BBDM2153 Tutorial 4-A
BBDM2153 Tutorial 4-A
Tutorials 4
ANSWER
1) A company is considering using CPM to plan a new project with the following activities and their
precedence relationships, you are to draw an AOA diagram to demonstrate the answer.
Immediate Immediate
Activity Predecessors Activity Predecessors
a - f a,b
b - g a,b,c
c - h d,e
d a,b i f,g
e a
AOA
Paths = 4
a-e-h
a-dummy-d-h
a-dummy-f-i
a-dummy-dummy-g-i
Tutorials 4
C B 3 3 3
D A 10 15 20
E D 6 7 8
F C 9 10 11
G D 5 7 10
H E,F 14 15 16
Most Expected
Optimist Likely Pessimist Duration Variance
Activity to tm tp te Vt
a 8 10 12 10.00 0.444
b 6 7 9 7.17 0.250
c 3 3 3 3.00 0.000
d 10 15 20 15.00 2.778
e 6 7 8 7.00 0.111
f 9 10 11 10.00 0.111
g 5 7 10 7.17 0.694
h 14 15 16 15.00 0.111
AOA
BBDM2153 - Operations Management
Tutorials 4
(d) What is the earliest finish (EF) time for activity “e”?
32.00 days
Activity Duration ES EF LS LF S
a 10.00 0.00 10.00 0.00 10.00 0.00*
b 7.17 0.00 7.17 11.83 19.00 11.83
c 3.00 7.17 10.17 19.00 22.00 11.83
d 15.00 10.00 25.00 10.00 25.00 0.00*
e 7.00 25.00 32.00 25.00 32.00 0.00*
f 10.00 10.17 20.17 22.00 32.00 11.83
g 7.17 25.00 32.17 39.83 47.00 14.83
h 15.00 32.00 47.00 32.00 47.00 0.00*
11.83 S = LS – ES
S = LF - EF
47 days
The project duration is 47 days
4) A construction company wants to construct a warehouse by using Critical Path Method (CPM).
The activities are as shown below in the table, where the duration are indicated in “week”,
cost in Ringgit Malaysia (RM), precedence relationships, and the costs to accelerate the
activity.
Present Accelerated
Immediate
Activity Predecessors Duration RM Duration RM
a -- 3 3,200 2 3,400
b -- 5 4,000 3 4,150
c a 4 3,600 3 3,900
d b 6 5,800 4 6,000
e c,d 4 6,600 3 6,900
BBDM2153 - Operations Management
Tutorials 4
f e 3 4,000 2 4,400
g f 4 9,000 3 9,100
h f 5 8,700 3 9,000
i g,h 4 2,700 3 3,000
(i) Construct the CPM network using Activity on node (AON) approach with the information
given in the table. (4 marks)
(ii) List the critical paths for this project. What is its duration in weeks?
(iii) What is the earliest finish (EF) time for activity "c"?
(iv) What activity should be crashed first in order to accelerate the project?
Per week crashing costs for each activity: (* denotes falling in critical paths)
Tutorials 4
Visual aids that are useful in loading and scheduling or it is a planning charts used to
schedule resources and allocate time.
6) Although the PERT or CPM network or analysis is prepared, but you are required to
speed up the completion of the project. How do you decide on the activities so as to
complete the project sooner?
Tutorials 4
7) A startup company is planning to use a CPM network to turn a promising new technology
into a product. They have established a project whose manager developed these activities,
precedence relationships, and activity durations (in days) for the effort:
Immediate
Activity Predecessors Duration
a -- 4
b -- 5
c -- 3
d a 2
e b 3
f c 1
g d,e,f 5
h d,e,f 4
i g 7
j h 3
k i 1
l j,k 2
m i 2
(b) What is the earliest finish (EF) time for activity "h"?
BBDM2153 - Operations Management
Tutorials 4
EF = 12 days
Activity Duration ES EF LS LF S
a 4 0 4 2 6 2
b 5 0 5 0 5 0*
c 3 0 3 4 7 4
d 2 4 6 6 8 2
e 3 5 8 5 8 0*
f 1 3 4 7 8 4
g 5 8 13 8 13 0*
h 4 8 12 14 18 6
i 7 13 20 13 20 0*
j 3 12 15 18 21 6
k 1 20 21 20 21 0*
1 2 21 23 21 23 0*
m 2 20 22 21 23 1
Slack = 0 day