2 Stories Building

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 24

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT

Summary

Preliminaries and General (18% of total cost)

Excavation $ 14,669.20

Concrete Work $ 58,620.80

Reinforcing Steel $ 8,023.20

Concrete Blockwork $ 67,760.00

Carpentry $ 93,479.73

Roofing $ 21,249.90

Door and Window $ 9,550.97

Solid Plaster $ 7,950.68

Painting $ 22,018.39

Subtotal $ 303,322.87

Labor (40%) $ 121,329.15

Preliminaries and General (18% of total cost) $ 54,598.12

Subtotal $ 479,250.14

Profit 10% $ 47,925.01

Subtotal $ 527,175.15

Tax 7.5% $ 39,538.14


AMOUNT OF TENDER $ 566,713.29
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS/WORKS QTY UNIT RATE AMOUNT


1 Preliminaries and General
Refer to the drawings and Specification for full details and
1 descriptions of materials and workmanship

Refer to the General and Special Conditions of contract


2 and Tender and to the Preliminary and General section of
the Specification
The scope of this Contract consists of the construction of a
3 new 2 storey building at XXX location.

This Bill of Quantities has been prepared generally in


accordance with NZS 4202:1995 Standard Method of
4 measurement of Building Works, but no deviation from
same shall form the basis of a claim
Refer to the General Rules of the NZS 4202:1995 Standard
5 Method of Measurement of Building Works
The following metric abbreviations for units have been
6 used:
m3 : Cubic Metres
m2 : Square Metres
m : Linear Metres
mm : Millimetres
no : Number
kg : Kilogram
MPa : Megapascal
The Bills of Quantities are not to be used as a basis for
7 ordering materials, nor as a basis for dimensions of
manufacture

Site works
Supervision
Allowance for full-time supervision of the works by a
8 suitable qualified and experienced individual as named and
detailed within the tender document
Additional Items
9 The contractor should read and familiarise himself with the 1
preliminaries section of the tender document item
Site Clearance
10 Allowance for site Clearance 1 item $ 1,500.00
Landscaping
11 Allow a provisional sum for landscaping to site 1 item $ 500.00
Sewerage Work
12 Allow the provisional sum of SBD$1000 for sewage 1
connection inclusive of all excavation,backfilling etc item $ 1,500.00
Water Connection
13 Allowance for connecting water to the local mains water 1
supply item $ 2,500.00
14 Allowance for providing and maintaining First Aid Kit and 1
all necessary safety equipment item $ 250.00
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION

AMOUNT OF PRELIMINARIES AND SITE WORKS


CARRIED TO SUMMARY $ 3,750.00
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


2 EXCAVATION

Clear Site and Surface Excavation


Clear site of all trees, shrubs etc.. And items
1 extract
Excavatestumps
topsoil 87 m² $ 75.00 $ 6,525.00
Foundation Excavation
Excavate 800mm x 800mm pad footing
0-0.900m deep, commencing from 9.9 m³ $ 90.00 $ 891.00
ground level
2
Excavate 400mm x 400mm pad footing
0-0.755 deep, commencing from ground 1.2 m³ $ 90.00 $ 108.00
level
3
Excavate 450mm x 200 SF 0-0.500m
deep, commencing from ground level 1.2 m³ $ 90.00 $ 108.00
4
Excavate 450mm x 200 RF 0-0.500m
deep, commencing from ground level 11 m³
5
Cartaway, Backfilling & Blinding
Approved backfill surplus excavated
materials to sides of footing and 25 m³ $ 250.00 $ 6,250.00
6
rammed as approved by Engineer
Filling
50mm thick sand blinding spread over
hardcore fill $ 12.50 $ 600.00
7 48 m²
Damp Proof membrane

Polythene DPC over 30mm thick sand


blinding $ 3.90 $ 187.20
8 48 m²

AMOUNT OF EXCAVATION WORK


CARRIED TO SUMMARY $ 14,669.20
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT

3 CONCRETE
SUB-STRUCTURE
25 Mpa strength concrete as specified in
:
1 800x800 pad footing 3 m³ $ 1,800.00 $ 5,400.00
2 400x400 pad footing 0.5 m³ $ 1,800.00 $ 900.00
3 450x300 strip footing 3 m³ $ 1,800.00 $ 5,400.00
4 300x150 R footing 0.3 m³ $ 1,800.00 $ 540.00
5 90mm concrete slab 5 m³ $ 1,800.00 $ 9,000.00
6 250Ø column 15 m³ $ 1,800.00 $ 27,000.00

SUPERSTRUCTURE
7 300X160 suspended beam 1 m³ $ 1,800.00 $ 1,800.00

FORMWORK
SUBSTRUCTURE
8 sides of pad footing 11 m² $ 138.40 $ 1,522.40
9 sides of strip footing 39 m² $ 138.40 $ 5,397.60
10 sides of 250Ø column 12 m² $ 138.40 $ 1,660.80
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF CONCRETE CARRIED TO SUMMARY $ 58,620.80


BOQ FOR PROPOSES 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


5 CONCRETE BLOCKWORK
Ground floor external wall
1 150mm thick reinforced plastered blo sides 800 pcs $ 82.00 $ 65,600.00

CONCRETE FILLING
2 Fill all cell with 25mpa concrete 1.2 m³ $ 1,800.00 $ 2,160.00
BOQ FOR PROPOSES 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF CONCRETE BLOCKWORK


CARRIED TO SUMMARY $ 67,760.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOACTION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


4 STEEL ROD REINFORCEMENT
SUB-STRUCTURE
Column Pads
1 D12 bars 143 l/m $ 7.60 $ 1,086.80
2 R6 ties 31 l/m $ 2.60 $ 80.60
3 Galvanized Tie wire 30 kg $ 27.00 $ 810.00

STRIP FOOTING
4 D12 139 L/M $ 7.60 $ 1,056.40
5 R6 ties 54 L/M $ 2.60 $ 140.40
6 Galvanized Tie wire 25 kg $ 27.00 $ 675.00

RF
7 D12 19 L/M $ 7.60 $ 144.40
8 R6 ties 7 L/M $ 2.60 $ 18.20
9 Tie wire 10 kg $ 27.00 $ 270.00

CIRCULAR COLUMN
10 D12 106 l/m $ 7.60 $ 805.60
11 R6 ties 56 l/m $ 2.60 $ 145.60
12 Galvanized Tie wire 25 kg $ 25.00 $ 625.00

BLOCK WORK
13 D12 87 l/m $ 7.60 $ 661.20
14 Galvanized Tie wire 10 l/m $ 27.00 $ 270.00

SUSPENDED BEAM
15 D12 93 l/m $ 7.60 $ 706.80
16 R6 stirrup 47 l/m $ 2.60 $ 122.20
17 Galvanized Tie wire 15 kg $ 27.00 $ 405.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOACTION

AMOUNT OF REINFORCING STEEL


CARRIED TO SUMMARY $ 8,023.20
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


6 CARPENTRY
FIRST FLOOR WALLS FRAMING
External walls
1 100X50 timber studs 136 l/m $ 20.00 $ 2,720.00
2 100X50 top plate 29 l/m $ 20.00 $ 580.00
3 100x50 bottom plate 29 l/m $ 20.00 $ 580.00
4 100x50 noggings 72 l/m $ 20.00 $ 1,440.00

Internal walls
5 100x50 noggings 43 l/m $ 20.00 $ 860.00
6 100x50 top plate 14 l/m $ 20.00 $ 280.00
7 100x50 bottom plate 14 l/m $ 20.00 $ 280.00
8 100x50 stud 81 l/m $ 20.00 $ 1,620.00

External wall covering


9 140X50 external weather board cladding 234 l/m $ 32.12 $ 7,516.08

Internal wall finishes


10 90X20 wall linnings 1125 l/m $ 27.40 $ 30,825.00

FLOORING
11 90X20 T&G floor boards to main floor 580 l/m $ 27.14 $ 15,741.20
12 90x20 floor boards to verander 84 l/m $ 27.14 $ 2,279.76
13 90x20 floor boards to back door stair landing 15 l/m $ 27.14 $ 407.10
250x75 Bearer 28 l/m $ 95.82 $ 2,682.96
150x50 floor joist 146 l/m $ 20.00 $ 2,920.00
Z nails 63 pcs $ 3.50 $ 220.50
U nails 22 pcs $ 3.50 $ 77.00
ROOF FRAMING
14 75X50 purlin strap in position 131 l/m $ 28.46 $ 3,728.26
15 150x50 rafters 95 l/m $ 32.10 $ 3,049.50
16 Cyclone strap 118 pcs $ 19.40 $ 2,289.20

EXTERIOR FINISHES
17 200X35 fascia board 19 l/m $ 88.45 $ 1,680.55
18 200x35 badge board 12 l/m $ 88.45 $ 1,061.40

VERANDA
19 90X90 king post 8 l/m $ 17.09 $ 136.72
20 100mm Ø galvanized iron post 13 l/m $ 124.00 $ 1,612.00

STAIR
21 250mmx50mm stair stringers and treads 50 l/m $ 24.14 $ 1,207.00
22 100mmx50mm post 11 l/m $ 20.00 $ 220.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

23 75mmx50mm hand rail 20 l/m $ 23.30 $ 466.00


ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT
HARD WARE

24 Allow pc sum of $7000 (seven thousand dollars) $ 7,000.00


for supply and installation of all hardware
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF CARPENTRY CARRIED TO


SUMMARY $ 93,479.73
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


7 ROOFING
Roof shall be 0.48mm thick 24 gauge
steel roofing in single length sheets
fastened to purlins with 'U' way
roofing nails with total cyclonic
assembly, as:
Maximum 6.11m Above Ground Floor
Level
1 Roofing fixed to timber purlins 80 m² 198.18 15854.4
2 Extra value, for turn up 17 m 10.1 171.7
3 Extar value, for turn down 21 m 10.1 212.1
4 Ridge cap 10 l/m 88.45 884.5
0
INSULATION 0
Double sided sisilation 453 laid over
5 80 m²
wire mesh netting 38.32 3065.6
6 Bird wire netting 80 ²m 13.27 1061.6

BRACING
7 Strap bracing 26 l/m 0
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF ROOFING CARRIED


TO SUMMARY $ 21,249.90
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


8 PLASTER
EXTERIOR
15mm thick two coat 1:3 cement/sand plaster with an
approved plasticiser added, finished with a smooth and
wood float finish, as specified in :

1 Concrete blockwalls both sides 185 m² $ 35.18 $ 6,508.30

INTERIOR
10mm thick two coat 1:3 cement/sand plaster with an
approved plasticiser added, finished with a smooth and
wood float finish, as specified in :

2 Blockwork wall both sides 41 m² $ 35.18 $ 1,442.38


BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF SOLID PLASTER CARRIED TO


SUMMARY $ 7,950.68
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


9 PAINTING

EXTERIOR

Prepare and Apply 2 coats of finishing


1 coats to 140x20 external weather $ 60.00 m² $ 36.75 $ 2,205.00
boards on fisrt floor

2 Apply 3 coats of finishing coats to $ 6.20 m² $ 44.23 $ 274.23


200x35 fascia boards and badge board
3 Apply 3 coats of finishing coats to 90x90 $ 1.08 m² $ 25.20 $ 27.22
king posts

INTERIOR
Sand, prepare and apply three coats of
clear varnish to:
4 T&G flooring board $ 53.00 m² $ 368.15 $ 19,511.95
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF PAINTING CARRIED TO


SUMMARY $ 22,018.39
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


10 DOORS AND WINDOWS
DOORS
Ground floor
1 2100mmx910mm solid core with hard 2 sets $ 740.00 $ 1,480.00
ware
2 2100x910 interior hollow core door 3 sets $ 935.00 $ 2,805.00
with hardware
3 145x45 door frame 25.5 l/m $ 65.63 $ 1,673.57
4 4" concrete nail 5 kg $ 25.00 $ 125.00

First floor
5 2100mmx910mm solid core door with 2 sets $ 740.00 $ 1,480.00
hard ware
6 2100x910 interior hollow core door 4 sets $ 935.00 $ 3,740.00
with hardware
7 145x45 door frame 30.6 l/m $ 65.63 $ 2,008.28
4" concrete nail 6 kg $ 25.00 $ 150.00

WINDOW
Ground floor
145x45 timber as specified in:
8 Window sill 8 l/m $ 76.79 $ 614.32
9 window head 8 l/m $ 65.63 $ 525.04
10 wilndow frame 16 l/m $ 65.63 $ 1,050.08

Aluminuim louvre frame


11 8 blade aluminium lovre frame 6 pairs $ 124.50 $ 747.00
12 Ditto but to 7 blades 1 pair $ 110.20 $ 110.20
13 Ditto but 4 blades 2 pairs $ 62.20 $ 124.40
14 Louvre frame Screw 6 pks $ 32.00 $ 192.00
Louvre glass
15 30" clear louvre glass 55 pcs $ 9.90 $ 544.50
16 30" obscure louvre glass blades 8 pcs $ 9.90 $ 79.20
Security mesh
17 Aluminium security mesh 10 m² $ 60.60 $ 606.00
18 20x20 Beads 14 l/m $ 21.40 $ 299.60
19 Concrete sill bed 7.2 l/m $ -

First floor
DOOR
20 2100mmx910mm solid core door with 2 sets $ 740.00 $ 1,480.00
hard ware
21 2100x910 interior hollow core door 4 sets $ 935.00 $ 3,740.00
with hardware
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

22 145x45 door frame 28 l/m $ 65.63 $ 1,837.64

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


WINDOW
145x45 timber as specified in:
23 window frame 39 l/m $ 65.63 $ 2,559.57
24 window head 16 l/m $ 65.63 $ 1,050.08
25 window sill 16 l/m $ 76.79 $ 1,228.64

Aluminuim louvre frame


26 8 blades louvre frame 13 pairs $ 124.50 $ 1,618.50
27 Ditto but to 4 blades 9 pairs $ 62.20 $ 559.80
28 Ditto but to 6 blades 4 pairs $ 93.90 $ 375.60
29 Louvre frame Screw 4 pkt $ 36.00 $ 144.00

Louvre glass
30 30" clear louvre glass blades 48 pcs $ 9.90 $ 475.20
31 30" obscure louvre glass blades 16 pcs $ 9.90 $ 158.40

Batten
32 75x20 batten 53 l/m $ 26.06 $ 1,381.18
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF WINDOWS AND DOORS CARRIED TO SUMMARY $ 9,550.97

You might also like