Document No. REV. 0 Job No. Date Page 1 of 22
Document No. REV. 0 Job No. Date Page 1 of 22
Document No. REV. 0 Job No. Date Page 1 of 22
DATE PAGE 1 OF
22
REVISION
HISTORICAL SHEET
CONTENTS
1. GENERAL
The commissioning objective is to ensure that the facilities will operated safely and meet
the performance within the project schedule, and in accordance with the applicable
codes, the latest applicable revision of design, drawings and specifications. Operability
and safety reviews have been implemented during the design.
2. REFERENCE
All work shall be in accordance with contract document and Appendix A - “Project
Spesification”.
TESTING & COMMISSIONING PROCEDURE
Document No. Rev. Contract No :
Page 4 of 5
0 Job No :
3. SAFETY PREPARATION
Safety requirement for this procedure will be covered by the permit to work and the
JSA specifically written for Testing and Commissioning.
4. PREPARATION
Individual test certificate already done.
Initial start-up the operating personnel has to read carefully the instructions
for prevention of accidents is described on JSA document.
Assesment for feasibility equipment for running test
Initial start-up may only be done by personnel and team.
Explaination step of initial start up and during start up.
Well understand mechanism of overall project.
5. PRE-COMMISSIONING
All components shall be inspected to verify that they have been fabricated /
manufactured, supplied, installed, aligned and lubricated in accordance with:
contract drawings and documentation;
Standards and Codes specified in this Standard;
Statutory Regulations;
Manufacturer’s requirements.
Tests and calibrations shall be carried out to prove that all systems are operational,
including protective and measuring devices.
Testing and commissioning of all belt conveyor electrical and instrument equipment
shall be carried out in accordance with Engineering Standard Testing and
Commissioning.