Piping Design Basis and FLexibility Criteria
Piping Design Basis and FLexibility Criteria
Piping Design Basis and FLexibility Criteria
Flexibility Criteria
Client
Rev Description Date Prepared by Checked by Approved by
Approval
TABLE OF CONTENTS
1.0 INTRODUCTION 4
2.0 OBJECTIVE 4
3.0 DEFINITIONS 4
4.0 ABBREVIATIONS 5
5.0 REFERENCE SPECIFICATIONS 5
5.1 COMPANY SPECIFICATION 5
5.2 GUIDELINES 5
8.2.1 GENERAL 8
8.2.2 DISTANCE BETWEEN PIPES 8
8.3 FLANGES 9
8.6 STRAINERS 9
8.14 PAINTING 12
1.0 INTRODUCTION
Pak-Arab Refinery Limited (PARCO) owns 364 KM long 18"/16" dia. API 5L X-52 MFM Pipeline.
The pipeline is designed for transporting High Speed Diesel (HSD) and Superior Kerosene (SK)
since it commissioned in 1997. The pipeline starts in the North of Pakistan at Mahmood Kot
near Muzaffargarh and ends at Machike near Sheikhupura. It has two Pump Stations (viz- Pump
Station # 5 (PS-5) & Pump Station #7, Faisalabad) and two Terminal Stations (viz. Terminal
Station # 3 (TS-3) at Faisalabad & Terminal Station # 4 (TS-4) at Machike). Pump Station- 5 is
connected with High Speed Diesel storage tanks and MCR HSD/SK tanks located at Terminal
Station # 3 to transfer these products in batches. Currently HSD is being delivered to TS-3,
Faisalabad via Gantry facility as both HSD and SK are delivered to OMCs storage tanks located at
TS-4 through pipeline.
COMPANY intends to review and check the adequacy of Pump Station (PS-7/ TS-3) & Terminal
Station (TS-4) FEED Package prior to start the EPC services. The Scope of Work for EPC
Contractor includes all activities required to perform engineering, procurement,
erection/installation, testing, and completion of all civil, mechanical, electrical and
instrumentation works for Phase – II works at PS-7/TS-3 located at Faisalabad & TS-4 at
Machike. Contractor shall provide all services including pre-commissioning and commissioning
for the implementation of the project in conformity with the requirements.
2.0 OBJECTIVE
The objective of this document defines the requirements for the piping design and layout of TS-3
and TS-4 terminal stations. The project scope involves the development of brown field area at
Faisalabad and Machike Terminal Stations. Piping design basis as covered by this document is
applicable for all on-plot piping at TS-3 and TS-4 that is governed by ASME B31.3 process piping
code.
3.0 DEFINITIONS
4.0 ABBREVIATIONS
API American Petroleum Industry
ASME American Society for Mechanical Engineering
OGRA Oil & Gas Regulatory Authority
CAD Computer Aided Design
ISO International Standard Organization
NFPA National Fire Protection Association
FEED Front End Engineering Design
MTO Matrial Take Off
ESDV Emergency Shutdown Valve
DLF Dynamic Load Factor
NPS Nominal Pipe Size
5.2 GUIDELINES
Oil & Gas Regulatory Authority (OGRA)-2009 Depots for the Storage of Petroleum Products
SRO-624(1)/2009
API STD 602 Steel Gate, Globe and Check valves for NPS 4 and Smaller for
the Petroleum and Natural Gas Industries
API STD 603 Corrosion Resistant, Bolted Bonnet gate valves- Flanged and
Butt welding ends
API STD 608 Metal Ball Valves – Flanged, Threaded, and Welding Ends
API STD 609 Butterfly Valves: Double flanged, lug and wafer type
API STD 594 Check Valves-Flanged, Lug, Wafer and Butt Welding
ISO 10497 Testing of Valve, Fire Type Testing Requirement
DEP 70.10.90.11 Spare Parts
ASME B16.36 Orifice Flanges
ASME B16.48 Line Blanks
API 650 Welded Steel Tanks for Oil Storage
API 610 Centrifugal pumps for petroleum, petrochemicals and Gas Industries
API 685 Seal less centrifugal pumps for petroleum, petrochemical and Gas
Industry process service
API 676 Positive Displacement Pumps
NFPA Codes NFPA 20, NFPA30, NFPA70 etc
Carryout pipe stress analysis for critical lines on CAESAR II latest version.
Piping Isometrics and MTOs.
Pipe supports / sleepers details.
Facility Layout Report.
Preparation of data sheets, specifications and requisitions for items (e.g. piping, valves, and
strainers etc.) applicable for the project.
Preparation of Tie-in list.
Piping drawings shall show all pipe supports, guides, springs, etc. and shall provide necessary
calculations or explanation for use of special supports (If any).
Provide details and procedures for tie-in piping to the existing Facility and shall ensure that
new piping system will not cause any overstress/overloading to the existing system and
supports with necessary anchoring.
Review all vendors’ drawings and other documents to ensure compliance with
specifications.
Review of both the supplier and vendor’s drawings to ensure that adequate operating and
maintenance access is provided to entire equipment.
New firefighting system shall be installed at TS-3 and TS-4 for the new Mogas Tanks (T-407,
T-510 A/B respectively) with respect to existing firefighting system. The system shall include
the fire water tanks (T-456, T-560 for TS-3 and TS-4 respectively), foam pourers, fire
hydrants, and fire monitors etc. and all interconnecting piping according to international
codes and standards and local regulatory authorities to protect the station from fire hazard.
Road shall be constructed all around the tank to provide access to it from all sides.
Technical Bid Evaluations for all static and piping items.
Equipment Erection/Installation data summary, Plans and Procedures.
Site datum or reference points, to be consistent with the level used for Existing facilities, and
incorporate accordingly into its design.
Tanks piping shall be checked to enable the absorption of nozzle displacement caused by the
tank settlement, or piping displacement caused by nozzle rotation due to tank shell
deformation.
New DRA skid and all interconnecting piping shall be installed at TS-3 to increase the thru
put of the MFM pipeline from Faisalabad to Machike.
The existing open/closed drain system at TS-3 & TS-4 shall be used for both Mogas and HSD
services. But due to service change, associated piping, receiver, Launcher and Mainline,
open/close drains connections to be revised (if required) as per new requirement.
List of two years’ operating spare parts in consultation with vendor.
8.3 FLANGES
Flanges shall be applied for piping connections at flanged equipment nozzles and inline piping
elements such as valves, strainers, instruments, etc. However, flanges shall also be provided
where frequent dismantling of piping and/or maintenance required.
8.6 STRAINERS
The element mesh size of strainers if any shall be in accordance with downstream equipment
vendor’s recommendation. A fine mesh overlay or screen for pump suction may be installed for
startup if required. Piping arrangement shall permit insertion and removal of permanent and
temporary strainer internals without disturbing machine installation alignment.
Motor operated valves and other major isolation valves shall be at grade level or provided with
a safe access. ESDV, SDV and other major isolation valves are to be at grade level or shall be
provided with safe access.
All routinely operated valves, sample points, vents and purge points shall be accessible or
operable from permanent decking, platform or grade. If not, chain wheel may be specified if
required after Owner approval.
8.11.2INSTRUMENT ACCESS
Gauges, instrumentation, cable trays, small bore equipment, underground, above ground and
buried piping shall not interfere with access for routine maintenance. Portable platforms shall
be provided to maintain instruments not accessible from the ground level.
All sight-glasses, gauges and manually controlled by-passed shall be visible and easily accessible.
Suitable access shall be provided for installation/removal of corrosion coupons by means of
retriever tools.
All instrument panels, switchboards and electrical panels should have rear access to facilitate
maintenance particularly during breakdowns including the pressurized panels. Electrical sockets
(i-e Welding Machine, Hydro testing Machine etc.) shall be provided near all major equipment
for connecting the portable equipment/tools during routine /shutdown maintenance.
Platforms/access required for maintenance of top foam pourers at tanks and level switches.
8.11.3UTILITY STATIONS
Utility service points for water, air, shall be provided at various locations for maintenance and
cleaning purpose. The hose station connection shall be pointed downward.
8.11.4MATERIAL HANDLING
Detailed Materials Handling Study shall be performed and ensure that the Facilities are provided
with adequate temporary or permanent facilities for the handling of Materials. This shall
include, but not be limited to, the need for permanent derricks, lift ports and crane access. In all
cases the handling study should ensure the safe lifting of equipment over live hydrocarbon lines
for maintenance.
If any equipment is common to two or more systems, the isolation shall be provided for both or
all the systems in order to ensure the operation of those which are not subject to maintenance.
8.14 PAINTING
Painting shall be carried out as per “Specification for Painting and Protective Coating” (03-0198-
GS-9502-0).
Pipe sag due to weight of pipe and contents shall be from 3mm to 5 mm for condensate and
two phase lines.
Hot/cold philosophy for various combinations of working and stand by criteria.
Wind load on larger pipe (>= NPS 10") at elevated structure (>=10 m).
Soil settlement for tanks.
Pressure relief loads shall be considered with Dynamic Load Factor (DLF) of 2.
Both static and dynamic loading (if applicable) shall be considered in the stress analysis of
piping.
Piping at pumps and tanks shall be sufficiently flexible and adequately supported to prevent
the equipment nozzles from being subjected to any stress that could disturb their alignment
or internal clearances or otherwise affect the equipment and jeopardize its operation.
10.3.3CLASSIFICATION OF LINES
The following critical features are reviewed for the classification of the piping systems:
Design Temperature & pressure
Diameter
Displacement
Pipe material
Service
Equipment connections
External Loads
Based upon above features the lines are divided into four categories:
Category#1
Lines falling into this category shall be computer analyzed and brought specifically attention.
The review is to be carried out very early in the project for the following conditions:
Large diameter pipes where the pipe diameter exceeds NPS 36”.
Lines designed for greater than 7,000 thermal cycles (ASME B31.3, Fig 302.3.5).
Lines in category “M” fluid service (per ASME B31.3).
Lines in service where Design. Temp. Below –46°C.
Process lines connected to Compressors.
Lines using vacuum stiffener rings.
Non-metallic piping.
Jacketed piping.
Category #2
Lines in this category require mandatory computer analysis by Contractor during detailed design
phase:
All process lines connected to Reciprocating Pumps and Compressors, Centrifugal
Compressors, Blowers and Fired Heaters.
All process lines to and from Turbines and Centrifugal Pumps NPS 3” and larger.
Lines to and from Air Coolers and Storage Tanks, NPS 2” and larger above 160°C and/or
below -60°C.
Lines to and from Storage Tanks, NPS 4" and larger above 110°C and/or below -28°C.
All lines to and from Air Coolers NPS 4” and larger.
All lines to Storage Tanks, Pressure Vessels, Heat Exchangers and Package Units NPS 10” and
larger.
Lines containing Expansion Joints and Bellows.
Refractory lined pipe.
Lines subject to Full Vacuum (NPS 2” & above).
PSV Suction & Discharge Lines (NPS 2” & above).
All lines subject to 2-phase flow / slugging (NPS 2” & above).
Lines subject to large displacements/settlement (NPS 2” & above).
All lines designated as Category 2 due to temperature in Figure 1.
Engineering, Procurement, Construction,
Erection, Installation, Testing, Commissioning,
startup and handover of MFM MOGAS Project
(MFMMP) Phase-II, TS-3, Faisalabad & TS-4,
Machike Stations
PIPING DESIGN BASIS AND FLEXIBILITY
CRITERIA
CLASS DOCUMENT NO: XXXXXX Page 15 of 16
Category #3
Lines in this category require mandatory investigation; the analysis can be done by any
recognized approximate method such as guided cantilever or by computer using a simplified
model if appropriate.
All boiler code piping.
All pipe rack piping where line size is NPS 6” or larger.
All lines designated as Category 3 due to temperature in Figure 1.
Category #4
All lines designated as Category 4 due to temperature in Figure-1. Lines in this category can be
analyzed by visual inspection or approximate methods using engineering judgment in
accordance with ASME B31.3.
Engineering, Procurement, Construction,
Erection, Installation, Testing, Commissioning,
startup and handover of MFM MOGAS Project
(MFMMP) Phase-II, TS-3, Faisalabad & TS-4,
Machike Stations
PIPING DESIGN BASIS AND FLEXIBILITY
CRITERIA
CLASS DOCUMENT NO: XXXXXX Page 16 of 16