Quality Procedure - Testing Manual
Quality Procedure - Testing Manual
Quality Procedure - Testing Manual
PROTECTION COMMISSIONING
Prepared By
Ra’ed Eftieha
Commissioning Departments / Protection section
1/43
OBJECTIVE
SCOPE
2/43
BASIC PROTECTION CONCEPTS
The relay is the heart of the protection system, which continuously senses
the conditions of the power system by analyzing the current and voltage
signal and detecting any abnormality, which exceeds the setting and initiates
the disconnection of the faulty part of the power system.
3/43
CONTENTS
4/43
2.2 On Load Test Procedure for Distance
Protection 39
3. Appendix
site test sheets
5/43
Chapter1 (Protection Component test)
1. Insulation test: -
• All the deliberate earth connection on the CT should first be removed, for
example earth links.
• The insulation resistance should be measured to earth and between
separate cores
3. Polarity check
• Each CT should be tested to verify that the primary & secondary polarity
markings are correct and this test can be done by applying low DC voltage
(9 V dc) on the primary winding (positive should be apply to P1 &
negative to P2) and connecting analog dc ammeter to the secondary side,
the positive side of the ammeter to S1 & the ammeter common side to S2,
on applying the voltage the dc ammeter should give a positive flick and on
removing the voltage the dc ammeter should give a negative flick.
Therefore when current flows from P1 to P2 it is transferred and flows
through the external secondary circuit from S1 to S2. Typically P2/S2 is
always towards the item of the system being protected.
6/43
Chapter1 (Protection Component test)
4. Magnetization curve
• Several points should be checked on each CT mag curve, this can be done
by energizing the secondary winding from the local main supply through
variable auto transformer while the primary circuit remain open, first we
have to re-magnetizing the CT by rising the voltage till we got rated
current value of the secondary winding then we have to reduce the voltage
to zero again.
The mag curve is measured at suitable intervals of applied voltage, until
the magnetizing current is seen to rise very rapidly (50%) for small
increase in voltage (10 %).
Care must be taken that the test equipment is suitably rated, if it found that
the CT have knee point voltage higher than the local mains supply , in this
case a set up transformer must be used to obtain the necessary voltage to
test the Mag curve.
7/43
Chapter1 (Protection Component test)
5. Ratio check
This check is carried out by primary injection, the ratio of the primary current
value to the secondary current value measured should approximate to the ratio
marked on the nameplate
8/43
1.2- Voltage transformer test procedure
1. Insulation test
• All the deliberate earth connection on the VT should first be removed, for
example earth links.
• The insulation resistance should be measured to earth and between separate
cores.
2. Polarity test.
• The voltage transformer polarity can be checked using the method for the CT
polarity tests. Care must be taken to connect the battery supply to the primary
winding, with the polarity ammeter connected to secondary winding. If the
voltage Transformer is of the capacitor type , then the polarity of the VT at the
bottom of the capacitor stack should be checked
3. Ratio check
• This check can be carried out by applying voltage to the primary winding,
measuring the voltage across the VT secondary winding, the ratio of primary
voltage to secondary voltage to be compared with the ratio shown on the
nameplate.
Remember
9/43
Chapter1 (Protection Component test)
This procedure is applicable for the testing of tripping, Auxiliary and supervisory relay
used in 400/132kv system
GENERAL INSPECTION
The inspector has to check the following:
i) Installation & wiring correct to relevant drawings
ii) Relay case connected to local earth bars
iii) Insulation resistance with 500v megger
iv) Supply connected to correct terminal
v) Operation of output contacts
vi) Operation of mechanical flag & resetting arm
vii) Sr.no on modules, case & cover identical
viii) Dc consumption at rated voltage
ix) Relay pickup voltage & pick up current
x) Relay drop off voltage ¤t
xi) Relay operating time
xii) Relay reset time.
This procedure is applicable for the testing of trip supply supervision relay used in
400/132kv system
GENERAL INSPECTION
The inspector has to check the following:
i) Installation & wiring correct to relevant drawings
ii) Relay case connected to local earth bars
iii) Insulation resistance with 500v megger
iv) Supply connected to correct terminal
v) Operation of output contacts
vi) Operation of mechanical flag & resetting arm
vii) Sr.no on modules, case & cover identical
viii) Dc consumption at rated voltage
ix) Relay pickup voltage & pick up current
x) Relay drop off voltage ¤t
xi) Relay operating time
xii) Relay reset time.
10/43
Chapter1 (Protection Component test)
This procedure is applicable for the testing of trip circuit supervision relay used in
400/132kv system
GENERAL INSPECTION
The inspector has to check the following:
This procedure is applicable for the testing of transformer Differential relay DUOBIAS
used in 400/132kv system
GENERAL INSPECTION
The inspector has to check the following:
1. Installation & wiring correct to relevant drawings
2. Relay case connected to local earth bars
3. Insulation resistance with 500v megger
4. Aux. Supply connected to correct terminal
5. Quiescent current operation condition
6. Relay test block ct shorting proved
11/43
Chapter1 (Protection Component test)
Metering Check:
The inspector has to check the metering element by applying current and record the
instrument display
CT multiplication factor
The inspector has to change the setting of the CT multiplication factor , applying current
and record the instrument display
12/43
Chapter1 (Protection Component test)
By following DEWA standard test sheet, the inspector has to check & fill the following
13/43
Chapter1 (Protection Component test)
25
B )(26
27
N )(28 C14 C15
R current is injected into the R phase, which is used as the Bias current, and another
current is injected into the Y phase, which is used as differential current. IR is always
greater than IY
LOWER SLOPE:
Adjust the test kit to give a bias current of 1Amp in R phase (terminal C3-C2), the relay
will trip, slowly increase the current in the Y phase from Zero until the Y phase trips ,
record Y phase current magnitude and check that it corresponds to the following Formula
Y phase operating current is 0.5*[IS1 + (IR * k1)] +/- 10% for IR < IS2
UPPER SLOPE:
Adjust the test kit to give a bias current of 3Amp in R phase (terminal C3-C2), the relay
will trip, slowly increase the current in the Y phase from Zero until the Y phase trips ,
record Y phase current magnitude and check that it corresponds to the following Formula
Y phase operating current is 0.5*[IS1 + (IR * k2) – ((k2 – k1)*IS2) + IS1] 10% for IR > IS2
14/43
Chapter1 (Protection Component test)
1.7.8 DISTANCE PROTECTION TEST: (P543, P544, P545 & P546 only)
If the distance protection function is being used, the reaches and time delays of the
distance functions should be tested.
The VT supervision may need to be disabled to avoid spurious pickup.
15/43
Chapter1 (Protection Component test)
Reduce the impedance and reapply this case to the relay. This procedure should be
repeated until a trip occurs. To view alarm message press the read Key, repeat of this key
should be used to verify that R phase was the “start Element”.
Record the impedance at which the relay tripped. The measured impedance should be
within +/- 10% of the expected reach.
Repeat the above testing for other phases (phase-phase faults & phase to ground faults)
16/43
Chapter1 (Protection Component test)
17/43
Chapter1 (Protection Component test)
18/43
Chapter1 (Protection Component test)
Start the testing by inject 0.5 amps at the second relay (relay no 2), slowly increase the
current at relay no 1 until the relay tripped, record the value. Repeat the testing by
increasing the injection current at relay 2 to start from 0.8 amps & slowly increased the
current at the relay 1 until the relay tripped. From the two values we can now calculate
error at the slop setting.
Repeat the above testing for all the phases.
Repeat the above test for the upper curve.
19/43
Chapter1 (Protection Component test)
GENERAL INSPECTION
The inspector has to check the following:
Connect the test circuit as shown in the following Figure, increase the current until the
relay operate, record the current & the voltage repeat the test for all the relay settings
value& for each pole of the relay. Measure the operating time at 3 time of any relay
setting.
MCAG
A 14 or 34
Stabilizing resistor
20/43
2.0 TEST PROCEDURE OF O/C & E/F
GENERAL INSPECTION
The inspector has to check the following:
1. Installation & wiring correct to relevant drawings
2. Relay case connected to local earth bars
3. Insulation resistance with 500v megger
4. Supply connected to correct terminal
5. Operation of output contacts
6. Sr.no on modules, case & cover identical
7. Dc consumption at rated voltage
8. relay CT shorting contact proved.
21/43
Chapter2 (Protection Scheme test)
22/43
Chapter2 (Protection Scheme test)
23/43
1.4 SENSITIVITY& STABILITY TEST PROCEDURE FOR TRANSFORMER
DIFFERENTIAL PROTECTION
1. Schematic Drawings.
2. Site Test Format.
1. Multi meter
2. Test Leads.
3. Primary Injection unit
4. Clamp meter
5. Mini Clamp meter
6. Split Pin
24/43
5) Repeat the step 2,3 & 4 for Y, B phases also.
Provide temporary cable from LVAC o/g feeder (400A) to 11kv outgoing
feeder as per the figure and ensure the cable IR strength by 1kv megger.
Make sure the Earth switch of 11kv BUS must be in open condition and
LVAC Incomer breaker in isolated position with pad locked condition.
Before Turn ON the supply from LVAC, ensure that the 11kv VCB (all o/g
FDR’s, BS & I/C) and 132kv IDT Breaker.
Turn ON the supply from LVAC o/g feeder and check the voltage.
After ensuring the all safety precaution Close the breaker where the test cable
is connected and then close the Incomer breaker
25/43
After ensuring the Line Earth switch in closed position (as per the fig) close
the GIS Circuit breaker and check any abnormalities (observe all readings
from HV ERF, LAREF & DIFF RELAY)
Open bus 2 side Line Earth switch then note down the readings from F87T
relay at Transformer Nominal Tap, Min Tap & Max Tap position.
After taken the readings OPEN the 11kv O/G feeder VCB.
Reverse the polarity of R phase CT secondary connection in HV side at LCC
–XA1
Repeat the steps 5 to 8 for Y & B phases also. (Only on IDT Nominal Tap
Position.)
Reverse the polarity of R phase CT secondary connection in LV side at 11kv
Incomer –XA
Repeat the steps 5 to 8 & 11 for Y, B phases also. (Only on IDT Nominal Tap
Position.)
If the HV CTs are located at the both limes of the BUS –Disconnector, Stability test has
to be a proved for both CT groups.
26/43
1.5 SENSITIVITY& STABILITY TEST PROCEDURE FOR HV REF PROTECTION
OF IDT’S
1) Make the connection of primary injection kit as per the following Fig
2) Prepare the multi meter connection for Voltage across Metrosil , Stab
Resistor, Relay Coil and Relay current
3) Turn on the Power to Kit, increase the primary current slowly till the MCAG-
14 (F64) gets Pick up, and maintain the same current.
4) Note down all the readings from the meters and record it.
5) Turn off the kit and compare the readings with Expected Primary operating
Current as per the Setting calculation.
6) Repeat the step 3, 4 & 5 for Y, B & NCT phases also.
27/43
REF STEABLITY TEST.
28/43
1.6 SENSITIVITY& STABILITY TEST PROCEDURE FOR BAS BAR PROTECTION
The Bas Bar protection scheme used at DEWA system is High impedance type & the Bas
Bar arrangement is typical Double Bas Bar. In this type of arrangement on-load transfer
of a circuit is possible, so the current transformer outputs are switched to the correct bus-
wires by auxiliary switches on the selecting isolators. These auxiliary switches close
before the main isolator closes and open after the main isolator opens to ensure stability
during switching operation, the property of these auxiliary switches (early make lately
break) must be confirmed & tested before connecting it in the circuit.
29/43
Open circuit of the connections between CT & the relay circuit detected by sensitive
voltage relay (CT wiring supervision relay), this relay have a time delay of about 3
second.
After adapting the final setting for the differential relay, supervision relay & stabilizing
resistor of B.B.P, sensitivity test shall be carried to verify that the primary operating
current is within the acceptable tolerance.
BBP SENSITIVITY TEST
The sensitivity of the BBP scheme can be checked using the circuit shown in the
following figure.
30/43
4) Turn on the Power to Kit, increase the primary current slowly till the MVTP
gets picked up, record the primary operating current for the MVTP relay, and
record the voltage at which the relay operated. The voltage should be with in
± 10% of the relay setting voltage.
5) Take the MVTP relay out from the case.
6) Increase the primary current slowly till the MCAG-14 operates, the primary
operating current and the relay current should noted .The voltage at which the
relay operates should be with in ± 10% of the relay setting voltage VR.
7) Note down all the readings from the meters and record it.
8) Turn off the kit and compare the readings with Expected Primary operating
Current as per the Setting calculation.
9) Repeat the steps 4, 5, 6 & 7 for Y & B CT phases and for the check Zone also.
10) Open the first Bus dis-connector & close the second one
11) Repeat all the steps for BBP Zone 2 for all phases.
12) Repeat all above steps for the other bays.
BBP STABILITY TEST
Stability test is carried out to prove that the scheme is stable during through faults & the
current transformers are correctly connected.
The stability of the BBP scheme can be checked using the circuit shown in the following
figure.
31/43
1) Close the first Bus dis-connector.
2) Select one of the bays as reference.
3) Prepare the multi meter connection for Voltage across Metrosil, , and MCAG
relay coil and prepare the ammeter for the MCAG relay current .
4) Turn on the Power to Kit, increase the primary current up to 50 % of the rated
current of the CT, confirm that the spill current is very low (only few
microamps/milliamps) and no operation for the BBP relay , record the primary
current , metrosil voltage& record the secondary phase current for both
bays(reference and the tested bays).
5) Turn off the kit and Open the first Bus dis-connector & close the second one.
6) Repeat the steps 2, 3 & 4 for BBP Zone 2.
7) Repeat all the above steps for Y & B CT phases.
8) Repeat all the above steps for other bays. Note that each time you are shifting
to next bay to test it; you have to select the previous tested one as reference
bay.
2) Prepare the multi meter connection for Voltage across Metrosil, Stab Resistor,
and MCAG 34 relay coil and prepare the ammeter for the MCAG relay
current.
3) Turn on the Power to Kit, increase the primary current up to 50 % of the rated
current of the CT, confirm that the spill current is very low (only few
32/43
microamps/milliamps) and no operation for the BBP relay , record the primary
current , metrosil voltage& record the secondary phase current for both bays.
4) During current injection close the second bus disconnector Q2 of the first bay,
confirm that the spill current is still very low.
5) Note down all the readings from the meters and record it.
6) Open the bus disconnector Q1 for the same bay (first one). Confirm that the
spill current is still very low, record the reading from the meters.
33/43
7) Close the second bus disconnector Q2 of the second bay; confirm that the spill
current is still very low.
8) Open the bus disconnector Q1 for the same bay (second one). Confirm that the
spill current is still very low, record the reading from the meters.
9) Repeat the load transfer sequence again for the same bays to transfer from Q2
to Q1 as the starting point. In each step we have to confirm that the spill
current is still very low.
10) Make the current zero and turn off the kit.
11) Repeat the step from 3 to 9 for Y & B phases.
12) Select another two bays and repeat all the above steps. Testing should be
carried on for all the bays.
34/43
1.7 TEST PROCEDURE FOR DISTANCE END TO END TEST
This procedure is applicable for each of the line feeders with test carried out individually.
1. Check the final setting is incorporated at both ends.
2. Ensure CBs at both ends are closed.
3. Initiate Zone 1 or Zone 2 fault at local end
4. Check the following:
a) Signal send LED at local end
b) Signal receive LED at remote end.
VTS Blocking
1. trip the VT MCB at local end , check VTS LED in the relay is lit up .
2. Apply a zone 1 or zone 2 fault No trip is observed.
3. Repeat the same at remote end.
35/43
1.8 TEST PROCEDURE FOR LINE DIFFERENTIAL PROTECTION END TO
END TEST
This test verifies that the relays at the both ends are communicating with each other
properly. The test will be carried on after adapting the final setting at the both ends.
Before starting the test confirm that there is no communication failure alarm.
2. Measure and record the optical power of the Channel 1 transmit port using the
optical power meter and length of optical fiber. The mean value should be in the
range –16.8dBm to 22.8dBm for an 850nm port and in the range -7dBm to -
13dBm for either a 1300nm or 1550nm port.
3. Repeat for Channel 2 transmit port (if applicable).
4. Remove TX core from the local end and confirm the following:
• Alarm on relay after 10sec
• Output contact of the relay closed after 10sec
• Alarm on remote end
5. Reconnect the TX core & remove RX, confirm the above points.
6. Repeat the same for Channel two.
Ensure that all transmit (Tx) and receive (Rx) optical fibers are reconnected to the P543,
ensuring correct placement.
Reset any alarm indications and check that no further communications failure alarms are
raised. Check channel status and propagation delays in [MEASUREMENTS 4].
Clear the statistics and record the number of valid messages and the number of error
messages after a minimum period of 1 hour. Check that the ratio of error/good messages
–4
is better than 10 .
Metering Check:
The inspector has to check the metering element by applying current and record the
instrument display (Local , remote , differential & Bias currents).
36/43
Injection current & checking the metering element should be done from the remote end
also.
This test verifies that the sensitivity of the relay pick-up is within the acceptable
tolerance.
Inject current less than ‘I threshold’ value onto one phase each time, slowly increase the
current until the relay picked up, record the value.
Checking the operation of the relay during lose one of communication channel.
If two communication channels are used, the operation performance of the relay should
be checked during lose of one of communication channel.
37/43
1.9 ON LOAD TEST PROCEDURE FOR DEF
This procedure is applicable for each of the line feeders with test carried out at each end
individually.
This procedure is applicable for each of the line feeders with test carried out individually.
To confirm the relay operation, only one phase current should go through the relay at a
time with VT connection normal, the test must be repeated for each phase.
The load direction should be determined before starting the test.
1. Remove Trip links for F67, F67N.
2. Short –circuit the CTs of the two phases on the test terminal block in protection
panel (Y & B phases)
3. Verify the power flow directional with the system load flow.
4. Insert the test plug for normal CT connection for R phase
5. If the load in forward direction the relay is going to operate if the current exceed
the threshold values other wise reduce the relay setting to be smaller than the load
current.
6. Remove the test plug.
7. Arrange the test plug for reverse CT connection.
8. Insert the test plug.
9. Perform the test with reverse CT connection.
10. Remove the test plug.
38/43
11. Repeat the testing steps from 2 to 9 for other phases
12. Normalize the relay setting
13. After test finished, all links /relay setting should be normalized.
1. Confirm that the external wiring to the current & voltage input is correct
2. Ensure that the on load differential current is well below the relay setting.
3. Confirm the stable & unstable condition of the protection under load current.
4. Prove the operation of the relay with the actual load current.
Method statement: -
1. Remove Trip links for F87.
2. Remove Trip links for Trip relays, inter tripping & direct tripping.
3. With the load current record the relay measurements at normal condition.
4. Short –circuit the CTs of the two phases on the test plug in protection panel (Y &
B phases), put only neutral and red phase through.
5. Verify the power flow directional with the system load flow.
6. Insert the test plug for normal CT connection for R phase at both ends (local &
remote).
7. Note the differential and bias current for the red phase; check that the relay
measurements are as expected and that the Diff current is similar to the value of
the capacitive charging current previously measured.
8. On the test plug at one end reverse the connection of the red phase. Insert the test
plug; note the Diff & Bias current R phase if the load is high enough relay should
trip.
Repeat the above test for other two phases.
Confirm proper measurements of the relay and fill it up in the test sheet. Confirm power
flow direction with Load Dispatch Center and verify P & Q signs, also verify all the six
impedance measurements have proper signs.
Change setting for star point (towards bus/towards line) and verify that the signs for P &
Q are changing.
Before star the load test trip isolation link should be removed, the test should not be done
simultaneously in both substations.
39/43
Prepare test plug with ‘Y’ & ‘B’ currents shorted and ‘R’ phase current with normal
connection in order to get zero sequence current in forward direction.
If the power flow was in reverse direction, Prepare test plug with ‘Y’ & ‘B’ currents
shorted and ‘R’ phase current with reverse connection in order to get zero sequence
current in forward direction.
Then: -
• Insert the test plug
• Remove the ‘R’ phase voltage from test plug (open link 7-8 on test plug)
• The relay will trip in Zone 1 for the earth fault in R phase , fill up the test sheet.
• Normalize the voltage, reset the relay & reverse the ‘R’ phase current.
• Remove the R phase voltage, Relay will trip in Zone3- reverse reach, confirm the
carrier send output operation.
• Fill the test sheet.
• Repeat the above test for all phases.
40/43
Appendix-1
Test formats index
Sl
Title Reference
No.
1 11kv C.T. Test Reports- Incomer Feeder Incomer Feeder
41/43
Title File Ref. no.
Un Balancing relay –P122 P122
42/43
43/43