1073R PDF
1073R PDF
B4-1073
http : //www.cigre.org
SUMMARY
Many HVDC systems have been applied to various kinds of AC power systems worldwide since 1954
when the first HVDC system was put into commercial operation. Main purposes of HVDC systems
can be roughly divided into two categories which are firstly long distance and bulk power
transmission, and secondly interconnection between power networks. Former HVDC systems
recently have aimed to increase DC system voltage such as ±800kV and much higher voltage and to
enlarge capacity of 6400MW and much larger capacity per bi-polar configuration. On the other hand,
latter HVDC systems have aimed to support AC system reliability with using flexible operation
method. This paper mainly introduces the applied HVDC technologies of latter case to Japan’s HVDC
system which have been improved for AC system reliably operating performances.
KEYWORDS
HVDC control system, Simultaneous Bi-directional Power Flow Control (SBPFC), Stable operation,
Bi-polar control, Flexible operation, AC power system quality, Metallic Return Circuit Protection, Ne
1. Introduction
HVDC Systems have been applied worldwide for the cases which HVDC operational characteristics
are superior to AC system’s characteristics for the individual project. The main purposes of applying
HVDC systems can be roughly divided into two categories which are firstly long distance and bulk
power transmission including submarine systems, and secondly interconnecting between AC power
systems. For the long distance and huge power transmission of HVDC system, required technologies
are to apply higher reliable and efficient transmission system and for the submarine cable system,
new type insulation cable has been developed and applied to achieve simpler maintainability and
more operational capabilities. In case of interconnecting AC systems, various kinds of technologies
are required in accordance with operational requirements and conditions of each project. This paper
describes brief history of HVDC and introduces the new technologies applied to Japan’s HVDC
systems interconnecting AC power systems.
[email protected]
2. Transition of HVDC projects
2.1 Beginning Phase
The first HVDC project in the world was Gotland HVDC Link which connected between main land of
Sweden and Gotland located far from east coast of the peninsular. This project was put into
commercial operation in 1954 and Mercury Arc Valves were used as the state of art technology at that
time. The feature of the project was 98-kilomiter-long submarine cable with a voltage of 100kV and
the capacity of 20MW.
Projects following to the Gotland HVDC Link using Mercury Arc Valves technologies were Cross
Channel HVDC Link between UK and France in 1961, New Zealand Inter Island HVDC Link in 1965,
Sakuma BTB in 1965 Japan and Vancouver in Canada 1968 commissioned respectively.
However, up to the HVDC project of Pacific Intertie commissioned in 1982 USA, Mercury Arc Valve
Technologies were replaced with Thyristor Valve Technologies because Mercury Arc Valves had a
fatal flaw as Consequential Arc Back so called CAB which once occurred HVDC Link should be
tripped for clearing the fault.
1
And the first commissioned UHVDC project was Xiangjiaba–Shanghai HVDC Link of which feature
is rated voltage of ±800kV, capacity of 6400MW, and circuit configuration of one bi-polar having
transmission length of 2000km.
In the next stage of UHVDC system voltage, ±1100kV will be selected and already the project has
been moved into action for implementation.
error. In other words, HVDC link cannot Power Setting to Hokkaido Direction 0.1pu
Pole#1
#P1
Rec Inv
In case of Pole#1operation independently
Power Flow
Power system controller such as Automatic Frequency Control (AFC) can be only used during HVDC
operating state. Usually, HVDC interconnection link only operates when the contracts are agreed
between system operators on Power Flow to Honshu 1.0pu
Output of AFC
HVDC system, even if power : +/- 0.1pu
0.2pu
exchange contract is not agreed or Power Setting to Hokkaido 0.1pu
5
This operation method is
Power Exchange with AFC through Hokkaido-Honshu HVDC Link
additionally installed in bi-polar
control system which is the highest 100
0:00
1:30
3:00
4:30
6:00
7:30
9:00
10:30
12:00
13:30
15:00
16:30
18:00
19:30
21:00
22:30
24:00
MW
-50 Max(PSS+60MW)
Other purpose of SBPFC is to Min(PSS-60MW)
-100
reduce the number of polarity
-150
reversal which may affect insulation
-200
stress of submarine cables used for Time
HVDC circuit. In case of applying
Simultaneous Bi – Directional Mono – Polar Bi – Polar
LCC to HVDC link, during power Power Flow Operation Operation
reversal operation in emergency Figure 9 Typical Operation Record with Flexible HVDC Control
state or reverse power order mode,
DC voltage is reversed. During this polarity reversal phenomenon, submarine cable is affected on
insulation stress. To avoid this kind of stresses by the power reversal operation, usually the operation
procedure is that first the HVDC link is blocked and after several hours for discharging, the HVDC
link is restarted with reverse power flow direction. However, using SBPFC, polarity reversals can be
avoided during power reversal operating. As the result of employing SBPFC, submarine cable life is
expected to become longer without operational restrictions.
In the actual AC network operation, a power oscillation sometimes occurs following disturbances in
AC system. This means that the equivalent inertia of one part of the AC system is temporarily
accelerated while the equivalent inertia of the other system temporarily decelerated and vice versa.
Using superior controllability of HVDC technologies, the power oscillation can be damped within the
duration of the initial state which has a possibility to amplify disturbance in whole AC network, if not
controlled. Usually, the Power Oscillation Damping function becomes active automatically when the
fluctuation value due to this phenomenon is beyond the preset value under emergency conditions or
major disturbance. There were three optional control methods applicable to Kii Channel HVDC Link
such as: Frequency difference between two converter stations; Generator rotor speed difference
between two systems; Power fluctuation of AC interconnecting line. Through the technical evaluation
using digital simulation on affection of three control methods, it was confirmed that all methods could
improve AC system stability. Therefore the most practical method as frequency difference of two
converter stations was selected since both frequencies should be send to each opposite converter
station for other purposes control. Conceptual diagram of this damping control and related power
networks are shown in Figure 10.
Power system oscillation frequency of Shikoku Power Network is the range between 0.3 to 0.4Hz and
Kansai Power Network associated with other 60Hz power is the rage of between 0.5 to 0.65Hz. The
6
actual effect of damping control was determined at the event of large capacity power plant failure
which is shown in Figure 11.
The failure of this event was not so severe degree compared to the trunk line fault, therefore the output
peak value required by the damping controller was up to 114MW.
As the countermeasure to solve those issues, Hokkaido Honshu HVDC Link has employed exclusive
protection system with superimposing AC current which monitors whether return circuit is faulted
state or not. The used frequency for this protection system has been carefully selected to avoid the
influences from fundamental frequency used in power system. Used frequency for the protection
system is 125Hz which is kept away from the fundamental frequency of 50Hz and the value of
multiplies of 50Hz. Although superimposed frequency is optimized, the value of AC 125Hz current is
not stable during HVDC system operation and the value is significantly changed by the operation
modes such as mono-polar operation and bi-polar operation. For these severe circumstances of
metallic return circuit protection, the adjustments of criteria values are very difficult to distinguish the
fault state from sound conditions. Since the original protection system was installed in 1970’s, more
than 30 years before, the types of protection relay and telecommunication technologies were very
limited in their functions. Therefore, it is needed to develop new protection system. New algorism
used for fault detecting and telecommunication system for real time data acquisition have been
investigated, evaluated, optimized and newly installed. Figure 12 shows the new metallic return circuit
protection circuit system including 125Hz monitoring current.
The new detecting algorism was drastically changed from the method used in original protection
7
system which simply compares preset level
Hakodate Furukawa Sai Cable Kamikita
to measured absolute value, to the new C/S Cable L/P L/P C/S
OH T/L Submarine Cable OH T/L Return Circuit
method which calculates each proportional
125Hz Monitoring Current
value of each measured value at converter
MRTB
stations and cable landing points. The new D-3
Newly developed DC-XLPE has the conductor size of 600 square mm for the submarine use and 900
square mm for land use. To avoid
mechanical damage due to external force as
far as possible, double steel-wire armour is
applied.
8
Figure 14 shows also the configuration with three-dimensional cut
model of DC-XLPE submarine cable used for this project.
Before laying DC-XLPE cable, electric and mechanical
capabilities were carefully confirmed with carrying out type tests
and acceptance tests in the manufactures works.
This cable was laid and put into commercial operation in
December 2012 through the onsite tests including insulation
withstand tests and HVDC system operation tests consisting of
various operation modes including polarity reversal operation.
And this cable has operated without any problems since
commissioning.
This kind of technologies will be used for worldwide LCC HVDC
projects through the technical evaluation based on actual
operational performance in Hokkaido Honshu HVDC Link.
Figure 14Three-demensional cut model of DC XLPE Submarine Cable
Figure 15 shows route location of DC-XLPE cable
laid for Hokkaido Honshu HVDC Link.
5. Conclusion
New HVDC technologies introduced in
this paper are useful not only for Japanese
power network but also for any power
networks which have similar characteristic
and operational requirements. Furthermore,
upgrading and modifying these
technologies, there are many possibilities
that the technologies are applicable to
number of existing and future HVDC
projects. Figure 15 Route Location of Submarine cable for Hokkaido Honshu HVDC link
References
[1] T. Sakai, K. Takahashi “New Operation and Control Scheme of HVDC Link under Power Market
Environment” CIGRE, 2010 Paris Session.
[2] Joint Working Group C4/B4/C1.601, CIGRE Technical Broacher “Influence of Embedded HVDC
Transmission on System Security and AC Network Performance” April 2013
[3] C. Watanabe, Y. Ito, H. Sasaki, Y. Murata, M. Suizu, M. Sakamaki, M. Watanabe, S. Katakai. IEEJ
Transaction on Power and Energy, Vol.134 No.1 pp64-75, DOI: 10.1541/ieejpes.134.64 “Practical
Application of +/-250kV DC-XLPE Cable for Hokkaido Honshu HVDC Link”