FYP GANTT CHART Legend Plan Actual
PLAN ACTUAL ACTUAL PERCENT
TASK NAME PLAN START
DURATION START DURATION COMPLETE
1 2 3 4 5 6 7 8 9 10 11
FYP 1 Briefing 2 2 2 1 100%
Find Supervisor 2 2 2 1 100%
Individual Proposal Form 4 3 4 2 100%
Group Proposal Form 6 3 6 2 100%
Prepare Group Proposal 6 15 6 13 100%
Project's Introduction 6 1 6 1 100%
Review Literature Work 7 2 6 2 100%
Methodology 9 3 6 3 100%
Analayze and Discussion 10 1 10 1 100%
Pre Proposal Presentation Video + Slide 14 1 14 1 0%
Presentation + Report Documentation 14 1 14 1 0%
Verify and Comment 14 1 14 1 0%
FYP 2 Briefing 0%
41 2 41 1
Prepare Project Fabrication Item 0%
43 2 42 3
Analayze and Discussion FYP 2 0%
45 1 44 1
Project Fabrication 0%
45 9 45 11
Project Testing 0%
54 9 53 2
Project Presentation 0%
56 2 54 2
Training Week
22 to
12 13 14 15 16 17 18 19 20 21 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56