0% found this document useful (0 votes)
40 views1 page

Quiz A1 Sol

The document provides data to estimate the total cost of a proposed commercial complex for a municipal corporation, including the height and number of stories, cubical content rate, and percentages for water/sanitary, electrification, fluctuations, contractor's profit, and petty supervision/contingencies. It then shows the calculations to determine the total area and volume of the complex and multiply it by the cubical content rate to get the basic cost of construction. Finally, it applies the given percentage rates to the basic cost to calculate the total estimated cost of the building project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views1 page

Quiz A1 Sol

The document provides data to estimate the total cost of a proposed commercial complex for a municipal corporation, including the height and number of stories, cubical content rate, and percentages for water/sanitary, electrification, fluctuations, contractor's profit, and petty supervision/contingencies. It then shows the calculations to determine the total area and volume of the complex and multiply it by the cubical content rate to get the basic cost of construction. Finally, it applies the given percentage rates to the basic cost to calculate the total estimated cost of the building project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Estimation – Quiz – 2018 – 2nd.

Semester – Solution
Wisam Abdulla Najim AL–Halfi

Prepare the estimate for a proposed commercial complex for a municipal


corporation for the following data. Height of each storey = 3.5m No. of
storey’s = G+2.Cubical content rate = 200 $/m3. Provided for a following
as a percentage of structured cost
1. Water supply& Sanitary arrangement @8%
2. Electrification @6%.
3. Fluctuation of rates @5%
4. Contractors profit @ 10%
5. Petty supervision & contingencies @ 3%.
Determine the total cost of building project.

Sol.
A1 = 20x10 = 200 m2.
A2 = ( ) = 39.270 m2.
Atotal = 239.270 m2.
Volume = 239.270 x 3.5 x 3 = 2513 m3.
Cost of building = Volume x Price/m3
= 2513x200 = 502600 $
Total cost = 502600(1+0.08+0.06+0.05+0.1+0.03)
= 663432 $