfilling etc item $ 1,500.00
Water Connection
13 Allowance for connecting water to the local mains water 1
supply item $ 2,500.00
14 Allowance for providing and maintaining First Aid Kit and 1
all necessary safety equipment item $ 250.00
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION
3 CONCRETE
SUB-STRUCTURE
25 Mpa strength concrete as specified in
:
1 800x800 pad footing 3 m³ $ 1,800.00 $ 5,400.00
2 400x400 pad footing 0.5 m³ $ 1,800.00 $ 900.00
3 450x300 strip footing 3 m³ $ 1,800.00 $ 5,400.00
4 300x150 R footing 0.3 m³ $ 1,800.00 $ 540.00
5 90mm concrete slab 5 m³ $ 1,800.00 $ 9,000.00
6 250Ø column 15 m³ $ 1,800.00 $ 27,000.00
SUPERSTRUCTURE
7 300X160 suspended beam 1 m³ $ 1,800.00 $ 1,800.00
FORMWORK
SUBSTRUCTURE
8 sides of pad footing 11 m² $ 138.40 $ 1,522.40
9 sides of strip footing 39 m² $ 138.40 $ 5,397.60
10 sides of 250Ø column 12 m² $ 138.40 $ 1,660.80
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION
CONCRETE FILLING
2 Fill all cell with 25mpa concrete 1.2 m³ $ 1,800.00 $ 2,160.00
BOQ FOR PROPOSES 2 STORY BUILDING AT XXX LOCATION
STRIP FOOTING
4 D12 139 L/M $ 7.60 $ 1,056.40
5 R6 ties 54 L/M $ 2.60 $ 140.40
6 Galvanized Tie wire 25 kg $ 27.00 $ 675.00
RF
7 D12 19 L/M $ 7.60 $ 144.40
8 R6 ties 7 L/M $ 2.60 $ 18.20
9 Tie wire 10 kg $ 27.00 $ 270.00
CIRCULAR COLUMN
10 D12 106 l/m $ 7.60 $ 805.60
11 R6 ties 56 l/m $ 2.60 $ 145.60
12 Galvanized Tie wire 25 kg $ 25.00 $ 625.00
BLOCK WORK
13 D12 87 l/m $ 7.60 $ 661.20
14 Galvanized Tie wire 10 l/m $ 27.00 $ 270.00
SUSPENDED BEAM
15 D12 93 l/m $ 7.60 $ 706.80
16 R6 stirrup 47 l/m $ 2.60 $ 122.20
17 Galvanized Tie wire 15 kg $ 27.00 $ 405.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOACTION
Internal walls
5 100x50 noggings 43 l/m $ 20.00 $ 860.00
6 100x50 top plate 14 l/m $ 20.00 $ 280.00
7 100x50 bottom plate 14 l/m $ 20.00 $ 280.00
8 100x50 stud 81 l/m $ 20.00 $ 1,620.00
FLOORING
11 90X20 T&G floor boards to main floor 580 l/m $ 27.14 $ 15,741.20
12 90x20 floor boards to verander 84 l/m $ 27.14 $ 2,279.76
13 90x20 floor boards to back door stair landing 15 l/m $ 27.14 $ 407.10
250x75 Bearer 28 l/m $ 95.82 $ 2,682.96
150x50 floor joist 146 l/m $ 20.00 $ 2,920.00
Z nails 63 pcs $ 3.50 $ 220.50
U nails 22 pcs $ 3.50 $ 77.00
ROOF FRAMING
14 75X50 purlin strap in position 131 l/m $ 28.46 $ 3,728.26
15 150x50 rafters 95 l/m $ 32.10 $ 3,049.50
16 Cyclone strap 118 pcs $ 19.40 $ 2,289.20
EXTERIOR FINISHES
17 200X35 fascia board 19 l/m $ 88.45 $ 1,680.55
18 200x35 badge board 12 l/m $ 88.45 $ 1,061.40
VERANDA
19 90X90 king post 8 l/m $ 17.09 $ 136.72
20 100mm Ø galvanized iron post 13 l/m $ 124.00 $ 1,612.00
STAIR
21 250mmx50mm stair stringers and treads 50 l/m $ 24.14 $ 1,207.00
22 100mmx50mm post 11 l/m $ 20.00 $ 220.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION
BRACING
7 Strap bracing 26 l/m 0
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION
INTERIOR
10mm thick two coat 1:3 cement/sand plaster with an
approved plasticiser added, finished with a smooth and
wood float finish, as specified in :
EXTERIOR
INTERIOR
Sand, prepare and apply three coats of
clear varnish to:
4 T&G flooring board $ 53.00 m² $ 368.15 $ 19,511.95
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION
First floor
5 2100mmx910mm solid core door with 2 sets $ 740.00 $ 1,480.00
hard ware
6 2100x910 interior hollow core door 4 sets $ 935.00 $ 3,740.00
with hardware
7 145x45 door frame 30.6 l/m $ 65.63 $ 2,008.28
4" concrete nail 6 kg $ 25.00 $ 150.00
WINDOW
Ground floor
145x45 timber as specified in:
8 Window sill 8 l/m $ 76.79 $ 614.32
9 window head 8 l/m $ 65.63 $ 525.04
10 wilndow frame 16 l/m $ 65.63 $ 1,050.08
First floor
DOOR
20 2100mmx910mm solid core door with 2 sets $ 740.00 $ 1,480.00
hard ware
21 2100x910 interior hollow core door 4 sets $ 935.00 $ 3,740.00
with hardware
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION
Louvre glass
30 30" clear louvre glass blades 48 pcs $ 9.90 $ 475.20
31 30" obscure louvre glass blades 16 pcs $ 9.90 $ 158.40
Batten
32 75x20 batten 53 l/m $ 26.06 $ 1,381.18
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION