Design Aspects of A Cost Effective Multipurpose PLC Based Thermovacuum Facility
Design Aspects of A Cost Effective Multipurpose PLC Based Thermovacuum Facility
NCCS 2019
December 12-14, 2019, Trivandrum, India
ABSTRACT
A new thermovacuum facility of 1.1 m diameter and 1.3 m length has been designed, fabricated,
installed and commissioned at Quality Division-Vehicle systems environment test facility, Vikram Sarabhai
Space Centre (VSSC), Thiruvananthapuram. This facility was built primarily for conducting thermovacuum
tests of launch vehicle and spacecraft subsystems up to a maximum and minimum temperature range of
+150°C and -150°C, under a vacuum environment of 1x10-5 hPa. Provisions for conducting thermovacuum
tests and helium fine leak tests of pressurized subsystems was implemented to improve versatility. All facility
subsystems were designed indigenously and integrated in-house, which has resulted in reduced initial cost.
Vacuum chamber and thermal shroud was fabricated through local sources as an import substitute. Other
facility subsystems like vacuum feedthroughs and PLC based control system were realized in-house. This has
resulted in 35% cost saving in comparison with outright procurement along with simplicity in design and
maintainability. Vacuum pumping system comprises of a roots-rotary vane vacuum pump combination for
generating low vacuum and two turbomolecular pumps for generating high vacuum. Double embossed type
thermal shroud mounted inside the thermovacuum chamber is circulated with ethanol or liquid nitrogen for
simulating low temperature. Infrared lamps mounted inside thermal shroud are used for simulating high
temperature. PLC based control system permits remote operation which also avoids operator errors.
Standalone data acquisition system is provided for recording test parameters. This paper describes the
methodology adopted to realize a thermovacuum test facility with multiple capabilities and reduced testing
costs.
Key Words: Thermovacuum, PLC, thermal shroud, vacuum chamber, pneumatic tests
NOMENCLATURE ε Emissivity
PLC Programmable logic controller σ Stefan-Boltzmann constant
RS Roughing skid T Temperature
SV Solenoid valves k Thermal conductivity
TMP Turbomolecular pump M Mass
EP Electropneumatic valve Cp Specific heat
VG Vacuum gauge SCADA Supervisory control and data acquisition
PF Power feedthrough RTD Resistance Temperature Detector
TF Thermocouple feedthrough GUI Graphical User Interface
DAQ Data acquisition unit RCC Reinforced cement concrete
t thickness V Needle valve
p pitch PT Pressure transducer
P Internal design pressure RV Safety relief valve
S Allowable stress value RVP Rotary vane pump
TIG Tungsten inert gas MSHLD Mass spectrometer helium leak detector
GN2 Gaseous nitrogen R&D Research and development
LN2 Liquid nitrogen
IR Infrared lamps
Q Heat loss
F View factor between shroud and chamber
A Area of shroud
1
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
2
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
3
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
4. THERMAL SYSTEM allowable stress value given in ASME Section II, part
D [2] in kPa.
Thermal system is used to simulate required
thermal environment in a thermovacuum chamber. = √ (1)
Thermal system comprises of a thermal shroud which Thermal shroud assembly has a cylindrical
is a thermally controlled envelop and associated section of 0.89 m diameter and 1.25 m length, with
cooling / heating system. Thermal shroud panels of two flat disc end shrouds of 0.82 m diameter. 3 D
double embossed configuration were designed as per model of thermal shroud is shown in figure 4.
ASME section VIII Division 1 [1] and fabricated Cylindrical shroud is designed as two ‘C’ shaped
through local source as an import substitute which segments. Each ‘C’ shaped segment is further
has resulted in reduced initial cost and lead time. separated into five regions by a long seam laser
Each shroud panels consists of two SA-240 SS304 L welding. Inlet and outlet piping to each segments are
sheets welded together by laser welding on identified welded to a common manifold at bottom and top
spots. Continuous TIG welding on edges are provided respectively. This ensured complete filling of coolant
for better leak tightness. Panels are inflated by medium throughout the shroud for uniform
hydroforming to obtain a predefined path for coolant temperature distribution along the length and
circulation. avoiding hot spots.
Thickness of sheet was calculated using The thermal shroud is configured as
equation 1, where t is the minimum thickness of plate optically tight envelop by closing all gaps between
in mm, p is the maximum pitch measured between the segments using passive copper plates. Partition
adjacent seam weld centre lines in mm, P is the welds are provided in the disc shrouds to prevent
internal design pressure in kPa, S is maximum
4
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
direct flow of coolant medium from inlet pipe to shroud to the chamber was estimated using equation
outlet. 2.
εtot = (3)
5
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
gas entering the shroud during subsequent openings chamber subsystems through a user-friendly graphic
of inlet solenoid valves, a vent valve is provided in user interface (GUI) on a desktop computer. The
the loop which will be actuated for 40 seconds prior software is also capable of real time monitoring and
to opening of inlet solenoid valves. archiving of complete test data. Individual screens are
provided for accessing the chamber system, pumping
system, thermal system and auxiliary systems and is
5. INSTRUMENTATION AND CONTROL provided with complete status of all equipments and
sensors in each subsystem. SCADA screen for
SYSTEM instrumentation and control system is shown in figure
5.
A PLC based system has been designed and
realized in-house for remote operation and control of The SCADA software is also capable for
all facility subsystems. The control system has been providing real-time warnings, errors and alarms in
designed to operate in two modes, allowing users to case of unexpected behavior of subsystems. Provision
operate the system in PLC mode using the PC based for setting temperature limits, warning limits etc. are
SCADA software and also in manual mode using the available. It is also equipped with an expert mode of
control consoles. The PLC based system is designed operation for trouble shooting and maintenance of the
with all the required sequences for automatic facility.
operation of the facility subsystems and the required The SCADA software is also interfaced with
safety interlocks to eliminate chances of human error an additional standalone data acquisition unit for
while operating the system. The PLC system monitoring and recording of the test data from test
monitors the sequences and interlocks in real-time article / thermal shroud instrumentation. The
and is designed to initiate shutdown sequences to instrumentation capabilities of the system include
reach fail safe mode, in case of emergency situations several channels identified for temperature
like power failure, equipment malfunction etc. measurements using thermocouple / RTD, strain
The PLC based system is interfaced to the measurements using strain gauges and other voltage
operator through in-house designed SCADA and current measurements.
software. This enables the user to control all the
6
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
Various provisions are incorporated in the Test fixtures for holding pressurized
facility design to improve the versatility of the subsystems inside the chamber was also designed and
thermovacuum test facility to meet customized test fabricated. This test fixture is capable of holding the
requirements. Some of the features are described test article; preventing the same from rotation, lateral
below. movement and at the same time permits axial
movement due to dilation during pressurization /
testing.
6.1 PROVISIONS FOR PNEUMATIC
TESTS
Thermovacuum facility is located inside an
RCC test bay, which is designed to withstand
inadvertent failure of pressurized subsystems during
tests. A dedicated system for automatically
pressurizing the test articles meeting all safety
requirements was realized. This system consists of an
air loaded regulator coupled with an electronic
regulator. A pressure feedthrough was designed and
realized for providing pneumatic pressure line to the
test article located inside the vacuum chamber.
Schematic of pressure feedthrough is shown in figure
6, which consists of a DN ISO 40 KF adaptor (1), a
gland nut with knurled head (2) which can be
tightened to push a collar (3) to compress the O ring
(4) between external surface of tube and internal
surface of adaptor to achieve sealing. Figure 7: Provisions for pneumatic test
An additional solenoid valve SV1 (in Figure
3) is connected to turbomolecular pump exhaust port
which connects the pump to a mass spectrometer
helium leak detector (MSHLD) for conducting
helium leak tests of pressurized satellite / launch
vehicle subsystems by global hard vacuum method.
All vacuum pumps will be disconnected except
tubomolecular pump TMP1 during leak tests.
Automatic control sequence of all pumps for
conducting leak test is implemented in SCADA.
7
National Conference on Cryogenics for Space
NCCS 2019
December 12-14, 2019, Trivandrum, India
6. CONCLUSION